Status

  Lead Approval

Owner
Stakeholders

Purpose

The purpose of this document is to define the conversion approach to create Maintenance Plan and Item in S/4 HANA.

Legacy Plant Maintenance Maintenance Plan and Item is using a diverse range of formats across the different systems. There are instances where the same Maintenance Plan and Item is duplicated within and across sources, with informal words. This results in data inconsistency. As per SyWay design, EAM Maintenance Plan and Item will be standardized.


Conversion Scope

The scope of this document covers the approach for converting active Maintenance Plan and Item from Legacy Source Systems into S/4HANA following the Maintenance Plan and Item Master Data Design Standard.

Maintenance Plan from legacy system is relevant if:

  1. have at least 1 valid maintenance Item

Maintenance Plan from legacy system is not relevant if:

  1. Maintenance plan marked for deletion

Maintenance Item within each maintenance plan is considered relevant if:

  1. It has at least 1 relevant material, FL or Equipment in ref object or item in object list based on material, FL and Equipment relevancy; and
  2. At least 1 valid task list based on task list relevancy

Object list within each relevant maintenance item will only include FL and Equipment that is relevant based on FL and Equipment Relevancy.


List of source systems and approximate number of records
SourceScope

Source Approx No. of Records

Target SystemTarget Approx

No. of Records

PF2, WP2

Maintenance Plan:

An initial extract will be provided to business to evaluate.

Additional data/records may be required and these will be constructed via DCT.

Enrichment of in-scope data may be required and will be added via transformation rules (business/technical).

69,594

S/4HANA 

69,594

PF2, WP2

Maintenance Items:

An initial extract will be provided to business to evaluate.

Additional data/records may be required and these will be constructed via DCT.

Enrichment of in-scope data may be required and will be added via transformation rules (business/technical).

73,310

S/4HANA 

73,310

Additional Information

Multi-language Requirement

EAM Class description will be made available in English.
Multi language is supported for EAM Class. Login via a different language will have its description displayed in the logon language if the language key is maintained in the Class.

Document Management

Long text and DIR are not covered in this document as they are defined as another data object.

Legal Requirement

Not Applicable

Special Requirements

Not Applicable




Target Design

Task List Data strictly adheres to the Master Data Standard. The complete information of the key fields that hold the Class information follows the Master Data Standard document that is located here <include hyperlink>.

The technical design of the target for this conversion approach.

MPLA - Maintenance Header

TableFieldData ElementField DescriptionData TypeLengthRequirement
MPLAWARPLWARPLMaintenance PlanCHAR12S
MPLAMPTYPMPTYPMaintenance plan categoryCHAR2R. Must exist in T399W
MPLASTRATSTRATMaintenance strategyCHAR6R. Must exist in T351
RMIPMMEHRFACH_ZMEHRFACH_ZMultiple counter planCHAR1NU
RMIPMWSETWSETCycle set for multiple counter planCHAR6NU
MPLAWPTXTWPTXTMaintenance Plan TextCHAR40R
MPLAVSPOSVERSCHPLUS
NUMC3C
MPLATOPOSTOLERPLUSTolerance for Late Completion (%)NUMC3C
MPLATONEGTOLERNEGTolerance for Early Completion (%)NUMC3C
MPLAVSNEGVERSCHNEGShift Factor for Early CompletionNUMC3C
MPLASFAKTSFAKTCycle modification factorDEC3(2)C
MPLAFABKLFABKLFactory calendar keyCHAR2NU
MPLAHORIZHORIZONTCall horizon for maintenance plan callsNUMC3R
MPLAHORIZ_QUALIFIEREAM_CC_CALLHORIZON_QUALIFIERCalculation Type of Call HorizonCHAR1R
MPLAABRHOABRHOScheduling PeriodNUMC3R
MPLAHUNITHUNITUnit in scheduling intervalUNIT3C
MPLACALL_CONFIRMCALL_CONFIRMOnly Create New Call Object After Completing PredecessorCHAR1C
MPLASTADTSTADTStart dateDATS8C
RMIPMZEITTIME_KNZIndicator for selection of time-based maintenanceCHAR1C
MPLASTICHTERMKNZScheduling indicatorCHAR1C
MPLAPLAN_SORTPLAN_SORTSort field for maintenance plansCHAR20R. Must exist in T399G
MPLABEGRUIAUTGTechnical object authorization groupCHAR4NU
RMIPMSTTAGMP_STTAGKey DateDATS8C
MPLAENDDT_FOR_SCHEDEAM_ENDDT_FOR_SCHEDEnd Date for SchedulingDATS8(0)C
MPOSWAPOSWAPOSMaintenance itemCHAR16(0)S
MPOSPSTXTPOSTXTItem Short TextCHAR40(0)R
MPLATPLNRTPLNRFunctional LocationCHAR30R. Must exist in IFLO
MPLAEQUNREQUNREquipment NumberCHAR18C. Must exist in EQUI
MPOSBAUTLBAUTLAssemblyCHAR40(0)NU
MPOSIWERKIWERKMaintenance Planning PlantCHAR4(0)S. Must exist in T399I
MPOSAUARTAUFARTOrder TypeCHAR4(0)R. Must exist in T003O
RMIPMGEWERKGEWRKMain work center for maintenance tasksCHAR8S
RMIPMWERGWWERGWPlant associated with main work centerCHAR4S. Must exist in T001W
MPOSPRIOKPRIOKPriorityCHAR1(0)R. Must exist in T356
MPOSGSBERGSBERBusiness AreaCHAR4(0)NU
MPOSPLNTYPLNTYTask List TypeCHAR1(0)R. Must exist in TCA01
MPOSPLNNRPLNNRKey for Task List GroupCHAR8(0)R
MPOSPLNALPLNALGroup CounterCHAR2(0)R
MPOSAPFKTAPFKTExecution factor for whole task listDEC3(0)C
MPOSANLZUANLZUSystem ConditionCHAR1(0)C
MPOSSERIALNRGERNRSerial NumberCHAR18NU
MPOSSERMATMATNRMaterial NumberCHAR40(0)NU
RMIPMOFFS1WOFFS1Maintenance package offsetCHAR22NU
RMIPMPAK_TEXTTXZYKLUSText for maintenance package/cycle (time/performance)CHAR30NU
MMPTPOINTIMRC_POINTMeasuring PointCHAR12C. Must exist in IMPTT
MMPTZYKL1DZYK_ZEITMaintenance package cycle/offsetFLTP16(16)S
MMPTZEIEHDZEIEHUnit for the performance of maintenance tasksUNIT3S. Must exist in T006
MITEM_OBJLIST_DEQUIPMENTEQUNREquipment NumberCHAR18(0)C. Must exist in EQUI
MITEM_OBJLIST_DFUNCTIONALLOCATIONFunctional locationTPLNR_UNCONVERTEDCHAR30(0)C. Must exist in IFLO


Data Cleansing

Work Order Data strictly adheres to the Master Data Standard. The complete information of the key fields that hold the Class information follows the Master Data Standard document that is located here <include hyperlink>.

IDCriticalityError Message/Report DescriptionRuleOutputSource System

1016-001

C1 

Invalid, Inactive or no maintenance item attached to Maintenance Plan 

Maintenance Plan as per Relevancy Criteria assigned with inactive or no Maintenance Items attached. 

Maintenance Item 

PF2, WP2

1016-002

C1

Invalid, Inactive or no Task List allocated to Maintenance Plan 

Maintenance Plan as per Relevancy Criteria assigned with a Task List which does not belong below:
1. Task List as per Relevancy Criteria 

Task List 

PF2, WP2

1016-003

C2

Active maintenance plans not triggered 

TBD 

Maintenance Plan Status 

PF2, WP2

1016-004

C3

Duplicate Maintenance Plan Items by Technical Object, Task List, Strategy, Description 

Maintenance Plan Items as per Relevancy Criteria where there is more than one Technical Object + Task List + Strategy + Description Combination. 

Technical Object, Task List, Strategy, Description 

PF2, WP2

1016-005

C1 

Invalid, Inactive or no Characteristic allocated to Maintenance Plan 

Maintenance Plan as per Relevancy Criteria assigned with a Characteristic which does not belong below:
1. Characteristic as per Relevancy Criteria 

Characteristic 

PF2, WP2

1016-006

C1 

Invalid, Inactive or no Class allocated to Maintenance Plan 

Maintenance Plan as per Relevancy Criteria assigned with a Class which does not belong below:
1. Class as per Relevancy Criteria 

Class 

PF2, WP2

1016-007

C1 

Invalid, Inactive or no Equipment or Functional Location allocated to Maintenance Plan 

Maintenance Plan as per Relevancy Criteria assigned with an Equipment or Functional Location which does not belong below:
1. Equipment as per Relevancy Criteria
2. Functional Location as per Relevancy Criteria 

Equipment, Functional Location 

PF2, WP2

1016-008

C1 

Invalid, Inactive or no Maintenance Strategy allocated to Maintenance Plan 

Maintenance Plan as per Relevancy Criteria assigned with a Maintenance Strategy which does not belong below:
1. Maintenance Strategy as per Relevancy Criteria 

Maintenance Strategy 

PF2, WP2

1016-009

C1 

Invalid, Inactive or no Work Centres linked to Maintenance Plans 

Maintenance Plan as per Relevancy Criteria assigned with a Work Centre which does not belong below:
1. Work Centre as per Relevancy Criteria 

Work Centre 

PF2, WP2

1016-010

C1

Invalid, Inactive or no Maintenance Plans linked to Maintenance Items 

Maintenance Item as per Relevancy Criteria assigned with no or inactive Maintenance Plan attached. 

Maintenance Plan 

PF2, WP2

1016-011

C1

Invalid or Inactive Measuring Point linked to Maintenance Plan 

Maintenance Plan as per Relevancy Criteria assigned with a Measuring Point which does not belong below:
1. Measuring Point as per Relevancy Criteria 

Measuring Point 

PF2, WP2

1016-012

C1 

Missing Maintenance Plan Descriptions 

Task List as per Relevancy Criteria where there are blank Task ListDescriptions. 

Maintenance Plan Description 

PF2, WP2

1016-013

C2

Maintenance Plan Descriptions with Informal Words 

Maintenance Plan as per Relevancy Criteria which contain [Informal Words] in the Maintenance Plan Description 

Maintenance Plan Description 

PF2, WP2

1016-014

C1 

Maintenance Plan and Item Plant incorrect. 

Maintenance Plan and Item as per Relevancy Criteria with Invalid Plant (T001W) 

Plant 

PF2, WP2

1016-015

C1

Maintenance Plan and Item UOM Missing / incorrect. 

Maintenance Plan and Item as per Relevancy Criteria with no UoM Assigned or Invalid UoM (T006) 

Unit of Measure 

PF2, WP2

1016-016

C1 

Invalid or no Planner Group linked to Maintenance Plan and Item 

Maintenance Plan and Itemas per Relevancy Criteria with no Planner Group Assigned or Invalid Planner Group (T024I) 

Planner Group 

PF2, WP2

1016-017

C1

Maintenance Plan and Item Technical object authorization group incorrect. 

Maintenance Plan and Item as per Relevancy Criteria with Invalid Authorization Group (T370F) 

Authorization Group 

PF2, WP2

1016-018

C2

Functional Item Planning Plant and Maintenance Plant are not the same. 

Maintenance Item as per Relevancy Criteria with Planning Plant <> Maintenance Plant 

Maintenance Plant, Planning Plant 

PF2, WP2

Informal Words **

Group 1

Group 2

Group 3

Group 4

Group 5

*DNU

Delete

donot

Formerly

Old #

..

Deletion

DONT USE

From

Old[ ]

/

DELISTED

DON'T USE

Incorrect

PLEASE USE

?

Discontinued

Dup Use

Invalid

Pls Use

@

Disposable

DUPLICATE

New

Previously

^

DNU

-DUPLICATE

NOT ACTIVE

Replace

+

Do Not

DUPLICATION

not in use

Replaced

++

Do Not Re

Duplicidad

Not Used

RESERVED

£

Do Not Sell

Duplikat

NOT VALID

Retired

Defective

Do Not Use

Former

Obsolete

ZZDEL


Conversion Process

The high-level process is represented by the diagram below:

For sites that are not on SAP-PF2 and WP2 systems, collection will be done manually in the data collection template.

The high-level process for DCT is represented by the diagram below:

Data Privacy and Sensitivity

Not Applicable


Extraction

Extract data from a source into . There are 2 possibilities:

  1. The data exists. connects to the source and loads the data into . There are 3 methods:
    1. Perform full data extraction from relevant tables in the source system(s).
    2. Perform extraction through the application layer.
    3. Only if Syniti Migrate cannot connect to the source, data is loaded to the repository from the provided source system extract/report.
  2. The data does not exist (or cannot be converted from its current state).  The data is manually collected by the business directly in Syniti Migrate. This is to be conducted using DCT (Data Collection Template) in Syniti Migrate

The agreed Relevancy criteria is applied to the extracted records to identify the records that are applicable for the Target loads

Extraction Run Sheet

Req #Requirement DescriptionTeam Responsible

1

Extract data from source system based on relevancy rule

SyWay Data Team

2

Google Sheet report pre-populated with WP2 and WP2 information to be generated based on relevancy criteria.

SyWay Data Team


Selection Screen

Selection Ref ScreenParameter NameSelection TypeRequirementValue to be entered/set
Not Applicable




Data Collection Template (DCT)

Target Ready Data Collection Template will be created for Maintenance Plan and Item data with exception of some fields which require transformation as mentioned in the transformation rule.

Maintenance Plan and Item DCT Rules

Field NameField DescriptionRule
ZHIS-WARPLLEGACY MAINTENANCE PLANReference information from WP2, WP2
MPLA-WARPLMAINTENANCE PLAN

Running number NNNNNNNN to NNNNNNNN for Maintenance Plan Category = XXX. 

MPLA-MPTYPMAINTENANCE PLAN CATEGORY
MPLA-WPTXTMAINTENANCE PLAN TEXT40 Char text

MPLA-WSTRA

MAINTENANCE STRATEGYMust be a valid strategy if not blank.
Must be the same strategy as the task list strategy

RMIPM-WSET

CYCLE SET

Drop down List (T351-STRAT where ANZP1 is blank)

Must be blank for non Multi Counter (Scheduling Indicator is not 4)

RMIPM-POINT

COUNTER

Must be blank for the following conditions:

  1. Strategy is blank
  2. Strategy is not blank, and Scheduling Indicator is not 3 (Performance based)

Extraction Dependencies

Item #Step DescriptionTeam Responsible

1

Ensure Syniti has the necessary connection and access to legacy servers 

Data

2

Ensure that the necessary cleansing activities in legacy sources are complete 

Data / Business 

3

Ensure that create, change and deletion of master data is freeze in legacy Production system 

Legacy IT 

4

Extraction of Equipment, Functional Location and Task list completed based on relevancy rule

Business


Transformation

The Target fields are mapped to the applicable Legacy field that will be its source, this is a 3-way activity involving the Business, Functional team and Data team. This identifies the transformation activity required to allow to make the data Target ready:

  1. Perform value mapping and data transformation rules.
    1. Legacy values are mapped to the to-be values (this could include a default value)
    2. Values are transformed according to the rules defined in
  2. Prepare target-ready data in the structure and format that is required for loading via prescribed Load Tool. This step also produces the load data ready for business to perform Pre-load Data Validation

Transformation Run Sheet

Item #Step DescriptionTeam Responsible

1

Obtain DCT Sign-off from Business

SyWay A2D Data Team

2

In dspMigrate, select the wave –R3 S/HANA – Plant Maintenance

Syniti

3

Go to Process Area Launch and Process the Object – Maintenance Plan

Syniti

4

Execute the transformation to prepare the target ttMPLA, ttMPOS, ttOBJK, ttMMPT

Syniti

5

Review and Validate Error and Preload Reports

SyWay A2D Data Team

6

Generate Load Files

Syniti


Transformation Rules

Rule #Source systemSource TableSource FieldSource DescriptionTarget SystemTarget TableTarget FieldTarget DescriptionTransformation Logic
1PF2, WP2MPLAHORIZ_QUALIFIER Calculation Type of Call HorizonS/4HANA MPLAHORIZ_QUALIFIER Calculation Type of Call HorizonIf no legacy data provided, default to "%"
2PF2, WP2MPLAABRHOScheduling PeriodS/4HANA MPLAABRHOScheduling PeriodIf no legacy data provided, default to "3YR"
3PF2, WP2MPLAHUNITUnit in scheduling intervalS/4HANA MPLAHUNITUnit in scheduling intervalIf no legacy data provided, default to "Yr"
4PF2, WP2MPLATPLNRFunctional LocationS/4HANA MPLATPLNRFunctional Location

Equipment field must be blank.
Functional Location CT = Task List CT.

System Generated if Equipment is Updated

5PF2, WP2MPLAEQUNREquipment NumberS/4HANA MPLAEQUNREquipment NumberCan be Blank only if FLOC is updated.
CT of the Equipment must match Task List CT
6PF2, WP2MPOSPLNALGroup CounterS/4HANA MPOSPLNALGroup CounterGroup - Group Counter CT must be same as the Technical Object CT
7PF2, WP2MPOSPOSTXTItem Short TextS/4HANA MPOSPOSTXTItem Short TextDescription shall be defined as Frequency + TOT + Asset Tag
8PF2, WP2MPLAMPTYPMaintenance plan categoryS/4HANA MPLAMPTYPMaintenance plan categoryDefault to "PM"
9PF2, WP2MPLAWPTXTMaintenance Plan TextS/4HANA MPLAWPTXTMaintenance Plan TextMaintenance Plan description must match Task list Description
10PF2, WP2MPOSAUFARTOrder TypeS/4HANA MPOSAUFARTOrder TypeDefault to "YA02"
11PF2, WP2MMPTPOINTMeasuring PointS/4HANA MMPTPOINTMeasuring PointUpdated if the first 2 Chars of the Strategy = 02. 
12PF2, WP2MPLAVSPOSShift Factor for Late CompletionS/4HANA MPLAVSPOSShift Factor for Late CompletionIf no legacy data provided, default to "0"
13PF2, WP2MPLATOPOSTolerance for Late Completion (%)S/4HANA MPLATOPOSTolerance for Late Completion (%)If no legacy data provided, default to "10%"
14PF2, WP2MPLAVSNEGShift Factor for Early CompletionS/4HANA MPLAVSNEGShift Factor for Early CompletionIf no legacy data provided, default to '0"
15PF2, WP2MPLATONEGTolerance for Early Completion (%)S/4HANA MPLATONEGTolerance for Early Completion (%)If no legacy data provided, default to "10%"
16PF2, WP2MPLASFAKTCycle modification factorS/4HANA MPLASFAKTCycle modification factorIf no legacy data provided, default to "1"
17PF2, WP2MPLACALL_CONFIRMOnly Create New Call Object After Completing PredecessorS/4HANA MPLACALL_CONFIRMOnly Create New Call Object After Completing Predecessor

If no legacy data provided, default to blank.

System Generated if Equipment is Updated

18PF2, WP2MPLASTADTStart dateS/4HANA MPLASTADTStart dateIf no legacy data provided, default to blank
19PF2, WP2RMIPMZEITIndicator for selection of time-based maintenanceS/4HANA RMIPMZEITIndicator for selection of time-based maintenanceIf no legacy data provided, default to "X"


Transformation Mapping

Mapping Table NameMapping Table Description

xtSTRAT

Xref for maintenance strategy. Fields: zLegacySTRAT, zLegacyKTEXT, STRAT, KTEXT

xtPOINT

Xref for measuring point. Fields: zLegacyPOINT, zLegacyPTTXT, POINT, PTTXT

xtMATNR

Xref for material number. Fields: zLegacyMATNR, MATNR

xtPLNNR

xref for task list. Fields: zLegacyPLNNR, PLNNR

Assembly

Legacy Assembly XREF table

xtTPLNR

Xref for functional location. Fields: zLegacyTPLNR, TPLNR

xtEQUNR

Xref for equipment number. Fields: zLegacyEQUNR, EQUNR

xtARBPL

Xref for Work Centre. Fields: zLegacyARBPL, ARBPL

Transformation Dependencies

List the steps that need to occur before transformation can commence
Item #Step DescriptionTeam Responsible

1

Ensure DCT tables completeness

SyWay A2D Data Team

2

Value Mappings are according to the latest design -<List of Value Mappings>

SyWay A2D Data Team


Pre-Load Validation

Project Team

Completeness

TaskAction

Verify Record Count

SyWay A2D Data Team to verify that the total number of relevant records from legacy systems and DCTs (if any) is equal to the total number of records in the Preload and Load Sheets.

Verify Data Integrity

SyWay A2D Data Team to verify that the total number of Operations per Work Oder header extracted from legacy systems and DCTs (if any) should be equal to the total number of operations identified in the Preload and Load Sheets


Accuracy

TaskAction

Conversion Accuracy

SyWay A2D Data Team to verify that all fields below meet pass the checks:

  1. Mandatory Fields
  2. Field and Value Mapping Correctness
  3. Null Checks
  4. Text Length Checks

Review Error Reports

Review and correct the errors. Achieve a zero-error record count as much as possible. Raise defects for data remediated and requiring a correction in the source data.


Business

Completeness

TaskAction

Verify Record Count

Business Data Owner/s to verify that the total number of relevant records from legacy systems and DCTs (if any) is equal to the total number of records in the Preload and Load Sheets.


Accuracy

TaskAction

Conversion Accuracy

Business Data Owner/s to verify that all fields below meet pass the checks:

  1. Mandatory Fields
  2. Field and Value Mapping Correctness
  3. Null Checks
  4. Text Length Checks


Load

The load process includes:

  1. Execute the automated data load into target system using load tool or product the load file if the load must be done manually
  2. Once the data is loaded to the target system, it will be extracted and prepared for Post Load Data Validation

Load Run Sheet

Item #Step DescriptionTeam Responsible

1

Obtain DCT Sign-off from Business

SyWay A2D Data Team

2

Syniti will provide load file

Syniti

3Go to <Load Tool>SyWay A2D Data Team
4Load 3 records for "Create Maintenance Plan" function (IP01) to validate if data is loaded successfully without errorsSyWay A2D Data Team
5Proceed with full load if step 4 is validatedSyWay A2D Data Team
6Validate few records loaded by accessing standard transactions from S/4HNA E.g. IP03SyWay A2D Data Team
7Generate post load report if step 6 is validatedSyWay A2D Data Team


Load Phase and Dependencies

Configuration

Item #Configuration Item

1

T399W - Maintenance plan category

2

T351 - Maintenance strategy

3

T399G - Maintenance Plan Sort Field details

4

Number Ranges for Work Plan & Item 

5

T357M - System Condition

6

T356 - Priorities details

7

T399I - Maintenance Planning Plants

8

T003O - Order Types details

9

T001W - Plants/Branches details

10

TCA01 - Task List Type

11

T006 - Units of Measurement details

Conversion Objects

Object #Preceding Object Conversion Approach

1002

EQUI - Equipment

1003

IFLO - Functional Location

1005

PLKO - Task List 

1012

IMPTT - Measuring point

1017

T351 - Maintenance Strategy

Error Handling

Error TypeError DescriptionAction Taken

Configuration

Invalid Maintenance Plan Category

Engage Functional team to expedite and fix the error in the system

Configuration

Invalid Planner Group

Engage Functional team to expedite and fix the error in the system

Configuration

Invalid Plant

Engage Functional team to expedite and fix the error in the system

Configuration

Invalid Planning Plant

Engage Functional team to expedite and fix the error in the system

Configuration

Invalid System Condition

Engage Functional team to expedite and fix the error in the system

Configuration 

Invalid Authorization Group

Engage Functional team to expedite and fix the error in the system

Configuration

Invalid Maintenance Activity Type

Engage Functional team to expedite and fix the error in the system

Configuration

Invalid Priority

Engage Functional team to expedite and fix the error in the system

Configuration

Invalid Notification Type

Engage Functional team to expedite and fix the error in the system

Configuration

Invalid Order Type

Engage Functional team to expedite and fix the error in the system

Invalid Data

Invalid Maintenance Strategy

Expedite whether the master data is changed in the system

Invalid Data

Invalid Work Centre

Expedite whether the master data is changed in the system

Invalid Data

Invalid Task List

Expedite whether the master data is changed in the system

Invalid Data

Invalid Functional Location

Expedite whether the master data is changed in the system

Invalid Data

Invalid Equipment

Expedite whether the master data is changed in the system


Post-Load Validation

Project Team

Completeness

TaskAction

Verify Count

SyWay A2D Data Team to verify the record count created in target S/4 HANA by accessing post load reports in dspMigrate or standard reports from S/4 HANA.

Verify Logs

Check if there is data that failed to load and perform the necessary actions (e.g. register as post load issue or attempt to load the record again, etc.).


Accuracy

TaskAction

Conversion Accuracy

SyWay A2D Data Team to verify that the Work order data in target S/4 HANA were loaded correctly via dspMigrate post load reports or standard reports from S/4 HANA.


Business

Completeness

TaskAction

Verify Count

Download Post Load Reports from dspMigrate and verify that the record count loaded in the target S/4 HANA is the same count as of the endorsed load file.


Accuracy

TaskAction

Conversion Accuracy

Verify that the EAM Work order data in target S/4 HANA were loaded correctly via dspMigrate post load reports or standard reports from S/4 HANA.


Key Assumptions

  • Master Data Standard is up to date as on the date of documenting this conversion approach and data load.
  • Maintenance Plan and Item is in scope based on data design and any exception requested by business.
  • All data cleansing and preparation has been completed.
  • Maintenance Plan collection timeline are the same as Equipment and Functional Location collection. Maintenance Plan collection needs to go hand in hand with equipment and functional location collection. Drop down for equipment and functional location in the maintenance plan DCT relies on the input in equipment and functional location DCT.
  • All Maintenance Plans and Items mapped to valid Technical Objects in S/4 HANA


See also

Change log

Version Published Changed By Comment
CURRENT (v. 27) Apr 27, 2026 09:55 ERGUIZA-ext, Pinky Love
v. 407 Apr 27, 2026 09:44 ERGUIZA-ext, Pinky Love
v. 406 Apr 27, 2026 09:43 ERGUIZA-ext, Pinky Love
v. 405 Apr 07, 2026 13:19 ERGUIZA-ext, Pinky Love CR0438: Update in Relevancy Criteria JEST Inactive Flag
v. 404 Apr 07, 2026 11:00 ERGUIZA-ext, Pinky Love
v. 403 Apr 07, 2026 10:59 ERGUIZA-ext, Pinky Love
v. 402 Apr 07, 2026 10:27 ERGUIZA-ext, Pinky Love CR0438: Update in Relevancy Criteria JEST Inactive Flag
v. 401 Apr 02, 2026 13:42 ERGUIZA-ext, Pinky Love
v. 400 Apr 01, 2026 15:07 MAHAJAN-ext, iesha CR0438
v. 399 Apr 01, 2026 13:05 MAHAJAN-ext, iesha Added details for CR 0438

Go to Page History

Workflow history

Title Last Updated By Updated Status  
There are no pages at the moment.

  • No labels