By default, all indicators are available in the report in number of days :

Lead Time

Request

request : this is the approval lead time based on the request date (Approval date end minus Approval request date).

Lead time transferred date: this is the approval lead time

further to

based on a transfer of validation ( Approval date end minus the Approval transferred date).

Lead Time

Conditional

conditional : if no transfer of validation is done, the Lead Time conditional is equal to the Lead Time request.

Lead time date: 

1) if no transfer of validation is done, then

 Approval

this indicator shows the duration of the approval process based on the beginning of the approval workflow (Approval Date end minus the Approval date start).

2)

If

In case of transfer of validation :

 Approval

the indicator shows the duration of the approval process based on the date of transfer (Approval date end minus Approval transferred date).

Image Modified