Status colour Blue title Step 1
Analyse the document sent.
If there is any AUC in column "Settlement Receiver" it should be deleted because it will be fulfilled automatically by the transaction.
Image Added
Status colour Blue title Step 2
Enter transaction ZZJ02

Status colour Blue title Step 23
Deselect the field “Release Project”.

Status colour Blue title Step 34
In the "File name" field, upload the Excel file received

Status colour Blue title Step 45
Click on the ''Execute'' in order to get to the following screen.
The information that is available on the chosen Excel file, is not displayed.
| Info |
|---|
The first 4 columns stand for: P: Project / W: WBS / S: Settlement rule /R: Release |

The "Release" column can have 4 different status:
| Ready to be created | |
| Created | |
| Error in creation | |
| Completed |
Status colour Blue title Step 56
Select one or several lines and click on
in order to create a new project.

Status colour Blue title Step 67
Click on ''OK'' when the warning message pops-up.

Status colour Blue title Step 78
If no errors will be found, a similar screen will be displayed.
Click on
to continue.

The project created will show a flag
in columns P, W and S.

| Viewtracker | ||
|---|---|---|
|