KPI Owner

François Carette
 Performance & Capex Reporting Manager - GEC

D&PS Expert

Marie-Line Ardito

General Description

Capability to have a general view of Capex/Capspend of the past (Y-2, Y-1) the present (Y) and the future (Y, Y+1, Y+2) by GBU
Calculation 
Capex Actuals
is the amount paid
If the cost is linked to a purchase order => it's the amount once the invoice has been paid.
If the cost is not related a purchase order => equal to the capspend (GR)
Capex Forecast
is the prevision of capex filled and updated by the GBU into Colmar
  
Capspend Actuals
is the actual costs (received costs)
it can correspond to :
  • Purchase orders, the reception of services/goods (at GR date)
  • Stock issue : value of the material (at stock issue date)
  • Hours : standard cost defined for each hour.
  • Transfers (from Maintenance orders etc...)
  • Manual entries (CO document) and other adjustments.
Capspend Forecast
is the prevision of Capspend filled and updated by the GBU into Colmar

Sources

Capex/Capspend Actuals

Capex/Capspend Forecasts

Core query
BW_QRY_MPR_PS014_0011
BW_COLMAR_MVIPCO17_0001
QV query
QVCOLMAR_BW_QRY_MVIPCO17_0002
QVCOLMAR_BW_QRY_MVIPCO17_0003
Refresh frequency
Daily - full reload
Daily - full reload
Filters
 
Investment type <> training

Specific Dimensions

  • Version : Active version (last version updated in Colmar), Y versions, Y-1 versions
  • Project type : Capitalized, Not Capitalized
  • Planned : Yes, No
  • Bundle : list of bundles (def + key)
  • Project status : Approved (as soon as there is an authorized amount), Not Approved
  • Project approval status : Present approval status of the project
  • Project approval year : for a bundle, 1rst date of approval of the projects of the bundle

Scope

  • All the projects entered in Colmar with forecasted budget on the available versions

Authorization & Rights

All the accesses must be validated by the
GBU Capex Coordinators
Authorisations' rights per GBU, Zone or Plant