| Status | Revision in Progress |
|---|---|
| Owner | Maytingsari Tjahjo |
| Stakeholders |
The purpose of this document is to define the conversion approach to migrate the balance of Capex WBS from legacy system to S/4HANA.
All the financial transactions posted below will be migrated from legacy source systems (PF2 and WP2) into S/4HANA:
- Active CAPEX WBS element
- Closed CAPEX WBS element that have cost in current year
Group 1 Go live (1 July 2028):
- Accumulated balances up to 31 Dec 2027 (Prior Year)
- Accumulated balances from 1 Jan 2028 till 30 June 2028 (Current Year)
Group 2 Go live (1 Jan 2029):
- Accumulated balances up to 31 Dec 2027 (Prior Year)
- Accumulated balances from 1 Jan 2028 till 30 Dec 2028 (Prior Year)
This would allow full reporting for 2028 in S/4HANA for both go lives post go live. For audit purposes it will be easier to check 1 system for both go lives. Therefore, it's ideal to keep Group 1 and Group 2 aligned in terms of FY 2028 FY.
All these transactions will be totaled into the one single value and then be posted to the relevant WBS Elements in S/4HANA. The approach will also run SAP settlement to the relevant Asset Under Construction.
Conversion Scope
The scope of this document covers the approach for migrating below from Legacy Source Systems into S/4HANA:
- 1. Active CAPEX WBS element from Legacy Source Systems into S/4HANA.
Logic:
A. Table PRPS
Key in field "Company Code" in scope.
Field "AA element" (Account Assignment Element) = X
Result: Object numbers of WBS that are in company codes in scope.
B. Table JEST:
Field "Object number" = Key in the object numbers of WBS (from Step A)
Field "Status Inactive" = blank
Result: Object numbers with all status.
C. Each object number (WBS) could have more than 1 status. Filter each object number to see all the status belongs to it.
Then filter object number that do not have status I0046 (Closed) or IFO07 (Closed)
Result: Object numbers that do not have status I0046 (Closed) or IFO07 (Closed).
D. Table PRPS
Key in field "Object number" with the object number from Step C.
Result: WBS number that do not have status I0046 (Closed) or IFO07 (Closed). The balance of these WBS need to be migrated.
2. Closed CAPEX WBS element that have cost in current year must also be migrated. From a portfolio level perspective, there needs to be full current year costs to be able to track against the annual budget allocation.
Logic:
D. Table JEST:
Field "Object number" = Key in the object numbers of WBS (from Step A)
Field "Status Inactive" = blank
Result: Object numbers with all status.
E. Each object number (WBS) could have more than 1 status. Filter each object number to see all the status belongs to each object number.
Then filter object number that has status I0046 (Closed) or IFO07 (Closed).
Result: Object number with status I0046 (Closed) or IFO07 (Closed).
F. Table RPSCO:
Field "Object number" = Key in the object numbers of WBS (from Step E)
Field "Fiscal Year" = Current year
Field "Value Type" = 4
Result = Object numbers that have cost in current year. These WBS needs to be migrated.
G. Table PRPS
Key in field "Object number" with the object number from Step F.
Result: WBS number that has status Closed but has cost in current yet. The balance of these WBS need to be migrated.
All the relevant WBS Elements (after applying the approved relevancy rules) open as at end of last month before go live that have received primary and secondary transactions posted to the cost elements within the WBS Elements
- Primary transactions refer to original postings from all sources whether it is debit or credit.
- Secondary transactions refer to allocations from sources such as allocations from payroll, work orders, other WBS Elements or cost centers. These postings will be subject to any settlement rules set up in the individual WBS Element.
Group 1 Go live (1 July 2028):
- Accumulated balances up to 31 Dec 2027 (Prior Year).
- Accumulated balances from 1 Jan 2028 till 30 June 2028 (Current Year)
It is expected that the balance of the WBS Elements is zero on 31 Dec 2027 and 30 Jun 2028, implying that the settlement transactions will be equal to all the primary and other secondary transactions posted to the relevant WBS Element.
Group 2 Go live (1 Jan 2029):
- Accumulated balances up to 31 Dec 2027 (Prior Year)
- Accumulated balances from 1 Jan 2028 till 31 Dec 2028 (Prior Year)
It is expected that the balance of the WBS Elements is zero on 31 Dec 2027 and 30 Dec 2028, implying that the settlement transactions will be equal to all the primary and other secondary transactions posted to the relevant WBS Element.
The scope of this document will therefore extract the settlement transactions from each individual WBS Element to provide a base for posting to the S/4HANA WBS Elements as at end of last month before go live. The total of the transactions will be used to compare to the balance in the Asset Under Construction that is used for settlement. The total of the settlement transactions will also be reconciled against the total costs posted to the WBS Element to ensure that all costs have been captured. Therefore, the scope will extend to the reconciliation of the legacy AUC values.
It will also extend to the reconciliation of the Balance Sheet General ledger accounts that may have been used in the legacy systems for settlement rules. It is expected that all transactions that were settled to the AUC Recon General ledger account will need to be settled to newly created S/4HANA AUC. The design is to never use the General Ledger account in S/4HANA for direct settlements from the Project System module.
Below is the list of AUC classes for SyWay:
- Z1100 Intangible-AUC
- Z1101 Intangible-R&I under construction
- Z1300 Tangible-AUC
The data from legacy system includes:
The data from legacy system excludes:
There will be 3 SAP boxes:
a. CUI box (US, GB, DE)
b. China box
c. ROW (Rest of the World) box
Please refer to file "Entreprise Structure Catalog" to see which company codes fall under which SAP boxes.
In terms of data migration, below is the guideline:
- Non CUI objects : Migration to US system by Syniti
- CUI objects : Manual cleansing/separate migration cockpit (Syniti is not certified)
List of source systems and approximate number of records
| Source | Scope | Source Approx No. of Records | Target System | Target Approx No. of Records |
|---|---|---|---|---|
| Legacy systems | Project level exclusions based on following relevancy rules:
| S/4HANA | ||
| Legacy systems |
Exceptions:
| S/4HANA | ||
| DCT | Where legal entities do not use SAP to record their projects, the DCT will be used to collect the balance of Capex WBS element data. | TBC | S/4HANA | TBC |
PF2 and WP2 | Extraction of the Sender Credit values from settlement that uses primary cost elements for settlement (Table COSP) | ??? | S/4HANA | |
PF2 and WP2 | Extraction of the Sender Credit values from settlement that uses secondary cost elements for settlement (Table COSS) | ??? | S/4HANA |
Additional Information
Multi-language Requirement
N/A
Document Management
N/A
Legal Requirement
N/A
Special Requirements
Target Design
There are two types of costs in the WBS Elements:
- Costs that are sourced from primary and secondary cost elements.
- The secondary cost elements cannot be used to post costs to S/4HANA. In many cases, the secondary cost element will form part of the total for the WBS Element. These costs (Table COSS) must be considered but the use of a primary cost element will be used to post these costs to the WBS Element in S/4HANA. The Primary Cost Total (COSP) table in source system (PF2 and WP2) also shows the values that have been settled to the receiver, be it an Asset Under Construction (AUC) or a Cost Centre or a General Ledger Account. In this object 9032, the receiver is AUC.
There is no need to replicate the postings that have occurred in the source system. The value that has been settled to the receiver object can be used to post with a selected General Ledger account. The settlement can then also use this account to clear the balance at the level. The offset General Ledger account will still be used to balance the journal entries.
The technical design of the target for this conversion approach.
| Table | Field | Data Element | Field Description | Data Type | Length | Requirement |
|---|---|---|---|---|---|---|
Data Cleansing
There will be cleansing required outside of that handled in the following DCA’s
- 1024 - Project Definition (CAPEX, OPEX)
- 1026 - WBS - CAPEX, OPEX, Statistical
- 1021 - Portfolio
Cleansing will be required to assist in the identification of values settled to the Balance Sheet accounts. Select the General Ledger Account to which value has been settled from either a WBS Element or an Internal Order.
In S/4HANA, settlement of costs from a WBS Element to an AUC General Ledger Account is not allowed. Syway will not be migrating any costs in those GL accounts to S/4HANA, so it is expected that any transactions resulting in a balance be transferred out of these accounts.
For any GL account that represents an asset or an AUC, it is expected that the business will transfer these values to another GL account or create an AUC or a final asset to which these values will be posted. To facilitate and assist in that process from a migration perspective, a cleansing report will be required. The result will be a nil value left in those General Ledger Accounts.
| ID | Criticality | Error Message/Report Description | Rule | Output | Source System |
|---|---|---|---|---|---|
| Cleansing GL Settlement account | Can load but business process will fail | Settlement value to be cleared after posting to the Balance Sheet GL account | Amount settled from an Internal Order or WBS Element | WBS Element: Internal Order: Date Posted: Amount Settled: General Ledger Account: Value Cleared: Cleared to Object: Value to be Cleared: | PF2 and WP2 |
Should there be value left in the Balance Sheet account, please see section Extraction run sheet for legacy WBS element settling to GL account.
Conversion Process
The high-level process is represented by the diagram below:
Process | Activity |
Extract | Extract involves collecting data from the source. There are 2 possible methods at this stage of process: 1. If the source is a system, extract means to pull the required data from source systems into repository. There are 2 steps for this method: a. Perform full data extraction from relevant tables in the source system(s). b. Apply relevancy criteria for filtering the data that will be applicable according to target system. 2. If the source is not a system, the data will need to be manually collected by business. This is to be done using DCT (Data Collection Template). |
Transform | There are 2 steps of Transform activities that can happen: 1. Perform mapping and data transformation rules. Some data will need to be mapped to the to-be values and/or updated according to the rules as per design requirement in target system. 2. Prepare load-ready data in the structure and format that is required for loading via standard Load Tool. This step also produces the load data ready for business to perform Pre-load Data Validation. |
Load | This process includes: 1. Execute the automated data load into target system using load tool. Note: There may be some cases where the load is done manually as part of business activities. 2. Once the data is loaded to target system, it will be extracted out and prepared for Post Load Data Validation. |
Data Privacy and Sensitivity
N/AExtraction
Extract data from a source into . There are 2 possibilities:
- The data exists. connects to the source and loads the data into . There are 3 methods:
- Perform full data extraction from relevant tables in the source system(s).
- Perform extraction through the application layer.
- Only if ; cannot connect to the source, data is loaded to the repository from the provided source system extract/report.
- The data does not exist (or cannot be converted from its current state). The data is manually collected by the business directly in . This is to be conducted using DCT (Data Collection Template) in
The agreed Relevancy criteria is applied to the extracted records to identify the records that are applicable for the Target loads
Extraction Run Sheet for legacy WBS Elements settling to AUCs
| Req # | Requirement Description | Team Responsible | ||||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | Extract data from source systems based on the current relevancy rules that apply to the Project and WBS Element Master Data. For each relevant WBS Element extract the object number from source systems with WBS Elements from table PRPS. | Data Team | ||||||||||||||||||||||||||||||||||||||||||||
| 2. | The following tables will be used to extract the settlement data:
To ensure that all costs have been collected via these tables (COSP & COSS), run a report (transaction code CJI3) to extract all the costs posted to the WBS Element/s to reconcile against the totals extracted from table COSP & COSS. Compare and agree the reconciliation values before progressing further to the next steps. For each open Project, confirm that the final balance is zero which will ensure that the settlement costs represent all the postings (debit and credit) within the Project by WBS Element. Extract the transactions by business transaction type. Use table AUFK (for order master data) to reconcile the settlement costs against actual posting extracts (extract by year by period by settlement transaction for each Project. | Data Team | ||||||||||||||||||||||||||||||||||||||||||||
| 3. | Go to source systems (PF2 and WP2) Primary Costs Total (Table COSP)
Go to source system (PF2 and WP2) Secondary Costs Total (Table COSS)
From the above, system will generate report as below. The report will need to be summarized by object number as below: Group 1 Go live (1 July 2028):
Group 2 Go live (1 Jan 2029):
| Data Team | ||||||||||||||||||||||||||||||||||||||||||||
| 4. | Step #3 provides what needs to be posted for each WBS Element. These can be split across cost elements, but the proposal is to use one Cost Element (TBD) for both posting and settlement. | Data Team | ||||||||||||||||||||||||||||||||||||||||||||
| 5. | Extract the Settlement Rule object from table COBRB in source systems (PF2 and WP2) to find the settlement objects for the above project.
System will provide a report as below that will include the following fields:
Extract the asset numbers from this report. | Data Team | ||||||||||||||||||||||||||||||||||||||||||||
| 6. | Extract the fixed asset values from table ANEP in source systems (PF2 and WP2) to check what has been posted to the Asset under Construction (AUC).
System will generate as below:
This report will need to be summarized by asset number as below: Group 1 Go live (1 July 2028):
Group 2 Go live (1 Jan 2029):
Check against the WBS Element postings (CJI3) before loading into S/4HANA.
| Data Team | ||||||||||||||||||||||||||||||||||||||||||||
| 7. | Run transaction code S_ALR_87011963 (Asset Balances report) for all AUC assets within the relevant company code. Check each individual asset balance before making any posting to a WBS Element. | Data Team | ||||||||||||||||||||||||||||||||||||||||||||
| 8. | Group 1 Go live (1 July 2028):
Once the AUC balance up to 31 Dec 2027 has been agreed, a posting will be required (document type 9*) and run settlement (CJ8G)
Once the AUC balance up from 1 Jan 2028-30 Jun 2028 has been agreed, a posting will be required (document type 9*) and run settlement (CJ8G) Group 2 Go live (1 Jan 2029):
Once the AUC balance up to 31 Dec 2027 has been agreed, a posting will be required (document type 9*) and run settlement (CJ8G)
Once the AUC balance up from 1 Jan 2028-31 Dec 2028 has been agreed, a posting will be required (document type 9*) and run settlement (CJ8G) | Data Team |
Extraction Run Sheet for legacy WBS Elements settling to GL accounts
| Req # | Requirement Description | Team Responsible | ||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | Extract data from source system (PF2 and WP2) based on the current relevancy rules that apply to the Project and WBS Element Data. Tables to be addressed are as follows: For each relevant WBS Element extract the object number from table PRPS | Data Team | ||||||||||||||||||||||||||||||
| 2. | Go to Table Primary Cost Total Table COSP in source systems (PF2 and WP2)
Provide a report or extract that will include the following fields
The report will need to be summarized by Object Number by total for all the fiscal years. | |||||||||||||||||||||||||||||||
| 3. | Step #2 provides what needs to be posted for each object number. Run table PRPS to see the WBS number for those object numbers. This is to be split across cost elements, but the proposal is to use one Cost Element for both posting and settlement. | Data Team | ||||||||||||||||||||||||||||||
| 4. | Review WBS Elements that have a Project type (table PRPS) that is not OPEX where the settlements are to General Ledger Accounts. | Data Team | ||||||||||||||||||||||||||||||
| 5. | Review all the legacy Object numbers and ensure that new WBS Elements have been created in S/4 HANA. Review the settlement rules for the new WBS Elements and ensure that a new AUC has been created for settlement. Create a report that shows what values will be posted to the new AUCs. This report will be required to verify what value is migrated for these General Ledger Accounts. The business will also need to be advised what new AUCs have been created for these WBS Elements. | Data Team and Business |
Selection Screen
| Selection Ref Screen | Parameter Name | Selection Type | Requirement | Value to be entered/set |
|---|---|---|---|---|
| N/A |
Data Collection Template (DCT)
A DCT will be required to collect the transactions posted to the WBS Elements/Project that are not in PF2 and WP2 but have been selected in the DCT for master data for Projects and WBS Elements – CAPEX. (DCT may not be required-TBC)
Target Ready Data Collection Template will be created for data with exception of some fields which require transformation as mentioned in the transformation rule.
DCT Rules
| Field Name | Field Description | Rules |
ACDOCA-POSID | WBS Element | To be prepopulated based on WBS element load with new WBS number. |
ACDOCA-WSL | Amount | For previous year actuals, total all transaction values and post as a single transaction with the posting date of the 31 Dec of the previous year. For current year actuals, total all transaction values by month and post as a single transaction with the posting date of the last month end of each month |
ACDOCA-BUDAT | Posting Date | For previous year actuals, total all transaction values and post as a single transaction with the posting date of the 31 Dec of the previous year. For current year actuals, total all transaction values by month and post as a single transaction with the posting date of the last month end of each month |
ACDOCA-POPER | Posting Period | Enter Posting Period. This should default in the DCT based on Posting Date |
ACDOCA-GJAHR | Fiscal Year | Enter fiscal year. This should default based on Posting Date |
ACDOCA-BLART | Document Type | Use Document Type 9* (as per config workbook) |
ACDOCA-BLDAT | Document Date | Same as Posting Date |
ACDOCA-BKTXT | Header Text | TBC |
ACDOCA-RBUKRS | Company Code | Enter Company Code |
ACDOCA-RACCT | GL Account | Default to GL XXXXX (TBC) |
ACDOCA-RWCUR | Currency | Enter Local Currency. Group currency will be calculated. |
ACDOCA-SGTXT | Item Text | Migration transaction TBC |
Extraction Dependencies
| Item # | Step Description | Team Responsible |
|---|---|---|
| 1. | All CAPEX WBS element cleansing has been completed in PF2 and WP2 | Business |
Transformation
The Target fields are mapped to the applicable Legacy field that will be its source, this is a 3-way activity involving the Business, Functional team and Data team. This identifies the transformation activity required to allow to make the data Target ready:
- Perform value mapping and data transformation rules.
- Legacy values are mapped to the to-be values (this could include a default value)
- Values are transformed according to the rules defined in
- Prepare target-ready data in the structure and format that is required for loading via prescribed Load Tool. This step also produces the load data ready for business to perform Pre-load Data Validation
Transformation Run Sheet
| Item # | Step Description | Team Responsible |
|---|---|---|
| 1. | In ADMM, select Object 9031 and launch this to execute transformation | Syniti Team |
| 2. | Perform transformation for all relevant WBS Elements. Legacy WBS Element is mapped to S/4HANA WBS elements in mapping table. | Syniti Team |
| 3. | Generate Pre-Load reports in ADMM for the extracted WBS Element amounts. | Syniti Team |
| 4. | Validate the transformed file as part of pre-load validation, raise data defects or provide the pre-load sign-off. | Business |
| 5. | Analyze and resolve any pre-load defects logged by business. | Data Team |
The fields required to be populated through the BAPI are as follows:
Section | Type | Example | Type | Number of Characters |
DOCUMENTHEADER | BUS_ACT | RFBU | C | 4 |
DOCUMENTHEADER | USERNAME | C | 12 | |
DOCUMENTHEADER | HEADER_TXT | Posting to WBS | C | 25 |
DOCUMENTHEADER | Company Code | C | 4 | |
DOCUMENTHEADER | Document Date | DATS | 8 | |
DOCUMENTHEADER | Posting date | DATS | 8 | |
DOCUMENTHEADER | Fiscal Year | Numeric | 4 | |
DOCUMENTHEADER | Fiscal Period | Numeric | 2 | |
DOCUMENTHEADER | Document Type | 9* | C | 2 |
ACCOUNTGL | ItemNO_ACC | 0000000001 | Numeric | 10 |
ACCOUNTGL | GL_ACCOUNT | GL expense (TBC) | C | 10 |
ACCOUNTGL | Item_Text | Test WBS | C | 50 |
ACCOUNTGL | WBS ELEMENT | C | 24 | |
ACCOUNTGL | ItemNO_ACC | 0000000002 | Numeric | 10 |
ACCOUNTGL | GL_ACCOUNT | C | 10 | |
ACCOUNTGL | Item_Text | Test WBS | C | 50 |
ACCOUNTGL | WBS ELEMENT | C | 24 | |
CURRENCYAMOUNT | ITEMNO_ACC | 0000000001 | Numeric | 10 |
CURRENCYAMOUNT | Currency | C | 2 | |
CURRENCYAMOUNT | AMT_DOCCUR | PACKED | 12 | |
CURRENCYAMOUNT | ITEMNO_ACC | 0000000002 | Numeric | 10 |
CURRENCYAMOUNT | Currency | C | 2 | |
CURRENCYAMOUNT | AMT_DOCCUR | PACKED | 12 |
Transformation Rules
| Rule # | Source system | Source Table | Source Field | Source Description | Target System | Target Table | Target Field | Target Description | Transformation Logic |
|---|---|---|---|---|---|---|---|---|---|
| 1. | PF2 and WP2 | COSP | OBJNR | Object Number | S/4HANA | ACDOCA | POSID | WBS Element Number | COSP Object Number will identify the WBS Element from PF2 and WP2 (PRPS table) which will map to the S/4HANA WBS Element identified in WBS mapping table. |
| 2. | PF2 and WP2 | COSS | OBJNR | Object Number | S/4HANA | ACDOCA | POSID | WBS Element Number | COSS Object Number will identify the WBS Element from PF2 and WP2 (PRPS table) which will map to the S/4HANA WBS Element identified in WBS mapping table. |
| 3. | PF2 and WP2 | COSP | BUKRS | Company Code | S/4HANA | ACDOCA | RBUKRS | Company Code | Mapping table from legacy company code to S/4HANA Company Code. |
| 4. | PF2 and WP2 | COSS | BUKRS | Company Code | S/4HANA | ACDOCA | RBUKRS | Company Code | Mapping table from legacy company code to S/4HANA Company Code. |
| 5. | PF2 and WP2 | PRPS | PRCTR | Profit Center | S/4HANA | ACDOCA | PRCTR | Profit Center | Map Legacy Profit Centre to the S/4HANA Profit Centers. |
| 6. | PF2 and WP2 | COSP | GJAHR | Fiscal Year | S/4HANA | ACDOCA | GJAHR | Fiscal Year | |
| 7. | PF2 and WP2 | COSS | GJAHR | Fiscal Year | S/4HANA | ACDOCA | GJAHR | Fiscal Year | |
| 8. | N/A | N/A | N/A | N/A | S/4HANA | ACDOCA | RACCT | Account Number | Use GL Account to post to the new WBS Element. TBC |
| 9. | PF2 and WP2 | COSP | WTGxx | Value Transaction Curr | S/4HANA | ACDOCA | POPER | Posting Period | |
| 10. | PF2 and WP2 | COSS | WTGxx | Value Transaction Curr | S/4HANA | ACDOCA | POPER | Posting Period | |
| 11. | N/A | S/4HANA | ACDOCA | BUDAT | Posting Date | ||||
| 12. | N/A | S/4HANA | ACDOCA | BLDAT | Document Date | ||||
| 13. | PF2 and WP2 | COSP | WTGxx | Value Transaction Curr | S/4HANA | ACDOCA | WSL | Amount in Transaction Currency | xx represents all periods for previous years. Value type (COSP-WRTTP) must be “4” and Dr/Cr Indicator (COSP-BEKNZ) set to “O - Special: Sender credit from settlement”. Once the data is collected the signage must be changed prior to posting. As most of the settlement amounts will be a negative amount, this value must be changed to a positive amount before posting back to the S/4HANA WBS Element. If the settlement amount is a positive value, it must be changed to a negative value. Logic will be required to determine the posting period from the field name WTGxxx, with xx being the posting month. E.g. 001,002,003, etc Note: Please ensure when extracting this field, it must read from column "Value" (not column "Value Unconverted"), because column "Value" is showing the correct value for all currencies (including currency with 0 decimal, such as JPY, KRW, etc)) In the table below, the column "Value" is showing the correct value (i.e. JPY 19.680.000)., but the amount in column "Value Unconverted" is incorrect (JPY 196.800). |
| PF2 and WP2 | COSP | WOGxx | Value in object currency (company code currency) | S/4HANA | ACDOCA | HSL | Amount in company code currency | xx represents all periods for previous years. Value type (COSS-WRTTP) must be “4” and Dr/Cr Indicator (COSP-BEKNZ) set to “O - Special: Sender credit from settlement”. Once the data is collected the signage must be changed prior to posting. As most of the settlement amounts will be a negative amount, this value must be changed to a positive amount before posting back to the S/4HANA WBS Element. If the settlement amount is a positive value, it must be changed to a negative value. Logic will be required to determine the posting period from the field name WOGxxx, with xx being the posting month. E.g. 001,002,003, etc Note: Please ensure when extracting this field, it must read from column "Value" (not column "Value Unconverted"), because column "Value" is showing the correct value for all currencies (including currency with 0 decimal, such as JPY, KRW, etc)) In the table below, the column "Value" is showing the correct value (i.e. JPY 19.680.000)., but the amount in column "Value Unconverted" is incorrect (JPY 196.800). | |
| PF2 and WP2 | COSP | WKGxx | Value in controlling area currency | S/4HANA | ACDOCA | KSL | Amount in global currency | To be confirmed what exchange rate to be used for loading amount in EUR (as legacy system does not have group currency) | |
| 14. | PF2 and WP2 | COSS | WTGxx | Value Transaction Curr | S/4HANA | ACDOCA | WSL | Amount in Transaction Currency | xx represents all periods for previous years. Value type (COSS-WRTTP) must be “4” and Dr/Cr Indicator (COSS-BEKNZ) set to “O - Special: Sender credit from settlement”. Once the data is collected the signage must be changed prior to posting. As most of the settlement amounts will be a negative amount, this value must be changed to a positive amount before posting back to the S/4HANA WBS Element. If the settlement amount is a positive value, it must be changed to a negative value. Logic will be required to determine the posting period from the field name WTGxx, with xx being the posting month. E.g. 01,02,03 Note: Please ensure when extracting this field, it must read from column "Value" (not column "Value Unconverted"), because column "Value" is showing the correct value for all currencies (including currency with 0 decimal, such as JPY, KRW, etc.) In the table below, the column "Value" is showing the correct value (i.e. JPY 8.774.093)., but the amount in column "Value Unconverted" is incorrect (JPY 87740.93)
|
| PF2 and WP2 | COSS | WOGxx | Value in object currency (company code currency) | S/4HANA | ACDOCA | HSL | Amount in company code currency | xx represents all periods for previous years. Value type (COSS-WRTTP) must be “4” and Dr/Cr Indicator (COSS-BEKNZ) set to “O - Special:Sender credit from settlement”. Once the data is collected the signage must be changed prior to posting. As most of the settlement amounts will be a negative amount, this value must be changed to a positive amount before posting back to the S/4HANA WBS Element. If the settlement amount is a positive value, it must be changed to a negative value. Logic will be required to determine the posting period from the field name WOGxx, with xx being the posting month. E.g. 01,02,03 Note: Please ensure when extracting this field, it must read from column "Value" (not column "Value Unconverted"), because column "Value" is showing the correct value for all currencies (including currency with 0 decimal, such as JPY, KRW, etc.) In the table below, the column "Value" is showing the correct value (i.e. JPY 8.774.093)., but the amount in column "Value Unconverted" is incorrect (JPY 87740.93) | |
| PF2 and WP2 | COSS | WKGxx | Value in controlling area currency | S/4HANA | ACDOCA | KSL | Amount in global currency | To be confirmed what exchange rate to be sued for loading amount in EUR | |
| 15. | N/A | S/4HANA | ACDOCA | BLART | Document Type | Default to UE? TBC | |||
| 16. | N/A | S/4HANA | ACDOCA | USNAM | User Name | Default to data migration user ID | |||
| 17. | N/A | S/4HANA | ACDOCA | SGTXT | Item Text | Specify legacy WBS Element | |||
| 18. | PF2 and WP2 | S/4HANA | ACDOCA | BKTXT | Header Text | Default to “Data Object 9031” | |||
| 19. | PF2 and WP2 | S/4HANA | ACDOCA | RACCT | Offsetting GL Account | Use the Offset GL Account used for GL Balance migration (GL account that is used for mapping AUC reconciliation account). Awaiting Alex to advise on the take-on account for AUC Please refer to table below (in this case, GL 299000) This will be used for migration for transactions that will eventually settle to AUC. |
Transformation Mapping
| Mapping Table Name | Mapping Table Description |
|---|---|
Company code | Mapping of legacy company code to S/4HANA company code |
Cost Centre | Map legacy Cost Centres to S/4HANA Cost Centres |
GL Accounts | Map legacy GL Accounts to S/4HANA GL Accounts |
Profit Centre | Map legacy Profit Centre to S/4HANA Profit Centre |
Fixed Asset Number | Map legacy Fixed Asset number to S/4HANA Fixed Asset number for CAPEX WBS Elements that have changed status to TECO |
WBS Elements | Map legacy WBS Elements to S/4HANA WBS Elements |
Currency | Map legacy currency to S4/HANA currency code |
Transformation Dependencies
List the steps that need to occur before transformation can commence| Item # | Step Description | Team Responsible |
|---|---|---|
| 1. | Ensure all the fields that require value mapping, as stipulated in Section "Mapping tables", have the correct values mapped. | Data Team |
Pre-Load Validation
Project Team
The following pre-load validations will be performed by Project Team.
This is to validate the total transactional movement in each open WBS Element. Validate the financial movement of all transactions excluding settlement transactions by WBS Element by Cost Element (GL Account) for the open WBS Elements as the closing balance.
Completeness
| Task | Action |
|---|---|
Verify Counts | Data team to verify the load count is the same as per identified data from Primary Cost Total COSP file and Secondary Cost Total COSS file. |
Validate | Validate that the extracted values from both tables agree with the total transaction costs excluding settlement for each individual WBS Element |
Accuracy
| Task | Action |
|---|---|
| Validate | Validate that the extracted values from both tables agree with the total transaction costs excluding settlement for each individual WBS Element |
| Validate | Validate that the extracted values are identical to those values settled to the Receiver. |
| Reconcile | Total by Asset number to compare to the WBS Element value to be posted. The value to be posted against the WBS Element must agree with the value shown for the relevant Asset Under Construction. See section "Extraction run sheet for legacy WBS element settling to AUCs. |
Business
The following pre-load validations will be performed by the Business.Completeness
| Task | Action |
|---|---|
| Verify counts | Business will use the preload report to validate the number of WBS Elements that will migrate values. |
Accuracy
| Task | Action |
|---|---|
| Validate | Validate that the extracted values are identical to those values posted to the WBS Element |
Load
Load Run Sheet
| Item # | Step Description | Team Responsible |
|---|---|---|
| 1. | Ensure Pre-Load signoffs are obtained. | Data Team |
| 2. | Load a small number of records to verify that the process is stable and will load all records as expected. | Syniti Team |
| 3. | If the above is successful, load all remaining records. | Syniti Team |
| 4. | If the above is unsuccessful, review errors and determine whether the error is data related, or system related. | Data Team |
| 5. | After correction, load corrected file or run corrected program to load data. | Syniti Team |
| 6. | Prepare report for Post Load Validation. | Syniti Team |
| 7. | Validate Post Load report. | Business |
Load Phase and Dependencies
Pre Cutover
Configuration
| Item # | Configuration Item |
|---|---|
| 1. | Asset Classes |
| 2. | Cost Element Groups |
| 3. | Settlement Profiles |
| 4. | Allocation Structures |
| 5. | Previous Asset Fiscal Year to be open |
| 6. | Settlement cost elements used for settlement available in all company codes in scope |
| 7. | Number ranges for settlement documents to be set up. This is manual config. |
Conversion Objects
| Object # | Preceding Object Conversion Approach |
|---|---|
| 1024 | Project Definition (CAPEX, OPEX) |
| 1025 | Project Text & Documents (attachments) |
| 1026 | WBS - CAPEX, OPEX, Statistical |
Error Handling
| Error Type | Error Description | Action Taken |
|---|---|---|
| Configuration | Document type does not exist in S/4HANA | Engage Functional team to fix the error in the system |
Post-Load Validation
Project Team
Completeness
| Task | Action |
|---|---|
| Verify counts | Data team to verify the load count is the same as per identified data from Pre Load file |
Accuracy
| Task | Action |
|---|---|
| Verify values | Ensure the Pre-Load report values are the same as in the Post Load Report. These values have to be verified before settling the costs to the AUCs. |
After validating the WBS Element transaction movements for count and accuracy, run settlement. This will provide balances to the AUCs.
AUC master will be created automatically once the WBS status is changed from CRTD (Created) to REL (Released) status.
Transaction code CJ88 will be used to settle all the WBS Element costs to their respective settlement objects. For those that are settling to the AUCs, a reconciliation must be done to compare the AUCs in the legacy system to those that are now in S/4HANA. Table ANLC will be used for this comparison.
The FA previous fiscal year cannot be closed until the AUC reconciliation for the previous year is completed.
Business
Completeness
| Task | Action |
|---|---|
Verify Counts | Business to verify the load count is the same as per identified data from Post Load Report. |
Accuracy
| Task | Action |
|---|---|
| Verify values | Ensure the Post Load report values are exactly the same as in the Pre Load report. These values have to be verified before settling the costs to the AUCs. |
Appendix:
Reconciliation process for Assets under Construction (AUC):
| Step | Description | Team responsible | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1. | Identify all AUC asset classesUse SAP Table ANKA – Asset Classes: General Data to identify all the AUC Asset Classes | Data Team | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
2. | Identify all assets under the AUC Asset ClassesApply the results from the above table to identify all assets in legacy systems in table ANLA that are classified as Assets Under Construction. | Data Team | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
3. | Identify all the above Assets Under Construction that have a previous year balance.The AUC may be restricted to only the ones with balances. Use table ANLC to gather year end balances. When running the report in Table ANLC it must run by Company Code by selected asset number. If it is run by asset number alone, all assets from across all regions will be selected. | Data Team | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
4. | Identify all the above Assets Under Construction that have a current year balance.Reconcile the results from the above report to identify any new AUC’s that may have been created in the current year. | Data Team | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
5. | Identify the monthly movements of all the above Assets Under Construction that have a previous or current year balanceUse table ANEP to extract all the monthly movements | Data Team | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 6. | This table shows all the fields that are to be extracted:
| Data Team | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 7. | Identify from which cost object the Asset Under Construction received financial postingsApply the asset number and company code to this table to receive the results. This will provide the cost object that will require the primary financial postings.
Explanation of the above fields:
This will provide the Object Number from which we can identify the real WBS Element in Table PRPS or the Internal Order number in table AUFK. | Data Team | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 8. | Settle the cost object financial postings to the new Asset Under ConstructionFrom there, these financial postings can be settled into the new S/4HANA AUC. The new AUC will be created when the cost object is released (from CRTD to REL). | Data Team | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 9. | Identify the cost object to which the settlement rule applies.Use table COBRB restricted to the WBS Elements selected above | Data Team | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 10. | Identify the internal and external financial postings in each WBS Element.Use tables COSP and COSS to collect the monthly movement by WBS Element by cost element by object currency. | Data Team |
Key Assumptions
- Master Data Standard is up to date as on the date of documenting this conversion approach and data load.
- is in scope based on data design and any exception requested by business.
- All WBS Elements will have a zero balance. If this is not true, there must be a BAU activity to ensure there is a zero balance.
- All costs in source system SAP-PE1 (Primary Costs Total Table COSP and Secondary Costs Total Table COSS) will represent the total transactional costs that have been posted to the respective WBS Element.
See also
Change log
Workflow history