Main steps:
- Assess
- Prepare
- Launch
- Accelerate
- Sustain and improve
| Steps | Ideal timeline before launch | Topic | Jira epics | Notes |
Assess | 6 months | Need for change set
| See article of SAFe (something Tipping point..) which describes reasons for this change | |
Assess | 6 months | Train leadership (leading safe) | ||
| Assess | 6 to 4 months | Define and validate the main milestones Define transformation team | Transformation team seems to be set - to discuss with Florence if the meeting Wednesdays includes the full team members | |
| Assess | 6 to 4 months | Communicate vision/ Engage teams | Plan created by Alix, cannot find vision nor economic view, to be discussed | |
| Prepare | 3 months | Identify value streams and ARTs:
Identify and communicate ideal attributes:
| Experience: The bigger the ART is , the most likely is a full value stream but the more complex it becomes to organise. Ideally, also on experience, we should start with one ART and focus on that launch |