You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 15 Next »

Status

  Approved

OwnerAntonio Zappone 
Stakeholders

Issue

Decision is required as the when to deploy the new S4\HANA In-House-Bank.


Recommendation:    Option A: Defer the deployment of IHB for all GBUs\Entities until after the second group go-live. 

This is the lowest risk option in an area that is generally considered higher risk. Payments and receipts is a critical processes.  There are additional layers of complexity with running an in-house-bank along with the higher complexity custom solutions to support the internal factoring process.

Interim interfaces are required, which adds complexity, however these interim interfaces are required in most of the deployment options.  The interim interfaces will be developed based on the existing interfaces from PF1\WP1 to PI1, hence they are not new design, although they will have to be adapted for the S4HANA. 

Deferring the deployment requires project resources for a longer period of time, which equates to additional cost.   Required resources will be limited to IHB consultants and technical developers.  Whether this is an "additional cost, or whether resources can commence later and finish later needs to be determined in the overall project planning. 


Background & Context

In-House Bank

The existing IHB within ECC resides in PI1, within the legal entities SSA and SFA.  SSA and SFA entities also reside in PF1 for all non IHB processes.  Interfaces are current in place to link PF1 and WP1 to the IHB in PI1. 

All entities are mandated to participate in the IHB process, except where it's not legally possible.  For example, China, x ,x ,x , is not part of the IHB due to legal restrictions.


Internal Factoring

A high level of complexity exists with IHB largely due to the internal factoring process. Internal factoring brings benefits in the way of; 

  • Tax cash advantage of ~3 m€ per year for Syensqo
  • Native centralisation of the cash flows onto Syensqo SA and SFA without the need to pool further
  • Centralisation of the FX exposures that enable centralised and efficient hedging over the largest exposures possible
  • Centralisation of the collection and credit risk allowing to streamline the CCT activities (Note: should be shared with CCT)
  • Centralisation of the vendor payments allowing the streamline the A/P and Payroll activities (Note: should be shared with A/P and HR-Payroll)

Internal factoring is not a common process and not supported by standard SAP, hence the current solution requires numerous complex custom developments.  To "to-be" design will aim to streamline and simplify, however it is expected that some level of custom developments will still be required. 


Risk

Cash movements related to payments and receipts is a higher risk area of any ERP implementation. The internal factoring complexity increases the risk. 

Risk is a major factor in the recommendation and decision of this KDD.


Assumptions

IHB and internal factoring will continue in S4HANA.

Entities not operating within the IHB will go-live with Bank Communication Management (BCM) in line with Overall project release\s.


Constraints

Nil 


Impacts

Depending on the approach, interfaces from S4HANA to PI1 require consideration. If they are required, the existing interfaces from PF1 \ WP1 will need to be replicated for S4HANA.

The new Consolidations tool will go-live in the last release.  This requires considerations for the Consolidation of the entities and processes within PI1.


Business Rules

Participation in the IHB will continue to be mandatory unless not legally supported.


Options considered

Early deployment (prior to the main S4HANA releases) of IHB was considered, however due to the impact of extending the overall ERP project timeline, and earlier transfer of master data, this option was not review in this KDD.  

Option A: Defer the deployment of IHB for all GBUs\Entities until after the second group go-live. 

Defer by 4 to 6 months


Lowest risk option, for IHB is a high risk \ high complexity process by allowing for a fall back \ contingency for the IHB payments and receipts

Allows time to integrated process to stabalise

Allows the option of production simulations

Interfaces need to be built between the S4HANA and PI1, although these will largely be replications of existing interfaces.


Option B: Deploy IHB for live GBUs/entities in-line with the groups of the phased deployment (Two IHBs).

This option entails deploying the IHB in line with the groups in the release plan. One IHB in PI1 for entities still on ECC, and a second IHB for GBUs\entities that have S4HANA for transitioned to S4HANA.

The main drawbacks with this option;

  1. Running two IHB can increase complexity 
  2. Additional business resources will be required


Option C: Deploy IHB for live GBUs/entities in the first group of the phased deployment.

This option entails IHB being deployed for all entities in the first group of the release plan. 

The main drawback with this option;

  1. Highest risk option 

  


Option D: Deploy IHB for all GBUs/entities along with the second Group of the phased deployment.

This option entails IHB being deployed for all entities in the second group of the release plan.

This was seen at the best alternative, however the recommended Option A is preferred due to additional de-risking.


Evaluation



Option A

Option B
Option C
Option D
Option A
Option B
Option C
Option D

De-Risk

Strong Contingency \ fallback option

(plus) PI1 will be available to as a contingency should there be significant issues with the S4HANA IHB. 


(minus) PI1 is not a possible fall back.   

(plus) Phased transitioned entails less entities go-live in first phase is a lower risk. if there is a significant issue, it will only impact the entities which have transitioned to S4HANA. 

(minus) PI1 not a possible fall back.

(plus) PI1 will be available to as a contingency should there be significant issues with the S4HANA IHB.  (only for group 1 entities)

High

Medium

Low

Medium

De-risk

Stabilisation on integrated process (Sales\Accounts Receivable, Payments\Accounts Payables)

(plus) Integrated processes will have had time to stabilise.

(minus) No additional time for integrated process to stabilise, and higher probability of integration issues.

(minus) No additional time for integrated process to stabilise, and higher probability of integration issues.(plus) Integrated processes will have had time to stabilise, (for GBUs\Entities from group 1).HighLowLowMedium

De-risk

Ability to run Productions Simulations

(plus) Production simulation possible, for all entities, which contributes to lowering the risk.(minus) Unable to execute production simulations prior to go-live.(minus) Unable to execute production simulations prior to go-live.(plus) Production simulation possible, for group 1 entities, which contributes to lowering the risk.HighLowLowHigh

Less Complexity - Less Interfaces

(minus) Requires interfaces to be built for integration of PI1 with S4HANA. Interfaces are required for all GBUs\Entities.

(plus) New interfaces are not required for PI1 to S4HANA


(minus) New interfaces are required for integration of ECC (WP1) with S4HANA, for GBUs\Entities transitioning in Group 2. 

(minus) New interfaces are required for integration of PI1 with S4HANA, for GBUs\Entities transitioning in group 1. 


Low

High

Medium

Medium

Less Complexity - One IHB Operating is less complex than two IHB in operation 

(plus) One IHB Operating

(minus) Two IHBs Operating

(plus) One IHB Operating

(plus) One IHB Operating

High

Low

High

High

Additional Resource Cost

(minus) With the go-live of IHB deferred, relevant resources will be required for an extended period.

(plus) No additional project resoure costs.(plus) No additional project resoure costs.(plus) No additional project resoure costs.LowHighHighHigh
Business resource impact(plus) No additional\adverse impact on business resources

(minus) Additional resources likely required to run two IHBs. 

(minus) Business resources will likely need to perform manual clearing payment sub-ledgers.

(plus) No additional\adverse impact on business resources(plus) No additional\adverse impact on business resourcesHighLowHighHigh
Ease of Consolidation

(minus) Consolidation of the entities on PI1 will require an interim solution, for new Consolidations Tool.

Standard process to load into Cosnsol are expected to be utilised

(minus) Consolidation of the entities on PI1 will require an interim solution. Utilise existing approach into BFC Consolidation Tool.(plus) Consolidations will follow the normal interim process for BFC Consol.

(minus) Consolidation of the entities on PI1 will require an interim solution, or new Consolidations Tool  

Standand process to load into Cosnsol are expected to be utilised

MediumMediumHighMedium
Lower Cut-over impact (less payments outages).(plus) One payment outage as only one cut-over is required.(minus) Two payment outages to manage.(plus) One payment outage as only one cut-over is required.(plus) One payment outage as only one cut-over is required.HighLowHighHigh

See also


No files shared here yet.

Change log

Version Published Changed By Comment
CURRENT (v. 15) Nov 14, 2024 08:01 ZAPONNE-ext, Antonio
v. 81 Nov 14, 2024 05:58 ZAPONNE-ext, Antonio
v. 80 Nov 14, 2024 03:47 ZAPONNE-ext, Antonio
v. 79 Nov 14, 2024 03:23 ZAPONNE-ext, Antonio
v. 78 Nov 13, 2024 16:33 ZAPONNE-ext, Antonio
v. 77 Nov 13, 2024 16:32 ZAPONNE-ext, Antonio
v. 76 Nov 13, 2024 09:12 ZAPONNE-ext, Antonio
v. 75 Nov 07, 2024 16:25 WENNINGER-ext, Sascha
v. 74 Nov 07, 2024 16:23 WENNINGER-ext, Sascha
v. 73 Nov 06, 2024 15:43 ZAPONNE-ext, Antonio

Go to Page History

Workflow history

Title Last Updated By Updated Status  
There are no pages at the moment.

  • No labels