In Solvay,the supply organization is not the same accross all GBU's. Sometimes, the factory have to create the purchase order and send it to the vendor, sometimes, the user needs to create
a purchase requisition but the Purchase order is managed centrally.

At any case, this is procurement team who negotiate with the vendors and create the contracts.

This training material describe how to use the MRP run to define the dates and quantities needed to insure the production planned.

As soon as the stocks are always correct in SAP and the production scheduling well done using MF50, the materials replenishment activities are almost automatics.



Provisioning best practices : This tutorial describe how to manage the raw and pack materials replenishment in an easy way.  As soon as the material master data fields are well updated in MM02 transaction, the calculation of the deliveries needed to insure production is very simple.  This training does not contain how to update master data.  This is included in the production scheduling master data here for PF1 and here for WP1.  The meaning of the fields are the same for both production scheduling and material replenishement 


Materials master data fields for raw material stored in a tank. For a good result of the MRP run, it is important to fill  the material master date fields in a logical way: you cannot have conflicts between the fields. example : a maximum lot size lower than the minimum lot size.  This small video describe how to manage those fields for a storage in a tank.