Materials master data fields for raw material stored in a tank. For a good result of the MRP run, it is important to fill the material master date fields in a logical way: you cannot have conflicts between the fields. example : a maximum lot size lower than the minimum lot size. This small video describe how to manage those fields for a storage in a tank.
FOB delivery with long lead time. This scenario represent a raw material Germany has to receive from Japan. The product is owned by Solvay as soon as the product arrives at the port at Japan.
There are several master data to update to facilitate the supply of raw and pack materials. Most of them are under the responsibility of Procurement but not always well managed. Here under, som trickx and tips to understand the impacts of those master data fields. |
|---|
Settings that impact the material replenishment activities : Contract - info record - source list - quota arrangment