1/ Definition

Quantity of production lost because of breakdowns or production stoppages caused by maintenance (OEE C2 and C4)

2/ Objective / Target

The set of strategic indicators has three main objectives:
- Verification of the effectiveness of maintenance processes
- Comparisons between plants independently from the business
- Comparisons with external organizations

3/ Formula

Direct impact of maintenance on industrial performance = ( OEE category 2 losses + OEE category 4 losses ) x Economic contribution


Unit
: local currency

Details of the formula: see "5/ SAP extraction and detailed calculation" 

4/ Frequency

Yearly

5/ SAP extraction and detailed calculation

Manual input of OEE losses from production report
(Site template > Yearly tab)

- OEE category 2 losses :
Amount of good product not delivered due to planned maintenance or planned capital installation 

- OEE category 4 losses :
Amount of good product not delivered due to breakdowns

- Economic contribution :
Contribution margin generated per produced unit (in local currency)

 

Causes categoriesSolvay
OEE Losses C22 - Planned Maint.
OEE Losses C44 -  Unplanened Maint.
Theoretical ProductionMaximum demonstrated Capacity (MDC)

 

 

QlikView layout

 

 