Tasks to be completed when documenting an operation (from creation to publication)
1. Enter the Title of the operation / page
2. Add the following Labels:
Scope of applicability: ww, country_accounting
Country or group of countries (if applicable): belux, china, france, italy, lam, nam,uk_ie, bulgaria, dach, netherlands, iberia, poland, latvia, australia, india, japan, south_korea, thailand, singapore, new_zealand, emea_transversal, apac_transversal
Unit and Domain according to the List of labels to be used in the Finance Service Line space
- E.g. 1: WW Operation in Financial Accounting under domain "Central Finance Processes & Compliance":
- Labels to be used: ww, financial_accounting, central_fin_proc_compliance
- Labels to be used: ww, financial_accounting, central_fin_proc_compliance
- E.g. 2: France Operation in Financial Accounting:
- Labels to be used: country_accounting, france, financial_accounting
(for country operations, the Domain is always country_accounting)
- Labels to be used: country_accounting, france, financial_accounting
- E.g. 1: WW Operation in Financial Accounting under domain "Central Finance Processes & Compliance":
3. Fill in all fields as described above
4. Name the title of each section using OPD methodology naming convention - Infinitive verb without the “to”, mainly action verb...something) -" I do something..."
5. Once the description of the operation is completed, ensure it is approved and published by launching the GBS-Finance approval workflow
Domain: Investments & Divestments
Responsibility area: Control GBS IS Projects
1. Objective and Scope
1.1. Objective of this Operation
Provide the updated list of networks available for GBS IS projects to the GBS IS Controllers
1.2. Scope
The scope of List of Networks Available Report is for all legal entities in PF2.
2. Definitions
See Finance Glossary:
3. Tasks description
3.1. I extract the Networks available from SAP PF2
3.1.1. Run the transaction ZZJ20
- Enter the selection of the network : from 6000000 to 9999999
- Select the fields:
- WBS element status active
- Network status active
- Exclude blocked WBS or Network
- Include activities in result?
- Select : Download excel file and put where the excel file will be saved automatically
The excel file will be saved in the directory noticed in field "File path"
- Click on Execute (or F8)
3.1.2. Download from Google drive the last version of the List of networks available report
- Change the date in the file name
- Open the file
3.2. I perform the necessary consistency checks
- Unhide the tab "Networks activities detail" and past the extraction made in the point 3.1.1.
- In the columns K "Project Type" and L "Stream" : update the tab "Matrix" with data using a VLOOKUP with the "Project Type" (OTC or CAPEX) and with the IT Stream (use the column F-Team Leader of WBS Element request file)
- Be sure to eliminate the companies deleted from the system
- In columns O and P, check if the project code indicated in the WBS description and Network description match the project group in column A. If not, you need to validate what is the correct information and update in the system by using CJ20N transaction and update also in the file, so there will not appear "NOK"s in the Test columns.
In tab "Recurrent activities" : update the pivot table with the following filter:
In tab "Networks-projects available" : update the pivot table by removing the rows without Group code
- Hide the tabs "Networks activities detail" and "Matrix"
Save the file
3.3. I upload the Networks Available report into Google drive
Upload the Networks Available report into Google drive in the correct year and month folder and convert the file to google sheets format.
3.4. I share the Networks Available report with IS Controllers


