Upon reception of the monthly notification, you want to:

  1. validate the schedule snapshot (the current month schedule)
  2. review and comment the adherence performances of last month

Step-by-step guide

  1. Validate the schedule snapshot
    1. open the MatSeg PA - Data file.
    2. open the Sch RoW YYYYMM sheet. YYYYMM is the current month. E.g. if today is April 03 2023, you want to work on Sch RoW 202304.

    3. Use a filter view to help. Many have been already created. Feel free to use them or create yours.

    4. Here, in this example, we use a filter view named 'Borger'.

      1. April production schedule is highlighted.

      2. The schedule of April has been downloaded from Picaso into that spreadsheet on April the 1st. 
    5. Review/validate these numbers, and make necessary adjustments. When should you adjust these numbers?


      1. if you made schedule changes on the first days of the month, that you think should have been accounted for in the monthly snapshot

      2. if for any reason, you could not update the schedule prior to the snapshot (prior to April 1st) and you think they should be accounted for in the snapshot.
  2. Review and comment the 