The cycle and the segment in which the cost center is included can be found by clicking .
On Environment
Then "Where-used List"
and
Cycles in CO-OM : for assessment from sender Cost Center to receiver Cost Center/Order/Cost object /WBS
Cycles in CO-PA : for assessment from sender Cost Center to Profitability Analysis Value Fields (that corresponds to P&L BFC headings)
STEP 5
The cycle and segment in which the cost center is included is displayed.
STEP 6
Obtain other information thanks to a double click on "SenderSet" in the column Usage.
STEP 7
Obtain the plant code and the receiver IECRA.
Ensure you are in the tab "Senders/Receivers"
Use the arrow to go down.
You will find in the list of information Plant code and IECRA.
STEP 8
Select now the tab Segment Header to obtain
The assessment cost element or allocation structure
Value field
Sender value (that display allocation rule and the amount or the % allocate through the allocation process)
STEP 9