High- Level Specification
| Parameter | Value |
|---|---|
| Application System | SAP S/4HANA ROW, SAP S/4HANA China, SAP S/4HANA CUI |
| Business Process Reference | 07.05.02.01. Perform Asset Maintenance Planning |
Functional Overview
The purpose of this enhancement is to introduce a validation and logic control during the creation of Settlement Rules in Plant Maintenance Orders.
Settlement rules are created automatically in line with standard SAP functionality, based on the Order Type configuration and assigned Settlement Profile. For Turnaround scenarios, the settlement should go to the WBS Element associated with the Turnaround event.
The enhancement will trigger at the moment of Settlement Rule creation (not necessarily during Order Release), check whether the Maintenance Order is part of a Turnaround (via Revision/Maintenance Event field), and assign the correct receiver type accordingly.
Scope and Objectives
Enhancement of Settlement Rule creation logic in PM Orders.
Automatic determination of WBS element for Turnaround-related orders.
Preserve standard settlement functionality for all non-Turnaround orders (no impact or modification in this case).
To ensure correct and automated determination of the appropriate settlement receiver (WBS element for Turnaround scenarios), while all other PM orders follow the standard settlement rule logic, maintaining compliance with project cost accounting principles.
Process Flow Diagram
Step | Description | Comment |
|---|---|---|
| 1 | User creates a Maintenance Order or opens an existing active order. | |
| 2 | User opens the Cost tab → manually triggers Settlement Rule Creation or triggers Settlement Rule via releasing the order. | |
| 3 | System calls Enhancement (User Exit). | |
| 4 | Settlement Rule created accordingly. |
|
| 5 | Order costs will settle correctly. |
Assumptions
Y3 Notification Type is available and configured in the system.
- Maintenance Orders will be released exclusively via the Fiori applications.
Relevant users have Fiori app access (Change Maintenance Order).
Each Turnaround Order has at least one Maintenance Event/Revision assigned.
Notifications with the same Maintenance Event/Revision contain the correct WBS element to be used for settlement.
Standard SAP PM settlement logic is assumed to be functioning correctly for non-turnaround orders.
Users creating Maintenance Orders have appropriate authorization for reading Notifications and WBS Elements.
Dependencies
Fiori app configuration for Notifications and Orders.
Y3 Notification must have WBS Element assigned.
- Y3 Notification Type is configured.
- To prevent creation of multiple Y3 Notifications for the same Maintenance Event, an enhancement will be implemented under “ERP-349 - UI Extensions in Create Maintenance Notification App.” This enhancement will ensure control and validation during Notification creation.
BADI implementation must be activated in the system for Settlement Rule enhancement.
Integration with PS module (for WBS Element retrieval) must be in place.
Other custom developments interacting with Tables AFIH, VIQMEL, or Settlement Rules must not conflict with this logic.
Security, Integrity and Controls
The enhancement will follow the SAP standard security and authorization framework to ensure data integrity and controlled access during the creation of Settlement Rules in Maintenance Orders.
Configuration Requirements
Not Applicable
Language Requirements
Not Applicable
Special Requirements
Ensure performance is not impacted when processing large numbers of Orders or Notifications.
If future integrations consume WBS or settlement data, ensure compliance with their data structure and format.
Design Rationale
Functional Requirements
Check Order:
Validate if the order is PM Order (Table-Field): AUFK-AUTYP.
- Check if the Maintenance Event/Revision (Field: REVNR) field is filled in the order (Table: AFIH).
Retrieve Maintenance Event:
If Maintenance Event/Revision (Field: REVNR) exists, go to the Notification (Table: VIQMEL) and populate Y3 Notification Type (Field: QMART) with the Maintenance Event/Revision (Field: REVNR) value from the order.
Identify WBS Element:
For the maintenance notification matching this Maintenance Event/Revision (Field: REVNR), retrieve the associated WBS element (Field: PROID).
Settlement Rule Creation:
For all orders with this Maintenance Event/Revision, create settlement rule to the retrieved WBS element.
If no Maintenance Event/Revision (Field: REVNR) is found, continue with the standard settlement rule logic.
Proposed Technology to Use
| Component | Details |
|---|---|
| Enhancement Type | User Exit Implementation |
| User Exit | IWO10027 – Generate user-defined settlement rule |
When the system starts creating a settlement rule for an order, the exit IWO10027 is called.
Data Source Considerations
| Table | Field Name | Comments/Calculation/Field Manipulation |
|---|---|---|
| AFIH | AUFNR, REVNR | Maintenance Event assigned to the order. |
| VIQMEL | QMART, REVNR, PROID | Used to identify if there is a notification of type ‘Y3’ linked to the same Maintenance Event. If yes, PROID (WBS Element) is used as the settlement receiver. |
Data Validation Considerations
| Table | Field Name | Comments/Calculation/Field Manipulation |
|---|---|---|
| AFIH | REVNR | Validate that the Maintenance Event field is not empty before proceeding to check in VIQMEL. |
| VIQMEL | QMART | Validate that QMART = ‘Y3’ |
| VIQMEL | PROID | Validate that PROID (WBS Element) is filled for the identified notification; if missing, continue with the standard settlement rule logic. |
Custom Tables
Not Applicable
Master Data
Not Applicable
Configuration Table
Not Applicable
Selection Screen Enhancement
Not Applicable
Processing Logic
Trigger Point:
Enhancement is triggered when the system attempts to create a settlement rule for a maintenance order.
- The exit IWO10027 is called.
- Validate Order Type:
- Check CAUFVD_IMP-AUTYP = ''30'' (Maintenance Order)
If not, exit enhancement.
- Check CAUFVD_IMP-AUTYP = ''30'' (Maintenance Order)
Check Maintenance Event:
- Check CAUFVD_IMP-REVNR
If REVNR = '' '', exit enhancement.
- Check CAUFVD_IMP-REVNR
Check Related Notification:
If REVNR is filled, check table VIQMEL for any notification where:
QMART = 'Y3'
REVNR = <CAUFVD_IMP-REVNR>
Determine Settlement Receiver:
If such a notification exists:
Read PROID (WBS element) from the notification.
Create settlement rule for WBS element.
- ZXWOCU24
pmdfu_tab-konty = 'PR'.
pmdfu_tab-fdind = 'VIQMEL-PROID'.
pmdfu_tab-perbz = 'GES'.
pmdfu_tab-prozs = 100.
APPEND pmdfu_tab
If no matching notification found:
Continue with standard SAP settlement rule logic.
For the Change Parameter: APROF (Parameter Name)
Use Existing Profile (YEAM02):
The existing settlement rule profile YEAM02 can be retained. In this case, no profile change is required.
Within the settlement rule profile configuration, ensure that WBS Element is defined as an ''optional'' receiver under the Valid Receivers section.
Validation Checks:
Ensure WBS element or Cost Center is valid and open for posting.
Volumetrics
Not Applicable
Performance Considerations
Not Applicable
Error Handling
No Error Handling Needed.
Testing
How to Test
Unit testing should be performed during settlement rule creation for maintenance orders to validate the enhancement logic implemented in User Exit IWO10027 (Generate user-defined settlement rule). The tester should create or use existing maintenance orders under different scenarios to confirm that settlement rules are correctly assigned to WBS elements or Cost Centers according to the defined logic.
Test Conditions and Expected Results
| ID | Condition | Expected Result |
|---|---|---|
| 1 | Order with Maintenance Event/Revision and there is a valid Y3 notification with the same Maintenance Event/Revision. | System creates settlement rule for WBS Element (VIQMEL-PROID) |
| 2 | Order with Maintenance Event but Y3 notification missing WBS element. | System continues with standard settlement rule logic. |
| 3 | Order without Maintenance Event/Revision. | System continues with standard settlement rule logic. |
| 4 | Order with Maintenance Event/Revision but there is no Y3 notification with the same Maintenance Event/Revision. | System continues with standard settlement rule logic. |
Test Considerations/Dependencies
This enhancement depends on the implementation of User Exit IWO10027 – Generate user-defined settlement rule.
Data validation relies on correct entries in tables AFIH (REVNR), VIQMEL (QMART, REVNR, PROID).
Ensure master data such as Cost Centers and WBS Elements are valid and open for posting in the test environment.
To prevent creation of multiple Y3 notifications for the same Maintenance Event, a separate enhancement under “ERP-98 – UI Extensions in Create Maintenance Notification App” will provide additional control and validation.
Testing should be executed in both standalone order creation and integrated Turnaround scenarios to confirm system behavior consistency.
Ensure proper authorizations exist for testers to create and edit orders, notifications, and settlement rules.
Other Information
Not Applicable.
Development Details
Package
| Package Name | Parent Package |
|---|---|
Enhancement Implementation
| Enhancement Type | Standard Definition Name | Custom Implementation Name | Design Rationale Reference |
|---|---|---|---|
Other Development Objects
| Object Type | Object Name | Purpose/High Level Logic | Design Rationale Reference |
|---|---|---|---|
Appendix
Custom Authorization Group Naming Convention
This table is based on the Syensqo development standards document. It provides the naming conventions for authorization groups to associated with custom reports and tables to comply with security requirements.
ABAP | ZFI | ZMM | ZPS | ZCO | ZSD | ZBC | ZFI | ZCA |
|---|---|---|---|---|---|---|---|---|
| TABLES | ZFIT | ZMMT | ZPST | ZCOT | ZSDT | ZBCT | ZFIT | ZCAT |