Status colour Blue title Step 1
To update the settlement rule of project to cost center, go to CJ02 and insert the code of project.
Status colour Blue title Step 2
Select the line related to project and click on
Status colour Blue title Step 3
Click on “New rule (F9)” and change the field “Valid to” to previous period.
Status colour Blue title Step 4
Go back to the previous screen and click on the menu “Goto”, “Settlement parameters”, and insert the code “ZPS10” in the field of Settlement profile and the code “BE” in the field of Allocation structure
Status colour Blue title Step 5
Change the “Settlement profile” to ZPS10 and “Allocation structure” to BE.
Status colour Blue title Step 6
Go back to the previous screen and click on “New rule (F9)” or go to the menu Edit, New rule.
Status colour Blue title Step 7
Inform the new Cost center and the “Valid from” to the period the project should start being settled using the new settlement rule.
Number: New settlement rule number (sequencial).
Settlement type: PER
Percent: if 100% or less
Status colour Blue title Step 8
Go back to the previous and now, you should find the two settlement rules
Go back to the previous screen and save it