| Element from SAP | ScreenShot | Explanations |
|---|---|---|
| Stockholding Strategy (MRP2) | New dedicated field in SAP to store this information.
| |
| Catalog Lead Time (MRP2) | Catalog Lead Time (Calendar days) definition has been reviewed and the reference date is the material availability date. Usage:
Note: for Novecare only, since the GBU wants to avoid having different values in TRLT and Catalog LT field, the "Catalog LT" from SAP is not used, only the TRLT field is used (see below). This TRLT field currently stocks the "Promised LT to Customer".
Order Date - Material Availability Date >= Catalog Lead Time If the Catalog Lead Time is empty or set to 0, then the control will be done against the Tot. Repl. Lead Time. | |
| Tot. repl. Lead time (MRP3) |
Ideally, DynaSys will calculate "SHS RLT" (Stock Holding Strategy dependent RLT). The GBU will decide if they want or not to feed the "TRLT" field of SAP wit this value |
The best way to get IT support is to use the new
Service One Platform.