You can account losses by phase (operation) in a multi-unit OEE line.

PRE-REQUISITES AND LIMITS:

  • Operations cannot overlap ( this means as soon as an operation starts the previous one has to be finished)
  • Account for a loss can only be done as soon as the phase ends.

PROCEDURE

From the multi-unit Administration page, select the unit where you want to account losses on operations and click on the configuration icon.

...