I calculate the standard hourly rate 

Process: Product Costing

Responsibility area: Manage product costing



Scope

 
Scope

WP2
Frequency

      
References


Attachments

IAC 01.01 Costing Model.xlsx 

IAC 01.01 Costing Model_366 days.xlsx

OP.026  << I calculate the standard hourly rate >> IAC 01.01. Costing model validation



  Guideline  

I am informed that the budget cycles was executed without error.


STEP 1

Start the transaction KSPI 

  1. Enter the cost center group PPPP-1
  2. Enter the period
  3. Run the transaction in test mode 

Execute 








STEP 2

The result of the calculation is displayed

  1. List of production cost centers
  2. List of activity types
  3. Unit price calculated 



Choose layout :

1SAP03  <-> Price in Object Currency For other currencies different from EUR




STEP 3

 

As the price was calculated in test mode, the system asks if you want to post the results.

Click on , only if the result was correct.






STEP 4

A message confirms that the price was posted





STEP 1

Check the activity rates with the transaction KSBT 

  1. Enter the cost center group:
       
       For PF2 same as in KSII
       For WP2 PPPP-1

  2. Enter a range of activity types (for PF2)

  3. Enter the version ‘0’

  4. Enter the Fiscal Year and the Period

  5. Enter price unit 1000

  6. Mark ‘display only activity prices used for allocations‘


      Execute 




STEP 2

For PF1:

The reports shows the actual and the planned activity price per cost center in 2 different lines:

In the last column the price indicator ‘PrI’ represents:

                    ‘3’ = planned price

                    ‘5’ = actual price

 

For WP1:

A report is displayed with the list of activity rates



I control the result and inform the FRA.

I also inform the person in charge of product costing

 

2 Comments

  1. The "Next Operations: OP44" has not the correct link.

  2. KSPI is for Plan price calculation for Cost center group. What is t-code  to perform single Cost center?