| PART I | Monthly Monitoring Steps | ||
|---|---|---|---|
| Step | What to check? | Where to check? | How to check? |
| #1 | Check status of all the monthly jobs | SBS - Technical views |
If not → wait until it end |
| #2 | NOVECARE - Consistency of data | Simulate WS A2. SOP Planning with user MGBA6210 | Find a SKUs as example and check the following data:
Check the projected inventory calculated by the DRP is correct (month with qty = 0, or lower quantities than actuals...) Check that the final demand after netting seems ok. Check that export to BW batch has run without error (SBS technical view) |
| #3 | Check SAP Independent requirements | MD63 in SAP | Check between SAP and Dynasys the Forecast exported => Take 3 SKUs PW as examples by BU > Novecare : in DIP, Final Demand after netting (last validated) in CS model !!! Please take examples from Sites where forecast export is activated!!! !!! Please take examples when forecast is different from 1 month to another !!! You can use this specific Grid view to help the monitoring ( In MD63, please fill the Plant/Material and the month to check. |
| #4 | Communication | Send an email to the DIP3 users | to: sco-dynasysusersdip3@syensqo.com title : DynaSys monthly update CS Text : Dear All, The monthly update is done. You can now connect into DIP. SAP data will not be updated until the end of the netting process on the 4th of the current month. → Verify the date each month ! => corresponds to the Netting day Next SAP data update takes place after S&OP validation on the 11th of the current month. → Verify the date each month ! => corresponds to the day after validation The remaining SAP data updates will take place every Saturday until the end of the current month. Regards. DynaSys - 2024 SOP Calendar => Example for Nov 2024, Email Example, |
| PART II | Checks to do after the validation of S&OP | ||
| #1 | Check the archive of S&OP Validation archive +1 day after the S&OP Validation |
Z800 should be equal to S&OP Validation of Month M for M+1 | |

