Once a plant starts using the SAP QM Module, the next step is to leverage on the new capability to determine when each new lot will be available (=released from QC).
This also allows SAP (and especially ATP) to prevent a lot to ship while it is in QI.
It furthermore allows SAP (and especially ATP) to determine if a specific lot can ship at a given date.
In order to achieve this, the Lab reviews their statistics and establishes the expected QC completion duration, which goes into SAP.
Both Picaso and SAP have to be kept in synchronization when accounting for time the Lab needs to do quality control (Lab Time: from receiving sample, to registering results of tests and analysis).
Step-by-step guide
Now, in order to determine the SAP QC Time, SAP Average Inspection Time, Picaso QC Lag, and Picaso QC Lag Adjustment, first determine what material flow applies:
- Scenario A: Lot is received in inventory at the manufacturing plant, then ships from the plant to final customer. All happening from within the production plant.
- Scenario B: Lot is received in inventory at the manufacturing plant, then is pushed to the warehouse once released from QC. Once it arrives at the warehouse, it can ship to final customers.
- Scenario C: Lot is received in inventory at the manufacturing plant, then is pushed to the warehouse right away, that is, before QC release. It is received at the warehouse in QC status. It will ship to final customers once released from QC.
- Scenario D: Same as C, with lots being received in SAP, and QC starting, while campaign still in progress. Even more complex, therefore only if adds value (to be continued)
Tips: The SAP QC Time, SAP Average Inspection Time, Picaso QC Lag, and Picaso QC Lag Adjustment apply during specific events of the life of a lot:
Applies before the lot is received in inventory
(aka Planning Phase)
Applies once the lot has been received in inventory and the QM Lot has been generated
(aka )
Picaso QC Lag
Picaso Schedule Upload Lag Adjustment
Goods Receipt Processing Time
Average Inspection Duration Material flows:
Phase Scenario A Production run time: 6 days
Lab time = 4 days
Before Goods Receipt from Production in the manufacturing plant After Goods Receipt from Production in the manufacturing plant After Release Master Data: Picaso: QC Lag = Lab Time (4 days)
SAP: Av.Ins.Duration = Lab Time (ex. : 4 days)
Phase Scenario B Production run time: 6 days
Lab time = 4 days
Transfer time between manufacturing plant and warehouse = 1 day
Lot moved to the warehouse after QC release
Before Goods Receipt
(aka Planning phase)
After Goods Receipt from Production in the manufacturing plant
(aka Goods Receipt from Production phase)
After Release
After Goods Receipt from Transfer in the warehouse
(aka Goods Receipt from Transfer)
Master Data: Picaso:
- QC Lag = expected QC duration + transfer to the warehouse, including handling. (ex. : 11 days)
- Schedule Upload Lag Adjustment = - QC Lag + transfer time (ex. : -10 days)
SAP:
- Av.Ins.Duration = expected QC duration (ex. : 4 days)
Phase Scenario C Production run time: 6 days
Lab time = 4 days
Transfer time between manufacturing plant and warehouse = 1 day
Lot moved to the warehouse during QC
Before Goods Receipt from Production
After Goods Receipt from Production in the manufacturing plant
After Goods Receipt from Transfer in the warehouse
After QC Release
Master Data: Picaso:
- QC Lag = expected max of Lab Time / transfer to the warehouse, including handling. (ex. : 4 days)
- Schedule Upload Lag Adjustment = - QC Lag (ex. : -4 days)
SAP (in the warehouse)
- Goods Receipt Processing Time (@warehouse)= Lab Time - Transfer time (ex. : 4 days)
- Av.Ins.Duration (@warehouse)= Lab Time - Transfer time (ex. : 3 days)
- Planned Delivery Time (@warehouse)= Transfer time (ex. : 1 days)
Recap:
Scenario Master Data Picaso Master Data SAP A QC Lag = Lab Time @the plant
Av.Ins.Duration = Lab Time
B QC Lag = Lab Time + transfer to the warehouse, including handling
Schedule Upload Lag Adjustment = - QC Lag + transfer time
@the plant
GRPT = Lab Time
Av.Ins.Duration = Lab Time
@the warehouse
Planned Delivery Time = Transfer time
C QC Lag = max of (Lab Time // transfer time)
Schedule Upload Lag Adjustment = - QC Lag
@the warehouse
GRPT = Lab Time - Transfer time
Av.Ins.Duration = GRPT
Planned Delivery Time = Transfer time
@the plant
N/A
- Use this template file to help calculate the data en masse.