Page tree

Term

Definition

Comment

SHS

Stock Holding Strategy (MTO / MTS / MTF).

MTF will be considered as MTS (simplification).

More info in P&I Wiki section: P&I Wiki: SHS

Monolevel RLT

Represents the total time between placing a production / replenishment order and the availability date. 

It’s “monolevel” since it only considers the product’s own lead times (scheduling / production lead time / ….) , does not consider other BOM level.

Monolevel and Independent of SHS

More info in P&I Wiki section: P&I Wiki: Monolevel RLT / SHS RLT

SHS RLT

Represents the total time between placing a production / replenishment order and the availability date.

It considers other BOM levels lead times (multi level) + distribution network (multi sites) and stock holding strategies.

Multilevel LT and SHS dependent

P&I Wiki: Monolevel RLT / SHS RLT

Catalog LT 

Promised LT to Customer (as defined by Solvay, not by Market). It’s part of ‘Product mix’. It’s a ‘Solvay’ Catalog LT, agreement between Supply Chain and Market team.
Difference between SO creation date and reference date (GI date or Avail date, to be defined, most probably: Avail date).

It’s value is defined during P&I process.

Also used in CEM Sales order entry control.

More information in P&I Wiki section: Catalog LT

SAP TRLT 

Name of SAP Field which contains data for ATP check. Use always this term to avoid confusion and if possible avoid to use “TRLT” instead of “SAP TRLT”

More information in P&I Wiki: SAP Leadtimes

For DiP-PP glossary (which includes P&I terms), please refer to the section: DynaSys - Glossary

The best way to get IT support is to use the new Service One Platform.