Domain: Investments & Divestments
Responsibility area: Control GBS IS Projects
1. Objective and Scope
1.1. Objective of this Operation
Once the GBS IS Projects are approved by all concerned parts, it is needed to create the project structure.
1.2. Scope
The scope of the WBS Elements creation for GBS IS Projects is to all legal entities in Syensqo Group WW.
2. Definitions
3. Open a GBS IS Project Description
All GBS IS Projects need to be approved by all the concerned parts (Responsible Financial Controller and Responsible GBS Manager).
The PPMO committee:
- Defines the Business Case (Project Approval Form) with the project presentation (scope, zone, …)
- Estimates the budget needed for the projects
- Makes a global evaluation of the projects and vote
- Suggests the projects to be developed to get the CIO’s approval
Project Approval Form are approved in AODOCs in Document PPMO.
There are two possibilities when assigning the costs of WBS Element
1. Capex (Investment) - are all expenses related to a project and that the company can amortize in several fiscal years.
Tangible : A Tangible asset is something that you can touch such as equipment or hardware.
Intangible : An Intangible asset is a something that you cannot touch such as software of services
2. OTC (One time cost/Overhead/Opex) - An OTC linked to a project, is an expense which is not expected to reoccur.
3.1. I receive new WBS Element Requests from the IS Controllers
3.1.1. IS Controllers insert new WBS Element Request
After the approval of the project, the IS Controllers insert a new WBS Element Request in WBS Element Request file with the following information:
- Project Code
- Cost Center
- Company Code
- Site/Plant
- Budget
- Responsible Position
- Network needed or not
3.2. I insert project code in Project List
Everyday the MAC Analyst goes to the WBS Element Request file to verify if there is any new request from the IS Controllers.
When there is a new request, it is needed to parameterize the Project name in the tab Project List:
- Access Accolade and search for the indicated code. For example IT9464, search for "9464" without the IT and click in the project name.
- Once inside the project page, click in the right column on the field "Details". In this field it is possible to find the project description, Controlling Allocation, BU/Function and Requesting Team.
- Copy the project name and paste in Description column the tab Project List on WBS Element Request file .
- Projects can be divided in three streams/teams: APPLI, INFRA and NON IS. In case of doubt when filling the team, always validate with the requestor.
3.3. I insert project code and parameters in SAP PF2/WP2
3.3.1. SAP PF2
- Go to transaction Z1J_GROUP - Maintenance Project Group w/ text and click on .
- Fill the table with the project group code, description and currency (always EUR). It's not needed to insert the budget.
- Save the record clicking
3.3.2. SAP WP2
- Go to transaction ZWPST004 - Customer Enterprise PS Definition and click on .
- Fill the table with the project group code, description, currency, team, customer 1 and customer 2.
Note! Where do I get the customer 1 and customer 2? I need follow the procedure in 3.2 point:
- Costumer 1 corresponds to Controlling Allocation field.
Exception: When the controlling allocation matches GBS, the Costumer 1 will be GBS Projects - Costumer 2 correlate to BU/Function .
Exception: When the controlling allocation matches GBS, the Costumer 2 must be the Requesting Team .
Important!
- If Costumer 1 is a GBU, the Costumer 2 cannot be a Function or a Service Line.
- If Costumer 1 is a Function, the Costumer 2 cannot be a GBU or a Service Line.
- If Costumer 1 is GBS Projects, the Costumer 2 can only be a Service Line.
- If Costumer 1 is SW/HW EQUIPMENT, the Costumer 2 must be HW/SW Investments (incl Video).
- If Costumer 1 is MAGD, the Costumer 2 may be GBU or Function.
- This way, I will be able to start the creation of the WBS Structure.
3.4. I verify the fields of the request (Company code, plant, cost center)
It is very important to understand and verify the fields of the request before trigger the creation.
- EMEA
- All OTC projects are created by Lisbon team.
- Capex - there are some exceptions. It is needed to consult the Contacts for WBS creation & Useful address list in the tabs For IS in WP2 and For IS in PF2 to understand who is responsible for the creation. It is also useful to refer to the past WBS Elements created to understand who as created it.
- APAC and LAM
All the requests, OTC and Capex are created by local team. I need to click on the link in column AP "Open ticket?", and an automatic e-mail will be filled with the requesting fields to be sent to freshdesk.
Example:
- NAM
For SAP PF2 System:
- All OTC projects are created by Lisbon team.
- Capex - there are some exceptions. It is needed to consult the Contacts for WBS creation & Useful address list in the tabs For IS in WP2 and For IS in PF2 to understand who is responsible for the creation. It is also useful to refer to the past WBS Elements created to understand who as created it.
For SAP WP2 System:
All the requests, OTC and Capex are created by local team. I need to click on the link in column AP "Open ticket?", and an automatic e-mail will be filled with the requesting fields to be sent to freshdesk.
Example:
3.5. I create WBS Elements as requested
3.5.1. SAP PF2 - Investment projects (Capex)
3.5.1.1. How to codify the project definition and WBS Element
- Project definition example NHA/IYY XXX
YY - Year. If 2020 - should be 20; if 2021 - should be 21... and so on.
XXX - Sequential number
- WBS must have 4 levels
Example:
- WBS must have 4 levels
Level 1 NHA-IYYNNN
Level 2 NHA-IYYNNN.01
Level 3 NHA-IYYNNN.01.7
Level 4- NHA-IYYNNN.01.7. LL . WWW Z
LL corresponds to the material code:
- 70 for tangible assets
- 79 for intangible assets
WWW identifies the Stream:
- ISA for Application
- ISI for Infrastructure
- NIS for Non IS
Z is to define if Capex Intangible or Tangible
- M for Tangible Capex
- L for Intangible Capex
3.5.1.2. Create project definition
3.5.1.2.1 WBS Element creation
- Create a wbs element of level 1: (on the first row)
- Create a wbs element of level 2: (on the second row)
- Create a WBS element of level 3: NHA-I20025.01.7
Create a WBS element of level 4 (= WBS element attributable): NHA-I20025.01.7. 79. ISA L
The 2 last numbered positions are the material code linked to nature of the WBS element:
70 = MANAGEMENT INFORMATION SYSTEMS HARDWARE
72 = Equipment's Telecom
74 = Local Networks (LAN)
79 = Software
The last letters:
Three of them identify the Stream:
- ISA for Application
- ISI for Infrastructure
- NIS for Non IS
Final one is to define if Capex Intangible or Tangible
- M for Tangible Capex
- L for Intangible Capex
In the Description put the name of the project + “TAN” (for Tangible) or “INT” (for Intangible)
In Short ID: is automatic
Tick in the box: PE and Acct (Acct is Mandatory because the WBS is attributable)
Double click on the WBS of level 4 (for example on NHA-C17883.01.7.79.ISAL)
Check of the investment profile and the investment reason are right.
Enter the responsible code and the cost center.
Check if the box Acct asst elem. is well ticked.
Press Enter
Check of the investment profile and the investment reason are right.
Validate clicking on
3.5.1.2.1.1 Create Asset Under Construction
Click on " Asset under construction "
- Press enter
Click on
In tab "General" enter in the field "Inventory note" : 01.7.70 or 01.7.79 (corresponding of the part of material code)
In tab "Allocations" enter the following information:
Evalutation group 4: 70 or 72 or 79 (linked to the material code)
Evalutation group 5: the budget number without the plan and followed by .01 (for ex 17883.01)
Investment reason: H0
Click to go back on
Validate clicking on
3.5.1.2.1.2 Release WBS Element
The system status must be set as Released for WBS elements before you can post actual costs to the project or confirm the actual dates
It is necessary to position on all the levels (lines become orange) by a click on each level created.
Press on EDIT – STATUS- RELEASE and SAVE
Remark : In PF2 for the WBS elements for CAPEX no need to enter a settlement rule receiver parameter (because the assets under construction is active during the creation of the WBS element)
VERY IMPORTANT!!!!
Use the transaction CJ20N in the last level of WBS to enter the position code linked to the Project Manager responsible => Search it in the field via the match code.
It is important to don’t leave it empty!
3.5.1.2.2 The networks opening on Capex
The networks under WBS Elements CAPEX should be imperative created only when the WBS element CAPEX will be completely created and saved. (Contrary that for Networks on OTC which is created in the same time that the WBS element on OTC).
Execute the transaction CJ20N
Enter the Project Definition code - Project –>Open
Extend the structure to see all levels under the Project Definition
- Click on the last WBS element (In the left part of your screen). Select Create – Network
- In the right part of the screen, enter the name of the network. This one must be always identical to that the WBS element. Click on Enter.
- Select the network profile. In this case for plant NHA, select GBS-IT NHA_network profile and press Enter.
- In the tab "Scheduling", in section Dates/Times, check if the dates in "Start Date” and "End date" are correct. Correct them if it is necessary and validate every date by clicking on "Enter"
- In the tabs: "Assignments", "Control, Administr." and "Long Text" => Don’t modify anything !
Remark : the tab "Long Text" could be used to indicate some comments.
3.5.1.2.3. Activity opening on capex (needed for posting "CATS")
Reminder: The activities must be always created under a network !!!
Creation of the first activity
Click right on the "Network" (In the part "Project Structure: Description"), select create – Activity (internal)
In the right part of your screen, in "Identification and view selection" put the name of the activity requested by the controller preceded by the code Group.
Remark : T he number "0010" appears automatically.
Change the code of the "Control key"
The code "ZS01" to be replaced by "PD01" in the following case:
- PD01: This code is assigned to all the activities connected to projects from 20 KEur and for which the cost must be collected and transferred in PS (WBS) during the monthly closure CATS via the transaction CAT5 (PF2 - ERP Syensqo).
- ZS01: This code appears by default. It is assigned to activities that do not owe collect costs.
“System Status” : CRTD SETC is the status which appears as one created an activity.
“WBS element” : this code appears automatically.
Work Center” : The persons planned to work on specific activities (project or IT services) are identified in a "work center". A “work center" is assigned to each IT employee. This work center is communicated by the Project manager. If it is not communicated or unknown, the activity will be assigned by default to Work center" GBS-IT "
“Work” : Put the number of day planned for the activity or put the number "1" by default (if unknown).
In the tab " Dates ", select:
Start: " Must start on " and put the date of the beginning of the project
Fin.: " Must finish on " and put the date of the end of the project
Remark : As it is a network/activity for CAPEX no need to enter a settlement rule receiver parameter.
Redo the same way for each other Network activity needed.
3.5.1.2.4. Release Networks and Activities
Click on " Edit " - " Status " - " Release "
Click on save
Remark : The codes of networks/activities will be ONLY created (available) in SAP after this saving.
The following message appears => Click on Yes
Now the status is REL for the project definition, the WBS element and the activities.
- The new project code as well as the WBS/ Networks/Activities must be communicated to the Project leader and the involved IS Controller.
- They are also indicated in the sheet “WBS elements Requests” shared inWBS Element Request file
3.5.1.3. Set the budget amount
Use the transaction CJ30 , update the budget amount on each level of the WBS elements created.
Enter the project definition. For example:
Press enter
- Record the amount budgeted in K€ for each level of the WBS element. In this example => put 34,00 in the column budget (for the levels 1, 2,3 and 4):
- Save your entries
3.5.2. SAP PF2 - Overhead projects (OTC)
3.5.2.1. How to codify the project definition and WBS Element
Project definition example: NHA. PX KKK
KKK – Sequential number
WBS example: NHA.PX KKK.WWWO
WWW identifies the Stream:
ISA for Application
ISI for Infrastructure
NIS for Non IS
O is for OTC
3.5.2.2. Create project definition
Determining project definition sequential number
Execute the transaction " CN43N " in order to obtain the project list and their WBS element already created in PF2
Enter profile: Database prof. – introduce 000000000004
- Insert the beginning of the “Project Definition” , like this: “ NHA.PX* ” (Remarque: this code is used for the projects of the company 0001 Syensqo (SCH), in order to know which Project definition code to open.
Click on “ execute ” or F8
You can see that the last created “Project Definition ” was: NHA.PX366
The new one to be created will be: NHA.PX367
NHA.PX366 is an example!! This code belongs to the company 0001 Syensqo (SCH)!!! Please consider the plant of the company / site / country in which the IT project must be opened.
3.5.2.2.1 WBS Element creation
- Click right on the "Project definition" (In the part "Project Structure: Description"). Select Create –> WBS Element
- In the right part of the screen appears in the field of "WBS Element" the number of the Projet Def., followed by the figure 1 : NHA.PX369 1
Replace the figure 1 by dot (.) followed by the related team abbreviation:
ISA for Application
ISI for Infrastructure
NIS for Non IS
The last one position is for OTC
Example: You need to open a WBS element on OTC for the stream “Application” in company 0001 Syensqo (SCH), NHA.PXxxx.ISAO (for OTC).
- In the tabs: "Dates", "Assignments" and "Control": don’t modify anything!!! (All the data appear by default)
- In the tabs: "Administr", "Superior" and "Progress": Don’t enter anything!!
In the tab "Cust. enhancement":
Position – Enter the code position linked to the Project Manager responsible => Search it in the field via the match code. It is important to don’t leave it empty!
3.5.2.2.1.1 Settlement rule of WBS element
- Click on "Edit" => "Costs" => "Settlement rule" in order to check the settlement rules
- Click on “Goto” > “Settlement parameters”
Select the parameters below:
Settlement profile : ZPS10: when the costs of the project are allocated to an OTC !!Allocation structure: always put A2 !!!
- Click on the green arrow to leave the screen.
- In «Distribution rules” select:
- In «Cat»: CTR (cost center) when the WBS Element has to be assigned to cost center.
- In «Settlement Receiver»: Enter the cost center receiver validated by the IT Controller.
- Click on Enter.
- Click on the green arrow to leave the screen
3.6. I communicate the WBS Elements codes to the IS Controllers and contacts indicated by them
Once the WBS Element is created, I fill the in WBS Element Request file the WBS code and networks created.
If the controller has indicated in the comments that it is needed to send the codes to specific contacts, I send an e-mail to the indicated contacts.
For example:
3.7 What to do when we have an error in a WBS and we have an indication to close it?
1º Step - Enter the transaction CJ20N
- Click on Open Project and afterthat insert the WBS element;
- Go do Edit - Status - Close - Set
2º Step - If this message appears
- Click on Status information
- Analyze the error (this for example)
3º Step - Enter the transaction ME2K
- Insert the WBS element and click Execute
- Analyze the Display Report
4º Step - Read the report information
(Example)
For the PO number 4500461863 with value 17600€, the PO material (Agitatore Periferio Liquefatore) has been fully delivered and invoiced.
In case of the other error
1º Step - Enter the transaction ME2K
- Insert the WBS element and click Execute
- Analyze the Display Report
2º Step - Read the Report information
- Create a Ticket on Service One for the Procurement Department to close the PO's.