In this document, you will find when datas are imported or exported between Dynasys, SAP and reports.

For exemple if you want to know when the datas are transferred between DP and dip, you look for the number (3 in our case) and you refer to the table on the right.


START OF DATA TRANSFERS

ExportImport
1

Import from SAP static and dynamic datas to DP (every days)


StaticDynamic
DP100:15 CET09:55 CET
DP311:50 CET10:05 CET
2

Export from DP Final Forecast to SAP (Every saturdays)

DP1 03:20 CET
DP315:00 CET

3

Export from DP Forecast to DIP-PP (every days)

DP1

03:05 CET

13:20 CET

17:15 CET

22:20 CET

DP3

01:30 CET

13:25 CET

17:20 CET

Import from DP Forecast to DIP-PP (every days)

DIP1

06:00 CET

13:45 CET

17:45 CET

22:45 CET

DIP2

05:00 CET

14:00 CET

18:00 CET

23:00 CET

DIP3

03:15 CET

13:55 CET

18:00 CET

22:50 CET

4

Export from DIP-PP constrained Demand to DP (every days)

DIP1

13:45 CET

17:45 CET

22:45 CET

DIP2

14:00 CET

17:30 CET

22:30 CET

DIP3

14:00 CET

17:55 CET

22:55 CET

Import from DIP-PP constrained Demand to DP (every days)

DP1

14:00 CET

18:00 CET

23:00 CET

DP3

14:05 CET

18:30 CET

23:15 CET

5


Import from SAP static and dynamic datas to DIP-PP (every days)


StaticDynamic
DIP103:45 CET07:10 CET
DIP203:30 CET07:20 CET
DIP302:00 CET07:15 CET
6

Export from DIP-PP constrained Demand  to SAP (every days)

DIP100:00 CET
DIP2NONE
DIP3NONE

7

Export data from DIP to BW DIP-PP report and Qlickview (every days updated at 14:00 CET in reports)

DIP109:00 CET
DIP209:00 CET
DIP309:00 CET

The best way to get IT support is to use the new Service One Platform.