Process Owner
François Carette
Performance & Capex Reporting Manager - GEC
D&PS Expert
Marie-Line Ardito
General Description |
|---|
Capex Dashboard consists indicators on Budget, Capex, Capital Spend, Downpayment and Commitments of the group.The Capex dashboard provides "actual" status and cost of projects allowing GBUs' controllers and project managers to keep track on all projects of its movement as and when needed. The dashboard also provides a "Cash Due" information where it shows the upcoming amount that needed to be pay to suppliers in coming months. |
| Tabs | Dashboard | CAPEX | CAPITAL SPEND | CAPITAL SPEND & CAPEX | My Page |
|---|---|---|---|---|---|
17KPis |
|
|
| General Dimensions |
|---|
|
Notes In Dashboard Tab
Capex (YTD) | It’s the amount paid during the current year. Amount is without tax. |
Capspend (YTD) | It’s the actual costs for the current year. Amount is without tax. |
Commitments (YTD) | It’s the current amount of the purchase requests and orders not yet received. Amount is without tax. |
Total Projects without Budget | This indicated the number of projects with movement during the selected period which are without Budget and percentage of these projects against total number of projects with movement during the selected period. By double clicking on this box in the dashboard, you will be able to see the list of projects that are without budget. |
Total projects > Budget | This indicates the total number of projects with movement during the selected period exceed Budget and percentages of these projects against total number of projects with movement during the selected period. By double clicking on this box in the dashboard, you will be able to see the list of projects that are over budget. |
Total projects "Late" | This indicates the number of projects with movement during the period that exceed the initial planned completion date and the percentage of these projects against total number of projects. By double clicking on this box in the dashboard, you will be able to see the list of projects that are late. |
Total projects "Inactive" | This indicates the number of projects that are inactive for more than 6 months and percentage of these projects against total number of projects. By double clicking on this box in the dashboard, you will be able to see the list of projects that are inactive. |
| Period of Analysis |
|---|
|
| Currencies |
|---|
|
|
Target Users
Finance
Controlling
Industrial
Authorization & Rights
All the accesses must be validated by the
GBU Finance or Industrial Directors
Authorisations' rights per GBU, Zone, Plant
Access form
CAPEX Management