Indicates whether, for a specific plant, the material may be used |
| Expand |
|---|
|
In WP1, there are 3 main status that can be used: - 01 Blocked for procment/whse => Mainly used in Brazil. Once accounting & costing views are created, before GBUs validation and the cost estimate is released.
- Z0 Blocked for all => Used when the material code is not used anymore (it is obsolete)
- Z1 Material creation in prog => Used when the creation is in progress (until the cost estimate is released)
The field remains empty once the cost estimate is released. The material code can be used. | Warning |
|---|
The field must always be filled until the cost estimate is released (except in trading plants) : - With the status Z1
- or with the status 01 (used in Brazil)
|
|
Make sure that status "Z1" is applied until the standard price is released
| Info |
|---|
| Only for Brazilian companies, it is necessary to fill the “PLANT-SP.MATL STATUS” field, always with 01. |
...