Bugfix request to RM

For bugfix for Prod,  ensure that:

  • The type of the jira ticket is Bug
  • You have assigned the "bugfix/*" fixversion according to the bugfix fixVersion process*
  • You have set the correct component CORE or iCARe
  • The status is "Ready for UAT" or "Ready for Production"
  • It's assigned to the RM

For bugfixes of monthly release, it's exactly the same the only difference is that the fixVersion is the monthly one, and in the status it can also be "Ready for INT"


Bugfix fixVersion process

Next time you create a bugfix to go to Prod, don't assign it to the weekly release (as we have been doing until now), instead:
1. If you already know when this should go to Production (taking into account time of development), create a fix version following the format bugfix/DD_MM_YY, and assign to the bugfix.
2. If you don't know when this will go to production, assign it to "bugfix-placeholder" fix version (Pankaj is creating this one in all projects). After you know the day of deployment, switch the bugfix fix version following point 1.


Calendar of activities

The purpose of this weekly calendar is that for BugFix releases, we provide transparency and allow for planning on when the different actions for deployments to UAT and Production occur. 

Some important details:

  • While BugFix deployments to production will occur on Tuesday, Wednesday, and Friday, it's important that:
    • These are tested in UAT first, and therefore deployed to it following the timelines in the calendar.
      • For example, if I want to deploy a bugfix to production on Tuesday, I should make sure that
        • I have submitted it to release manager before the cut-off on Monday 16pm
        • A developer will be able to assist the release manager during possible fixes in the validation to UAT.
        • A Tester will be able to test from 11-12 CET, taking into account that the cut-off to include it in the deployment to production is 12pm CET.
    • On a general basis, there are no deployment to Production of BugFixes neither Mondays or Fridays, due to other deployment activities of Weekly / Monthly happening at the same time. However, if there is urgency, reach out to Release managers through the "Deploys" group to find a solution.
    • Differentiate HotFix from general Bugfix, to clarify that in the event of a HotFix (bugfix with maximum priority), this will be raised through the HotFix channel in google chat and release managers will assist for the soonest deployment of it, and possibly bypassing the calendar below due to business impact.



BugFix Weekly Activities

MondayTuesdayWedesdayThusdayFriday
CETUATPRODUATPRODUATPRODUATPRODUATPROD
10:00

Validation, Fixes and Deployment to UAT

Validation, Fixes and Deployment to UAT


Validation, Fixes and Deployment to UAT




11:00

UAT Test






12:00

12:00 CET - Cut-off for Tuesday Production deploymentUAT Test12:00 CET - Cut-off for Wednesday Production deploymentUAT Test12:00 CET - Cut-off for Thursday Production deployment

13:00


Tue PROD Bug Fixing Validation & Deployment


Wed PROD Bug Fixing Validation & Deployment


Thu PROD Bug Fixing Validation & Deployment



14:00

15:00 CET - Cut-off for Tuesday-Afternoon UAT Deployment15:00 CET - Cut-off for Wednesday-Afternoon UAT Deployment15:00 CET - Cut-off for Thursday-Afternoon UAT Deployment

15:00

Validation, Fixes and Deployment to UAT

Validation, Fixes and Deployment to UAT

Validation, Fixes and Deployment to UAT



16:00Cut-off for first Monday/Tuesday UAT Deployment
Tue PROD Bug fixing DeploymentWed PROD Bug fixing DeploymentThu PROD Bug fixing Deployment

17:00

Validation, Fixes and Deployment to UAT







18:00

UAT Test


19:00 CET - Cut-off for Wednesday-Morning UAT Deployment


UAT Test


19:00 CET - Cut-off for Thursday-Morning UAT Deployment


UAT Test


19:00 CET - Cut-off for next UAT Deployment



19:00




The best way to get IT support is to use the new Service One Platform.