1/ Definition
The indicator shows the rate of available
workload scheduled resources during the last week.
2/ Objective / Target
The objective is to show the amount of resources we are scheduling
in order to know
which are the resources
allocated to planned works. One of the biggest interests is to compare this indicator face to the
schedule compliance. Comparing both of them we can find the good level of resources to be scheduled. This indicator may also show us the accuracy of
our planning process in
time estimation.
Example of a good target (Benchmark SolMaX): 80%
3/ Formula
| % available resource scheduled : [ ( ∑ scheduled workload for the last week (remaining work in hours)) / (available resource workload for the last week (capacity in hours) ) |
|---|
| ] x 100 |
|---|
4/ Frequency
Weekly
5/ SAP extraction and detailed calculation
QlikView layout
Table ZWBWT001 for PF1 / ZWBWT002 for RCS. Those tables are for DT only