Status colour Blue title Step 1
Analyse the document sent.
If there is any AUC in column "Settlement Receiver" it should be deleted because it will be fulfilled automatically by the transaction.
Image Added
Status colour Blue title Step 2
Enter transaction ZZJ02.
Image Modified
Status colour Blue title Step 23
Deselect the field “Release Project”.

Status colour Blue title Step 34
In the "File name" field, upload the Excel file received ( see template SBS-FRM-DRTR-02-019 - R&D Project Creation Template.xlsx).
Image Added
Image Removed
Status colour Blue title Step 4 5
Click on the ''Execute''
Image Removed Image Added in order to get to the following screen.
The information that is available on the chosen Excel file, is not displayed.
| Info |
|---|
The first 4 columns stand for: P: Project / W: WBS / S: Settlement rule /R: Release |
Image Modified
Status colour Blue title Step 5
The The "Release" column column can have 4 different status:
| Ready to be created | |
| Created | |
| Error in creation | |
| Completed |
Image Removed
Status colour Blue title Step 6
Select one or several lines and click on
Image Removed
Image Added in order to create a new project.
Image Added
Image Removed
Status colour Blue title Step 7
Click on ''OK'' when the warning message pops-up.
Image Added
Image Removed
Status colour Blue title Step 8
If no errors will be found, a similar screen will be displayed.
Click on
to continue.
Image Modified
The project created will show a flag
Image Added in columns P, W and S.