3. Fill in all fields as described above4. Name the title of each section using OPD methodology naming convention - Infinitive verb without the “to”, mainly action verb...something) - " I do something..."5. Once the description of the operation is completed, ensure it is approved and published by launching theSBSGBS-Finance approval workflow |
| Panel | ||||||||
|---|---|---|---|---|---|---|---|---|
| ||||||||
| Domain: Investments & Divestments |
| Panel | ||||||
|---|---|---|---|---|---|---|
| ||||||
Responsibility area: Control SBS GBS IS Projects |
1. Objective and Scope
1.1. Objective of this Operation
Provide the updated list of networks available for SBS GBS IS projects to the SBS GBS IS Controllers
1.2. Scope
The scope of List of Networks Available Report is for all legal entities in PF1PF2.
2. Definitions
See Finance Glossary:
3. Tasks description
3.1. I extract the Networks available from SAP
PF1PF2
3.1.1. Run the transaction ZZJ20
- Enter the selection of the network : from 6000000 to 9999999
- Select the fields:
- WBS element status active
- Network status active
- Exclude blocked WBS or Network
- Include activities in result?
- Select : Download excel file and put where the excel file will be saved automatically
The excel file will be saved in the directory noticed in field "File path"
- Click on Execute (or F8)
3.1.2. Download from Google drive the last version of the List of networks available report
- Change the date in the file name
- Open the file
3.2. I perform the necessary consistency checks
- Unhide the tab "Networks activities detail" and past the extraction made in the point 3.1.1.
- In the columns K "Project Type" and L "Stream" : update the tab "Matrix" with data using a VLOOKUP with the "Project Type" (OTC or CAPEX) and with the IT Stream (use the column F-Team Leader of WBS Element request file)
- Be sure to eliminate the companies deleted from the system
- In columns O and P, check if the project code indicated in the WBS description and Network description match the project group in column A. If not, you need to validate what is the correct information and update in the system by using CJ20N transaction and update also in the file, so there will not appear "NOK"s in the Test columns.
In tab "Recurrent activities" : update the pivot table with the following filter:
In tab "Networks-projects available" : update the pivot table by removing the rows without Group code
- Hide the tabs "Networks activities detail" and "Matrix"
Save the file
3.3. I upload the Networks Available report into Google drive
Upload the Networks Available report into Google drive in the correct year and month folder and convert the file to google sheets format.
3.4. I share the Networks Available report with IS Controllers
End of document.