Page tree

Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.


Embedded Google Drive File
docid1p9fGSEo0NjC-mBIAkoT106-Px-1DcoyjcObRpDr9-Qs



Excerpt
hiddentrue

This application is made for to follow the financial indicators at project level (WBS Element) including

  • CASH Out (Capex and OTC
  • Actual Costs (PEC - Capital Spend)
  • Commitments
  • Budget
  • Planned costs
  • Future costs


Table of Contents
maxLevel1

Children Display

 

General Presentation

The PS Application provides reports that shows the financial indicators areat project level (WBS Element).

The Financial Indicators include :

  • CASH Out (Capex and OTC
  • Actual Costs (PEC - Capital Spend)
  • Commitments
  • Budget
  • Planned costs
  • Future costs

Access

Access to the "PS - Project Costs" Application has to be requested (See Getting an account).

Access is managed at 2 levels, which you will need to precise when requesting the access : 

  • Global Business Unit (GBU) - Note that this is the CLIENT GBU (Not the one responsible for the project, but the one receiving the benefits of the projet).
  • Family of the WBS

Perimeter

Currently the WBP PS Application only contains data coming from the RCS System, so only the legal entities managed in WP1 SAP system will be included in this reportPS - Project Costs  is a set of BW queries on Rhodia legacy (WP1), Solvay legacy (PF1) and Acetow (RHO) area.

Data update

The data is updated daily around ~4 am Paris Time.

Queries

All the queries for the PS Application can be found in the role "PS - Project Costs" (ZR_RCS_CA_M09) :Image Removed

  • BW_QRY_MPR_PS014_0001 - Project costs & Cash out (Core query)

Here are the links to the detailed query documentations :

Key Figures

Simple example

In this example we consider the case where a purchase order with a value of 100$ w/o tax (116$ with tax) was created and assigned on the project.

Expand
titleClick here to see step by step example...

Step 1 - The Purchase Request (PR) is created - There is no cost yet, but there is a commitment.

Image Removed

Step 2 - The PR is approved and the Purchase Order is created. In this case, the amount of the PO will be added into the "Cash Future" as at some point in the future this will have to be paid.

Image Removed

Step 3 - The goods (or service) are received (GR). We received everything, so a value of 100$. The commitments are now 0 (since everyting was received) and the PEC (Actual Cost) is 100$. Nothing has yet been paid for CASH is still 0.

Image Removed

Step 4 - The invoice is received. Total value with tax is 116$. The tax is instantly "recovered" : we will have a CASH of -16$.

 

Image Removed

Step 5 - The invoice is paid. As we pay 116$ but we had a -16$ (Tax recovery) CASH, at the end the CASH is equal to 100$, the amount without tax. The Cash Future becomes 0 as everything was paid.

Image Removed

Definitions

Commitments (Current)

Definition : It’s the current amount of the purchase requests and orders not yet received. Amount is without tax and in local currency. In the purchase order (ME23N) it corresponds to the "To be delivered"  in the PO header :

Image Removed

Calculation : None. Amount comes directly from SAP. You can see the details/documents via the CJI5 transaction

About the Posting date for commitments : For the commitment data, the posting date (and all linked characteristics : year, quarter, month) is based on the expected delivery date of the PO/PR : 

Note: This is the present (previous day or current day) value. It doesn't take into account the period selected in the query prompt (it is not possible to get the commitments at a selected date due to the way SAP manages that data)

PEC

Definition : The PEC (Capital Spend) is the actual costs (received costs). This includes the downpayments. The cost can correspond to :

  • Purchase orders, the reception of services/goods (at GR date)
  • Stock issue : value of the material (at stock issue date)
  • Hours : standard cost defined for each hour.
  • Transfers (from Maintenance orders etc...)
  • Manual entries (CO document) and other adjustments.
  • Downpayments

In the purchase order header this corresponds to the "Delivered" value + Downpayments :

Image Removed

Calculation : None. Data comes directly from RCS and can be checked by transaction CJI6.

Info
titleSplitting the GR & Downpayments

If you want to show separately the downpayments and the actual costs (GR - Goods receipt) you can use the "Key Figure Type" :

Image Removed

Downpayments

Definition : The down-payment is the value of the advanced payments done to the supplier. It is also included in the PEC.

 Image Removed

Calculation : None. The data comes directly from RCS and can be checked by transaction CJI6, or directly on the purchase order history (ME23N).

Cash

Cash (or "Cash Out") is the amount paid (Without tax).

  • If cost is linked to a purchase order, then it's the amount once the invoice has been paid.
  • If cost is not related a purchase order, then it's equal to the PEC (GR).

Formula is  CASH = PEC + Variation of the payables balance. In other words : 

Image Removed

Where :

  • Balance = Amount of all open documents (documents not cleared)
  • FIAP = Payables ledger = Invoices.payments, Excluding Downpayments (as DP are already included in the PEC).
  • FIGL = General ledger = Provisions/GRNI
Note
titleTax Recovery

Due to the way the formula works, between the time where the invoice is received and the time where it is paid, the CASH will show a negative amount equal to the tax value. This is intended. Basically, we consider that the tax is recovered instantly (Negative cash) when the invoice is received. Then the invoice is paid (with tax) and the end cash result is without tax.

 

Simple example (PO - No downpayment)

Expand
titleClick here for simple example...

Step 1 - PR and then PO are created. No costs or payments yet.

Image Removed

Step 2 - Goods/services are received for 100$. PEC, which is getting the data from CO, will show 100$ due to the GR and there will be a FIGL posting of -100$ for the GRNI.

Image Removed

Step 3 - The invoice (116$ with tax) is received. The FIGL GRNI is cleared and there is a new FIAP posting for 116$. PEC + FIGL Posted + FIGL Cleared + FIAP Posted = -16$. This corresponds to the tax value that is "recovered".

Image Removed

Step 4 - The invoice is paid. The FIAP document (invoice) is cleared. At the end FIGL Posted + FIGL Cleared + FIAP Posted + FIGL cleared = 0, so the CASH out is equal to the PEC. 100$ which is the amount without tax.

Image Removed

 

Cash Future (and details)

CASH Future is the amount that at some point will have to be paid. This includes :

  • Amount of PO's not yet received
  • Amount of invoices not yet paid
  • Amount received but yet invoiced.

 

The Cash Future is then split into 2 parts :

Image Removed

  • Cash Due  : amounts that are estimated to be due in the future. This is then split by month : Due M (this month), Due M+1 etc...
  • Cash Overdue : amounts that are estimated to be overdue already. 

Due/Overdue are determined by looking at the Net Due Date of the document. Either the actual one (for invoices), or a estimated one (when there is no invoice yet) :

Info

Purchase Requisitions are not included in the Cash Future (or commitments). Only costs related to a purchase order are included in the Cash Future.

Cash Due and Cash Overdue can be then split into the different types : 

Image Removed

Note
titleEstimated Net Due Date

If the invoice was not received, the future cash period will be based on an estimated Net Due Date. This Net Due date is calculated from the Payment Terms.

If the Payment Term is complex (Multiple payments) or doesnt correspond to the reality (Ex : Payment based on the progress of construction) then the period will be incorrect/irrelevant.

 

Cash Due (Actual or estimated Net due Date is in the future): 

  • Ordered but Receipt Late : Order exists, but no GR or invoice yet and the requested delivery date is in the past. Net due date is calculated based on the requested delivery date + Terms of payment.
  • Ordered,  Receipt in Future : Order exists, but no GR or invoice and the requested delivery date is in the future.Net due date is calculated based on the requested delivery date + Terms of payment.
  • Received : GR is done, but no invoice and the estimated net due date is in the future. Net due date is calculated based on the GR date + Terms of payment..
  • Invoiced : Invoice has been received but not yet cleared. The net due date is coming from the invoice and is a future date.

Cash Overdue (Actual or estimated Net due Date is in the past): 

  • Received : GR is done, but no invoice and the estimated net due date is in the past. Net due date is calculated based on the GR date + Terms of payment..
  • Invoiced : Invoice has been received but not yet cleared. The net due date is coming from the invoice and is a past date. 

The Cash Due can also be split by month :

Image Removed

The period (M for current month, M+1 for next month etc...) is based on the Net Due date. Depending on the case the Net Due date is the actual one from the invoice, or an estimated one based on a date + the payment erms :

Image Removed

 

Hours

Definition : Number of Hours allocated to the WBS. The value associated is included in the PEC.

Calculation : None. The data comes directly from RCS and can be checked in transaction CJI3.

Assigned

It’s the sum of the current received costs (PEC, excluding Downpayments) and to be received costs from purchase orders (Commitment) 

Info
titleTime

Note that if you try to display the Assigned costs by period, the month will represent the posting month for the actual costs and the requested delivery date for the commitments.

 

Budget

Definition : Global authorized amount for the project. The amount is not time-dependant (it's a global amount for the overall duration of the project). Amount is in local currency.

Calculation : None. The data comes directly from RCS and can be checked CJ31.

Info
titleTime

There is normally no time dimension for the budget, but we added Project Start Date in it.

 

Group code PS Budget

Definition : Budget for the PS Group code projects grouping. This is currently mostly used by IT and R&D to allocate an overall budget to multi-company projects. Amount is always in EUR

Calculation : None. The amount comes directly from transaction ZWPST004.

PEC Forecast

Obsolete Key Figure - No longer used.

CASH Forecast

 

Currency conversion

All the PS queries use the same type of currency conversion : 

This means that each document will be converted with the rate available for the posting date of that document.

IE : Documents posted in January will be converted with the January rate, even if you run the report in february.

Depending on the key figure, the "Period" will be different :

  • Budget : the date will be the start of the project (WBS Creation date)
  • Commitments : Rate available at the theoretical reception date if the date is in the past, or current rate if date in the future.
  • Plan : Rate available at the month of the plan data.
  • PEC : Rate available at the reception date.
  • Cash – Payments : Rate available at the invoice reception date.
  • Cash – Down payment : Rate available at the down payment posting date.
  • Cash – Non-Purchase requests (Stocks, Hours) : Rate available at the cost reception date

CASH OUT - About Invoices split by WBS element

In some cases, a Purchase Order (PO) can be assigned to several costing elements (Cost Centers, WBS elements, Orders). 

This happens in two ways :

  • Different items in the PO are assigned to different costing elements (Ex : Item 1 on WBS A, Item 2 on Cost Center B)
  • There is a settlement rule to share the cost of the item (Ex : 40% on WBS A, 60% on Cost center B).

In this case, the GR will be correctly split and the cost assigned to each element but as there will be only one invoice, SAP will not split the value of the invoice (Payable - FIAP) into each assigned element

The result is that by default, the full amount of the invoice will be assigned on the first element found by SAP and the CASH will not reflect the reality.

In order to avoid this, the BW system will split the invoice by WBS/CostCenter/Order in the BW reports.

Case 1 - 1 PO with multiple items assigned to several elements - But 1 single invoice

Image Added

In this case BW will split proportional the amount of the invoice by element. In this example, the CASH will reflect only 115$ on WBS1 even though the full value of the invoice (1160$) is assigned on WBS1 in SAP.

Case 2 - 1 PO with 1 item, 1 settlement rule with 2 objects, 1 invoice

Image Added

BW will split the amount of the invoice based on the settlement ruleObsolete Key Figure - No longer used..

PS Frequenty Asked Questions

What does "PEC" stand for ?

"PEC" is the acronym for the french name "Prise En Charge", which translates into "Bearing of the costs". Meaning the Actual Costs of all goods/services received.

The "PEC" was used for Rhodia Legacy. It is replaced by the wording "Capital Spend".

What does "CAPEX" stand for?

CAPEX stands for Capital Expenditure. It is equal to the CASH (Out) when filtering on investments only.

What does "CASH" stand for ?

CASH is short for "Cash Out", meaning the amount that has been paid (or received for invoicing WBS). It includes both "CAPEX" (Investment Cash Out" and "OTC" (One Time Costs - Non-investment cash out).