More information about each lead time below:
The final value of the “Procurement LT for P&I” will be the result of the following values, each with different priorities
For more information about PIR Pld Delivery time, please refer to: Procured LT
In DynaSys, the tab "Procurement LT for PI" will be the one used to calculate the "Procurement LT" used for P&I.
> Procurement LT historical: this is only displayed as information. It's median value calculated from historical Purchase Orders in SAP in the last 12 calendar months (we take the median of the lead times of each PO, this lead time being = date of PO reception - date of PO creation).
> Planned delivery time from MRP2 : this is the initial value. It takes the Pl
> Planned Delivery time from PIR: prioritary to the one from MRP2. Data coming from PIR. For more information about PIR Pld Delivery time, please refer to: Procured LT
> Proc LT override: user can override the value
> Procurement LT: this will be the result of the logic from previous lines (referto schema below)