There are different clearing possibilities for this transaction: 




Tasks to be completed when documenting an SAP Transaction, Report or Message code.

1. Title of the page = SAP Transaction code, SAP Report or SAP Message

2. Add the following Labels, respectively:

    • SAP Transaction => "sap_transaction", Transaction code "xxxx"

    • SAP Report => "sap_report"

    • SAP Message => "sap_msg"

3. On the left section, describe the steps. On the right section, insert respective print screens and additional guidelines, if needed (e.g. Main selections of the transaction...)


STEP 1


Go to transaction MM01

MM01 - Create Material: Initial Screen

  1.  Insert the material number

    and 




STEP 2


Select Views Accounting 1 and 2 & Costing 1 and 2







STEP 3


Enter the plant code 

and 




STEP 4


 Creation of the Accounting 1 (mandatory fields are marked with *)


Fill the following fields:


  1. Valuation Class *

  2. Valuation Category - To be used only in the cases where we need to create a specific view "Produced" or "Purchased"

  3. ML active *

  4. Price Determination

    - 2 (Transaction-Based)
    - 3 (Single-/Multilevel)

  5. Price Control *

    - S (Standard price )

    - V (Moving average price)

  6. Price Unit

    - By default the unit used is 1000

  7. Per unit Price (Moving average Price MAP)


and 



Fill the following fields::


  1. Valuation Class *

  2. Valuation Category (not relevant for WP1)

  3. ML active (only relevant for the companies using ML - Brazil + Korea)

  4. Price Determination (only relevant for the plants with ML active. For all the others it should be kept blank)

    - 2 (Transaction-Based)
    - 3 (Single-/Multilevel)
  5. Price Control *

    - S (Standard price )

    - V (Moving average price)

  6. Price Unit

    - By default the unit used is 1000

  7. Per unit Price (Moving average Price MAP)


and 




STEP 5

Creation of Accounting 2


  1. Commercial Price 1

and 


  •         Note: This field is only used for WP1 materials




STEP 6


Creation of Costing 1 (mandatory fields are marked with *)


Fill the following fields:


  1. Do not cost - Normally this field is flagged only for materials with Valuation class Z101

  2. With Qty Structure & Material Origin *

  3. Variance Key - (not relevant for PF1)

  4. Profit Center * 

    In case it's not given by the controller, please check the rules below to suggest the PC to the controller



    STEP 1

    Log is in English to start with the creation of the profit center in English. 




     

     

     

    Start the transaction using the menu path or transaction code 

     

     


    STEP 2

    Enter the code of the profit center and enter



  5. Special Procurement Costing

  6. Plant -sp -material status - If necessary to block the material for some reason


and 



Fill the following fields:


  1. Do not cost - Only when requested

  2. With Qty Structure & Material Origin *

  3. Variance Key - Mandatory to use Z_Z001 for all finished goods produced

  4. Profit Center * 

    In case it's not given by the controller, please check the rules below to suggest the PC to the controller



    STEP 1

    Log is in English to start with the creation of the profit center in English. 




     

     

     

    Start the transaction using the menu path or transaction code 

     

     


    STEP 2

    Enter the code of the profit center and enter



  5. Special Procurement Costing

  6. Plant -sp -material status - Make sure that the status "Z1" is applied until the Std Price is released


and 




STEP 7


Creation of Costing 2


  1.  Planned Price 

and 


  •        Note: This field is only used for PF1 materials



Then save 


See different possibilities for this transaction:



STEP 1

Start the transaction using the menu path or transaction code MM02

Double-click 



 

Create Material : Initial Screen

 

 


STEP 2

Enter the material code

and 

 

 


STEP 3

Select the view to be updated

and 

 

 


STEP 4

Enter the plant code 

and 


 

 

 


STEP 5

Perform the changes and save 

  • A message confirms the change 

 

 


STEP 1

  • Use transaction MM02
  • Enter the material code and 

 

 

 

 

 


STEP 2

  • Select the view "Costing 1" and 

 

 


STEP 3

  1. Enter the plant code and 
  2. If there is a warning message "Deletion flag is set at client level" you can skip it and click 

 

 

 


STEP 4

  • Enter the status Z0 in the field Plant-sp.matl status and save 
  • A message confirms the change 

 

 

 


STEP 1

  • Use transaction MM02
  • Enter the material code and 

 

 

 

 


STEP 2

  • Select the view "Costing 1" and 

 

 


STEP 3

  • Enter the plant code and 

 

 

 


STEP 4

  • Enter the status Z1 in the field Plant-sp.matl status and save 
  • A message confirms the change 

 

 

 


STEP 1

  • Use transaction MM02
  • Enter the material code and 

 

 

 

 


STEP 2

  • Select the view "Costing 1" and 

 

 


STEP 3

  • Enter the plant code and 

 

 

 


STEP 4

  • Remove the status Z1 in the field Plant-sp.matl status and save 
  • A message confirms the change 

 

 

 

See different possibilities for this transaction:



STEP 1

  • Use transaction MM03
  • Click  to display the organization level and click  beside the plant code
  • The list of plants is displayed => The material code 92618 exists in 5 plants
  • If the material 92618 is not produced in the plant 7777 is can be procured externally or in another plant in WP1 listed below : 
    • 7512 ZFR3 Clamecy
    • 7622 ZFR3 Collonges
    • 7714 7418 / Nippon Express - AOMI
    • 7806 7418 / Nippon Express Yamashit

 

 


STEP 2

  • The existing procurement code C3 should be removed or replaced as it refers to a plant 7605 Incheon in which the material code 92618 was not created 

 


STEP 1
  • Use transaction MM03
  • Enter the material code and 

 

 

 


STEP 2

  • Select the view "Costing 2" and 

 

 


STEP 3

  • Enter the plant code and 

 

 


STEP 4

  • When the cost estimate is marked, it becomes the Future Cost estimate

 

 

 


STEP 5

  • When the cost estimate is released, it becomes the Current Cost estimate

 


STEP 1
  • Use transaction MM03
  • Enter the material code and 

 

 

 

 


STEP 2

  • Select the view "MRP2" and 

 

 


STEP 3

  • Enter the plant code and 

 

 


STEP 4

  • The special procurement code is C3

 

 

 


STEP 5

  • Click on the code and  to have the description of the code 
  • The code C3 means that the material 92618 comes from the plant 7605 Incheon

 


STEP 1
  • Use transaction MM03
  • Enter the material code and   

 

 


STEP 2

  • Select the view "Basic data 1" and 

 

 


STEP 3

  • The division code is TN

 

 


STEP 4

  • Click on the code and  to have the description of the code 
  • The code TN means that the material 110778 is included in a group of similar products "GAS STIMUL SURF [WB]"

 

 

 

 


STEP 1

Display the material master data of any code with MM03 and select its sales organization)

 

 

 


STEP 2

Click on the Sales org 2

 

 

 

 

 


STEP 1

Display the material master data of any code with MM03 and click on 

 

 


STEP 2

Click on the button beside the plant code

 

 

 


STEP 3

Click on the button beside any plant code

 

 

 


STEP 4

Fill possible entries depending on your need

 

 

 


STEP 5

 

The plant type of 7703 is NDIR