General Description |
|---|
Number of days to transform a PReq (Purchasing Requisition) into a PO (Purchasing Order)Lead timeDetailsdetails results can be analyzed by:
Date Date Reference: |
KPI Name | Definition |
| |
Lead time to transform a conform Preq into a PO |
# of days between conform PReq Release date vs PO Item Creation date |
:Variation in days between Preq and PO |
1 day
|
Lead time to transform a non conform Preq into a PO | # of days between non confrom PReq Release date vs PO Item Creation date |
:Variation in days between Preq and PO |
Lead time to transform a Preq into a PO | # of days between PReq Release date vs PO Item Creation date |
:Variation in days between Preq and PO | ||
# PO Item with PReq | Number of PO Items with PReq (PReq number <>#)
|
# Conform PReq | Numbers of PReq in accordance to the conformity (refers to all mandatory information are filled when creating a purchase request)
|
# Non Conform PReq | Numbers of PReq out of accordance to the conformity (Nom conform)Nom conform refers to either one of these Purchasing Groups is |
equal E02, E03, FQE, N01, N02, N03, N04, N05, N06, N07, N08, N09, N10, N11, N12, N13, N14, N15 (missing of at least 1 mandatory information when creating a purchase request to create a PO). Below is the process of Non conform PREq. |
% Nom Conform PReq |
% Nom Conform PReq
Nb of non-conform Preq | ||
Leadtime by range of days | % of a conform/Non conform Preq transformed into a PO spread by range of days |
| Source Information: BW (WP1 & PF1) |
|---|
Core Query: | BW_QRY_MV_PROVG_0004 |
QV Query: | QVSBS_BW_QRY_MV_PROVG_0001 (PREQ) |
BW Filters | PO Transaction = ME21, ME21N, ME22, ME22N, ME23, ME23N, ME52, ME52N, ME53, ME53N, ME59, ME59N, ZBBP, # |
Core Query:
BW_QRY_MV_PROVG_0004
QV Query:
QVSBS_BW_QRY_MV_PROVG_0001 (PREQ)
Specific Dimensions |
PO Item Created By | |
Capex Flag | For CAPEX (IM), the Project type assigned to the relevant WBS element is: II (Investments) type in WP1.For OPEX (NC), the Project type assigned to the relevant WBS element is OI (Internal Operations) type in WP1 |
PO Category | E-Catalogue : PO Need Origin = 1Ref. Material in Stock : Material <> # + Account assignment code = #Ref. Material non in Stock : Material <> # + Account assignment code <> #Services & Material non Ref. : Material = # |
PO Item Critical | Y/N
|
VIP Supplier | Y/N (Vendor Attribute = VIP Vendor => Y=VIP ; N=#) |
Internal Suppliers | Y/N (Vendor Attribute = Class => Y=G ; N=the rest) |
Purchasing Group | |
Purchasing Organization | |