You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 63 Next »

Status

  Approved

OwnerAntonio Zappone 
StakeholdersGilles Madjarian, Selim Ulhasan

Issue

Decision is required as to when to deploy the new S4/HANA In-House-Bank.


Recommendation:  Option E: Defer the deployment of IHB for all GBUs/Entities until after the second group go-live.  

This is the lowest risk option in an area that is considered higher risk. Payments and receipts are critical processes.  There are additional layers of complexity, they include; running an in-house-bank, the higher complexity custom solutions to support the internal factoring process.

This option is the lowest risk alternative. It has a fall back / contingency option with the ECC/PI1 IHB, allows time for integrated process to stabilize, and also allows for production simulations. This is relevant for all entities.

Interim interfaces are required, which adds complexity, however these interim interfaces are required in most of the deployment options.  The interim interfaces in this option will be developed based on the existing interfaces from PF1/WP1 to PI1, hence they are not new design, although they will have to be adapted for the S/4 HANA.  Where interim interfaces between PI1 and S/4 HANA would have already been built for group 1, extending these interfaces for group 2 will be easily manageable.

Deferring the deployment requires project resources for a longer period of time, which equates to additional cost.   Required resources will be limited to IHB consultants and technical developers.  This cost may be mitigated to some extent, however this will be determined within the roadmap planning.  Regardless, the additional cost is outweighed by the risk mitigated. 

Payments outside of IHB will go-live with the groups as per the release plan. These payments will continue via Bank Communication Management (BCM), and they will draw out any issues prior to the larger volume/value payments commence via IHB. 

Being outside of the go-live of the main group/s, it can be expected that the cut-over outage will be shorter, resulting is a shorter payment outage which will be easier to manage. 

Defer period of 3 to 6 months, alignment with the deployment roadmap and business available months required.

Further details on this option, and how it compares to alternatives is available in the evaluation section.


Background & Context


This KDD is focused on the deployment approach for the new S/4 HANA IHB.  The existing processes and customization are in scope for the ERP rebuild project. These processes will be reviewed in the detailed design phase, with the aim to streamline and simplify where possible. 


In-House Bank

The existing IHB within ECC resides in PI1, within the legal entities Syensqo SA and Solvay Finance America

All entities are mandated to participate in the IHB process, except where it's not legally possible. 

Interfaces are currently in place to link PF1 and WP1 to the IHB in PI1. 

SSA also reside in PF1 for all non-IHB processes. 


Internal Factoring

A high level of complexity exists with IHB largely due to the internal factoring process. 

Internal factoring is not a common process and not supported by standard SAP, hence the current solution requires numerous complex custom developments.  The "to-be" design will aim to streamline and simplify, however it is expected that some level of custom developments will still be required. 


Risk

Cash movements related to payments and receipts is a higher risk area of any ERP implementation. The internal factoring complexity increases the risk. 

Risk is a major factor in the recommendation and decision of this KDD.


Assumptions

IHB and internal factoring will continue in S/4 HANA.

Entities not operating within the IHB will go-live with Bank Communication Management (BCM) in line with Overall project release/s.


Constraints

Nil 


Impacts

Depending on the approach, interfaces from S/4 HANA to PI1 require consideration. If they are required, the existing interfaces from PF1 / WP1 will need to be replicated for S/4 HANA.

The new Consolidations tool will go-live in the last release.  This requires considerations for the Consolidation of the entities and processes within PI1.


Business Rules

Participation in the IHB will continue to be mandatory unless not legally supported.


Options considered

Early deployment (prior to the main S/4 HANA releases) of IHB was considered, however due to the impact of extending the overall ERP project timeline, and earlier transfer of master data, this option was not review in this KDD.  

IHB is a high risk, mitigating that risk is a critical factor as when compare options.

Option A: Deploy IHB for all GBUs/entities along with the first group of the phased deployment.

This option entails the new IHB being deployed for all entities, and execution with the first group of the release plan. 

Main Points (further details are in the evaluation section). 

  • Higher risk option, with no ECC/PI1 fall back / contingency option, no time for overall system and process stabilization and no opportunity for production simulations.
  • New interfaces required from ECC to S/4 HANA. These will be newly designed interfaces and not replication of existing interface functionality.    


Option B: Deploy IHB for live GBUs/entities in-line with the groups of the phased deployment (Two IHBs).

This option entails deploying the new IHB in-line with the groups in the release plan. One/existing IHB in PI1 for entities still on ECC, and a second/new IHB for GBUs/entities that have transitioned to S/4 HANA.

Main Points (further details are in the evaluation section). 

  • Higher risk option, with no ECC/PI1 fall back / contingency option, no time for overall system and process stabilization and no opportunity for production simulations.
  • Running two IHB will increase complexity and possibility of errors.
  • Additional business resources will be required.   

  

Option C: Deploy IHB for all GBUs/entities along with the second Group of the phased deployment.

This option entails the new IHB being deployed for all entities, and execution with the second group of the release plan.

Main Points (further details are in the evaluation section). 

  • This was seen as a viable alternative, however the recommended Option E is preferred due to additional de-risking.
  • Risk mitigation (fall back contingency, overall system and process stabilization and production simulations are available for Group 1 Entities, but not the whole organization.
  • Payments via BCM will draw out issues prior to IHB deployment - this is limited to group 1 entities.


Option D: Deploy IHB for all GBUs/entities along with the All-in one deployment.

This option entails the new IHC will be deployed at the same time as all GBUs/Entities as part of the all-in one deployment approach.

Main Points (further details are in the evaluation section). 

  • This option is low complexity but higher risk.
  • Interim interfaces are not required.
  • The robust de-risking options mentioned in this document are not available with this option. Alternative risk mitigation will need to be determined, for example additional testing.

Option E: Defer the deployment of IHB for all GBUs/Entities until after the second group go-live. 

Defer by 3 to 6 months (need to align with deployment roadmap and business available months).


Main Points (further details are in the evaluation section). 

  • Lowest risk option. This option has a fall back / contingency option with the ECC/PI1 IHB, allows time for integrated process to stabilize, and also allows for production simulations. Relevant for all entities.
  • Payments via BCM will draw out issues prior to IHB deployment - this is relevant for all entities.
  • Interfaces need to be built between the S/4 HANA and PI1, although these will largely be replication of the existing interface functionality, and adjusting for master data changes.
  • Interim interfaces between PI1 and S/4 HANA would have already been built for group 1, extending these interfaces for group 2 will be easily manageable. 
  • Additional cost expected with relevant resources required for an extended period. This cost is seen to be outweighed by the risk it mitigates.


Evaluation



Option A
Deploy IHB for all GBUs/entities along with the first group of the phased deployment
Option B
Deploy IHB for live GBUs/entities in-line with the groups of the phased deployment (Two IHBs).
Option C
Deploy IHB for all GBUs/entities along with the second Group of the phased deployment.

Option D
Deploy IHB for all GBUs/entities along with the All-in one deployment.

Option E

Defer the deployment of IHB for all GBUs/Entities until after the second group go-live.

Option A
Option B
Option C
Option D
Option E

De-risk level

  • Robust contingency / fallback option

(minus) PI1 not a possible fall back.

(minus) PI1 is not a possible fall back.   

(plus) Phased transitioned entails less entities go-live in first phase is a lower risk. if there is a significant issue, it will only impact the entities which have transitioned to S/4 HANA. 

(plus) PI1 IHB will be available to as a contingency should there be significant issues with the S/4 HANA IHB.  (only for group 1 entities)

(minus) PI1 not a possible fall back.

(plus) PI1 IHB will be available to as a contingency should there be significant issues with the S/4 HANA IHB. 


Low

Medium

Medium

Low

High


De-risk Level

  • Stabilization on integrated process (Sales/Accounts Receivable, Payments/Accounts Payables)
(minus) No additional time for integrated process to stabilize, and higher probability of integration issues.

(minus) No additional time for integrated process to stabilize, and higher probability of integration issues.

(plus) Integrated processes will have had time to stabilize, (for GBUs/Entities from group 1).(minus) No additional time for integrated process to stabilize, and higher probability of integration issues.(plus) Integrated processes will have had time to stabilize.LowLowMediumLowHigh

De-risk Level

  • Payments outside of IHB will draw out issues
(minus) IHB and BCM will go-live together. No opportunity for BCM to draw out issues in advance.

(minus) IHB and BCM will go-live together. No opportunity for BCM to draw out issues in advance.

(plus) Non-IHB payments via BCM will draw out issues prior to IHB deployment.  

Relevant for group 1 entities.

(minus) IHB and BCM will go-live together. No opportunity for BCM to draw out issues in advance.

(plus) Non-IHB payments via BCM will draw out issues prior to IHB deployment.  

Relevant for all  entities.

LowHighLowLowHigh

De-risk level

  • Ability to run Productions Simulations
(minus) Unable to execute production simulations prior to go-live.(minus) Unable to execute production simulations prior to go-live.(plus) Production simulation possible, for group 1 entities, which contributes to lowering the risk.(minus) Unable to execute production simulations prior to go-live.(plus) Production simulation possible, for all entities, which contributes to lowering the risk.LowLowMediumLowHigh

Less Complexity

  • Less Interfaces or lower complexity interfaces

(minus) New interfaces are required for integration of ECC (WP1) with S/4 HANA, for GBUs/Entities transitioning in Group 2. 

New interfaces need to be designed and built for Group 2 entities in order to match ECC with the new S/4 HANA design.

(plus) New interfaces are not required for PI1 to S/4 HANA


(minus) New interfaces are required for integration of PI1 with S/4 HANA, for GBUs/Entities transitioning in group 1. 

Interfaces will be based on existing ECC interfaces already in place.

(plus) New interfaces are not required for PI1 to S/4 HANA


(minus) Requires interfaces to be built for integration of PI1 with S/4 HANA. Interfaces are required for all GBUs/Entities.

Interfaces will be based on existing ECC interfaces already in place.

Interfaces for Group 1 would already be built, extension to Group 2 will be required. 

Low

High

Medium

High

Medium


Less Complexity

  • One IHB Operating is less complex than two IHB in operation 

(plus) One IHB Operating

Less complex, less chance or errors

(minus) Two IHBs Operating

More complex, high chance or errors

(plus) One IHB Operating

Less complex, less chance or errors

(plus) One IHB Operating

Less complex, less chance or errors

(plus) One IHB Operating

Less complex, less chance or errors

High

Low

High

High

High


No additional Resource Cost(plus) No additional project resource costs.(plus) No additional project resource costs.(plus) No additional project resource costs.(plus) No additional project resource costs.

(minus) With the go-live of IHB deferred, relevant project resources will be required for an extended period.


HighHighHighHighLow
Lower business resource impact(plus) No additional/adverse impact on business resources

(minus) Additional resources likely required to run two IHBs. 

(minus) Business resources will likely need to perform manual clearing payment sub-ledgers.

(plus) No additional/adverse impact on business resources(plus) No additional/adverse impact on business resources.(plus) No additional/adverse impact on business resourcesHighLowHighHighHigh
Ease of Consolidation(plus) Consolidations will follow the normal "interim" process for BFC Consol.(minus) Consolidation of the entities on PI1 will require an interim solution. Utilize existing approach into BFC Consolidation Tool.

(minus) Consolidation of the entities on PI1 will require an interim solution, or new Consolidations Tool  

Standardized process to load into Consolidation system expected to be utilized

(plus) Consolidation will follow the new Consolidation process, no interim process required.

(minus) Consolidation of the entities on PI1 will require an interim solution, for new Consolidations Tool.

Standardized process to load into Consolidation system expected to be utilized

HighMediumMediumHighMedium
Lower Cut-over impact (less payments outages).(plus) One payment outage as only one cut-over is required.(minus) Two payment outages to manage.(plus) One payment outage as only one cut-over is required.(plus) One payment outage as only one cut-over is required.

(plus) One payment outage as only one cut-over is required.

A shorter cut-over outage for payments.

HighLowHighHighHigh

See also


No files shared here yet.

Change log

Version Published Changed By Comment
CURRENT (v. 63) Nov 14, 2024 08:01 ZAPONNE-ext, Antonio
v. 81 Nov 14, 2024 05:58 ZAPONNE-ext, Antonio
v. 80 Nov 14, 2024 03:47 ZAPONNE-ext, Antonio
v. 79 Nov 14, 2024 03:23 ZAPONNE-ext, Antonio
v. 78 Nov 13, 2024 16:33 ZAPONNE-ext, Antonio
v. 77 Nov 13, 2024 16:32 ZAPONNE-ext, Antonio
v. 76 Nov 13, 2024 09:12 ZAPONNE-ext, Antonio
v. 75 Nov 07, 2024 16:25 WENNINGER-ext, Sascha
v. 74 Nov 07, 2024 16:23 WENNINGER-ext, Sascha
v. 73 Nov 06, 2024 15:43 ZAPONNE-ext, Antonio

Go to Page History

Workflow history

Title Last Updated By Updated Status  
There are no pages at the moment.

  • No labels