The purpose of this document is to define the conversion approach to create Maintenance Strategy in S/4 HANA.

Legacy Plant Maintenance Maintenance Strategy is using a diverse range of formats across the different systems. There are instances where the same Maintenance Strategy is duplicated within and across sources, with informal words. This results in data inconsistency. As per SyWay design, Maintenance Strategy will be standardized.


Conversion Scope

The scope of this document covers the approach for converting active Maintenance Strategy from Legacy Source Systems into S/4HANA following the Maintenance Strategy Master Data Design Standard.


The data from legacy system includes:

  1. All legacy strategies & packages assigned to valid legacy

    • strategy Task Lists
    • Maintenance Items

The data from legacy system excludes:

  1. All legacy strategies & packages NOT assigned to any valid legacy
    • strategy Task Lists
    • Maintenance Items


List of source systems and approximate number of records 

SourceScope

Source Approx No. of Records

Target SystemTarget Approx

No. of Records

PF2, WP2

An initial extract will be provided to business to evaluate.

Additional data/records may be required and these will be constructed via DCT.

Enrichment of in-scope data may be required and will be added via transformation rules (business/technical).

352

S/4HANA

352

Additional Information

Multi-language Requirement

Not Applicable

Document Management

Not Applicable

Legal Requirement

Not Applicable

Special Requirements

Not Applicable




Target Design

The technical design of the target for this conversion approach.

TableFieldData ElementField DescriptionData TypeLengthRequirement






















Data Cleansing

IDCriticalityError Message/Report DescriptionRuleOutputSource System
1
Description must not be blankKTEXT is blankSTRAT, KTEXTDCT






Informal Words **

Group 1

Group 2

Group 3

Group 4

Group 5

*DNU

Delete

donot

Formerly

Old #

..

Deletion

DONT USE

From

Old[ ]

/

DELISTED

DON'T USE

Incorrect

PLEASE USE

?

Discontinued

Dup Use

Invalid

Pls Use

@

Disposable

DUPLICATE

New

Previously

^

DNU

-DUPLICATE

NOT ACTIVE

Replace

+

Do Not

DUPLICATION

not in use

Replaced

++

Do Not Re

Duplicidad

Not Used

RESERVED

£

Do Not Sell

Duplikat

NOT VALID

Retired

Defective

Do Not Use

Former

Obsolete

ZZDEL


Conversion Process

The high-level process is represented by the diagram below:

For sites that are not on SAP-PF2 and WP2 systems, collection will be done manually in the data collection template.

The high-level process for DCT is represented by the diagram below:

Data Privacy and Sensitivity


Extraction

Syniti will extract data from source system based on relevancy rule. This is done only ONCE at the start of the project.

The agreed Relevancy criteria is applied to the extracted records to identify the records that are applicable for the Target loads

Extraction Run Sheet

Req #Requirement DescriptionTeam Responsible

1

Syniti will extract data from source system based on relevancy rule. This is done only ONCE at the start of the project.

Syniti

2

The legacy data will then be used in Syniti Data construction page.

Syniti

Selection Screen

Selection Ref ScreenParameter NameSelection TypeRequirementValue to be entered/set

Not Applicable






Data Collection Template (DCT)

Target Ready Data Collection Template will be created for data with exception of some fields which require transformation as mentioned in the transformation rule.

Maintenance Strategy DCT Rules

Field Name
Field DescriptionRule
LegacySTRATCHAR(6)Legacy StrategyMandatory(Key)
LegacyKTEXTCHAR(30)Legacy DescriptionMandatory
LegacyZEIEHUNIT(3)Legacy Unit for the performance of maintenance tasksMandatory
STRATCHAR(6)StrategyS4/HANA value
KTEXTCHAR(30)DescriptionS4/HANA value
ZEIEHUNIT(3)Unit for the performance of maintenance tasksValues must exist in config table T006
LegacyHORIZ
Legacy Call horizon for maintenance plan calls
LegacyHORIZ_QUALIFIER
Legacy Calculation Type of Call Horizon
LegacyLEIEH
Legacy Maintenance strategy activity unit
LegacyZYK1G
Legacy Total cycle duration of a maintenance strategy
LegacyZYK2G
Legacy Total cycle duration of a maintenance strategy
LegacyZYK1K
Legacy Smallest step between two maintenance packages
LegacyZYK2K
Legacy Smallest step between two performance-based MaintPackages
LegacyANZP1
Legacy Number of MaintPackages in the MaintStrategy
LegacyANZP2
Legacy Number of MaintPackages in the MaintStrategy (performance)
LegacyTOLE1 Legacy Tolerance for Late Completion (%)
LegacyTOLE2
Legacy Tolerance for Early Completion (%)
LegacyVERS1
Legacy Shift Factor for Late Completion
LegacyVERS2
Legacy Shift Factor for Early Completion
LegacyTERMK
Legacy Scheduling indicator
LegacyFABKL
Legacy Factory calendar key
LegacyAUTHGR
Legacy Authorization Group

Extraction Dependencies

Item #Step DescriptionTeam Responsible

Not Applicable




Transformation

The legacy data is maintained in Syniti Data Construction page. All mapping is performed in Syniti Data Construction page.

Prepare target-ready data in the structure and format that is required for loading via prescribed Load Tool. This step also produces the load data ready for business to perform Pre-load Data Validation

Transformation Run Sheet

Item #Step DescriptionTeam Responsible

1

Obtain DCT Sign-off from Business

SyWay A2D Data Team

2

<Add steps from Syniti Migrate here>

SyWay A2D Data Team

3

Review and Validate Error and Preload Reports

SyWay A2D Data Team

4

Generate Load Files

SyWay A2D Data Team


Transformation Rules

All transformation and mapping is performed in Syniti Data Construction page.

Rule #Source systemSource TableSource FieldSource DescriptionTarget SystemTarget TableTarget FieldTarget DescriptionTransformation Logic





















Transformation Mapping

All transformation and mapping is performed in Syniti Data Construction page.
Mapping Table NameMapping Table Description


Transformation Dependencies

List the steps that need to occur before transformation can commence
Item #Step DescriptionTeam Responsible

1

Ensure DCT completeness

Business & SyWay A2D Data Team


Pre-Load Validation

Project Team

Completeness

TaskAction

Verify Record Count

SyWay A2D Data Team to verify that the total number of relevant records from the DCT is equal to the total number of records in the Preload and Load Sheets.


Accuracy

TaskAction

Conversion Accuracy

SyWay A2D Data Team to verify that all fields below meet pass the checks:

  1. Mandatory Fields

  2. Field and Value Mapping Correctness

  3. Null Checks

  4. Text Length Checks

Review Error Reports

Review and correct the errors. Achieve a zero-error record count as much as possible. Raise defects for data remediated and requiring a correction in the source data.


Business

Completeness

TaskAction

Verify Record Count

Business Data Owner/s to verify that the total number of relevant records from the the DCT is equal to the total number of records in the Preload and Load Sheets.


Accuracy

TaskAction

Conversion Accuracy

Business Data Owner/s to verify that all the data in the load table/file is accurate as per endorsed transformation/mapping rules (and signed-off DCT data).


Load

The load process includes:

  1. Execute the automated data load into target system using load tool or product the load file if the load must be done manually
  2. Once the data is loaded to the target system, it will be extracted and prepared for Post Load Data Validation

Load Run Sheet

Item #Step DescriptionTeam Responsible













Load Phase and Dependencies

Configuration

Item #Configuration Item






Conversion Objects

Object #Preceding Object Conversion Approach

list the exact title of the conversion object of only the immediate predecessor – this will then confirm the DDD (Data Dependency Diagram)




Error Handling

Error TypeError DescriptionAction Taken










Post-Load Validation

Project Team

Completeness

TaskAction

Verify Count

SyWay A2D Data Team to verify the record count created in target S/4 HANA by accessing post load reports in dspMigrate or standard reports from S/4 HANA.

Verify Logs

Check if there is data that failed to load and perform the necessary actions (e.g. register as post load issue or attempt to load the record again, etc.).


Accuracy

TaskAction

Conversion Accuracy

SyWay A2D Data Team to verify that the Maintenance Strategy data in target S/4 HANA were loaded correctly via dspMigrate post load reports or standard reports from S/4 HANA.


Business

Completeness

TaskAction

Verify Count

Download Post Load Reports from dspMigrate and verify that the record count loaded in the target S/4 HANA is the same count as of the endorsed load file.


Accuracy

TaskAction

Conversion Accuracy

Verify that the Maintenance Strategy data in target S/4 HANA were loaded correctly via dspMigrate post load reports or standard reports from S/4 HANA.


Key Assumptions

  • Master Data Standard is up to date as on the date of documenting this conversion approach and data load.
  • Maintenance Strategy is in scope based on data design and any exception requested by business.
  • Valid legacy data objects dependent on S4/HANA strategies have relevant S4/HANA strategy/packages mapped


See also

Change log

Version Published Changed By Comment
CURRENT (v. 4) Apr 02, 2026 13:43 ERGUIZA-ext, Pinky Love Changed Owner to Iesha
v. 205 Mar 03, 2026 13:16 TEE-ext, Paul
v. 204 Mar 03, 2026 12:03 TEE-ext, Paul
v. 203 Mar 03, 2026 08:57 TEE-ext, Paul
v. 202 Mar 03, 2026 08:29 TEE-ext, Paul
v. 201 Mar 03, 2026 06:44 TEE-ext, Paul
v. 200 Mar 03, 2026 06:31 TEE-ext, Paul
v. 199 Mar 03, 2026 06:26 TEE-ext, Paul
v. 198 Feb 27, 2026 12:45 TEE-ext, Paul
v. 197 Feb 27, 2026 12:30 TEE-ext, Paul

Go to Page History

Workflow history

Title Last Updated By Updated Status  
There are no pages at the moment.

  • No labels