The purpose of this document is to define the conversion approach to create Batches with Classification Data in S/4 HANA.
Batches are used extensively used in Syensqo Legacy System and used for below purposes.:
Quality Control
- Each batch can be tested and its quality attributes recorded. SAP enables linking quality results to specific batches, ensuring only compliant products are shipped.
Inventory Management
- Batches help manage inventory by expiration date, production date, or quality status.
- Enables First-Expired-First-Out (FEFO) or First-In-First-Out (FIFO) inventory strategies.
Production Efficiency
- Batches allow for detailed production planning and tracking.
Conversion Scope
The scope of this document covers the approach for converting active Batches & Classification Data from Legacy Source Systems into S/4HANA following the
Master Data Design Standard.
The data from legacy system includes:
- Batches in Stock
The data from legacy system excludes:
| Source | Scope | Source Approx No. of Records | Target System | Target Approx No. of Records |
|---|---|---|---|---|
| PF2 | Batches in Stock | |||
| WP2 | Batches in Stock | |||
Additional Information
Multi-language Requirement
NA
Document Management
NA
Legal Requirement
NA
Special Requirements
NA
NA
Target Design
The technical design of the target for this conversion approach.
| Table | Field | Data Element | Field Description | Data Type | Length | Requirement |
|---|---|---|---|---|---|---|
| MCHA | HSDAT | HSDAT | Date of Manufacture of the batch | |||
| MCHA | VFDAT | VFDAT | Shelf Life Expiration Date of the batch | |||
| MCHA | VERAB | VERAB | Batch available from date | |||
| MARA | IPRKZ | IPRKZ | Period indicator | |||
| MCHA | ZUSCH | ZUSCH | Unrestricted or Restricted | |||
| MCHA | ZAEDT | ZAEDT | Date of last status change | |||
| MCHA | QNDAT | QNDAT | Date of next inspection | |||
| MCH1 | LVORM | LVORM | Deletion flag at client level | |||
| MCHA | LVORM | LVORM | Deltion flag at plant level | |||
| MCHA | ZFDAT | ZFDAT | Date of certification | |||
| MCHA | LIFNR | LIFNR | Supplier number | |||
| MCHA | LICHA | LICHA | Supplier batch | |||
| MCHA | LWEDT | LWEDT | Date of last goods receipt | |||
| MCHA | HERKL | HERKL | Batch country of origin | |||
| MCHA | HERKR | HERKR | Region of origin | |||
| MCHA | MTVER | MTVER | Grouping of materials with similar instrastat requriements | |||
| MCHA | FVDT1 | FVDT1 | Date for free use | |||
| MCHA | FVDT2 | FVDT2 | Date for free use | |||
| MCHA | FVDT3 | FVDT3 | Date for free use | |||
| MCHA | FVDT4 | FVDT4 | Date for free use | |||
| MCHA | FVDT5 | FVDT5 | Date for free use | |||
| MCHA | FVDT6 | FVDT6 | Date for free use | |||
| AUSP | ATWRT | ATWRT | Value for each characteristic of class | |||
| MARA | MHDRZ | MHDRZ | Calculated remaining Shelf Life | |||
| MARA | MHDHB | MHDHB | Total shelf life | |||
| MARA | IPRKZ | IPRKZ | Period indicator from material | |||
| MARA | RDMHD | RDMHD | Rounding rule |
Data Cleansing
| ID | Criticality | Error Message/Report Description | Rule | Output | Source System |
|---|---|---|---|---|---|
Conversion Process
The high-level process is represented by the diagram below:
Data Privacy and Sensitivity
Extraction
Extract data from a source into . There are 2 possibilities:
- The data exists. connects to the source and loads the data into . There are 3 methods:
- Perform full data extraction from relevant tables in the source system(s).
- Perform extraction through the application layer.
- Only if ; cannot connect to the source, data is loaded to the repository from the provided source system extract/report.
- The data does not exist (or cannot be converted from its current state). The data is manually collected by the business directly in . This is to be conducted using DCT (Data Collection Template) in
The agreed Relevancy criteria is applied to the extracted records to identify the records that are applicable for the Target loads
Extraction Run Sheet
| Req # | Requirement Description | Team Responsible |
|---|---|---|
Selection Screen
| Selection Ref Screen | Parameter Name | Selection Type | Requirement | Value to be entered/set |
|---|---|---|---|---|
Data Collection Template (DCT)
Target Ready Data Collection Template will be created for data with exception of some fields which require transformation as mentioned in the transformation rule.DCT Rules
| Field Name | Field Description | Rule |
|---|---|---|
Extraction Dependencies
| Item # | Step Description | Team Responsible |
|---|---|---|
Transformation
The Target fields are mapped to the applicable Legacy field that will be its source, this is a 3-way activity involving the Business, Functional team and Data team. This identifies the transformation activity required to allow to make the data Target ready:
- Perform value mapping and data transformation rules.
- Legacy values are mapped to the to-be values (this could include a default value)
- Values are transformed according to the rules defined in
- Prepare target-ready data in the structure and format that is required for loading via prescribed Load Tool. This step also produces the load data ready for business to perform Pre-load Data Validation
Transformation Run Sheet
| Item # | Step Description | Team Responsible |
|---|---|---|
Transformation Rules
| Rule # | Source system | Source Table | Source Field | Source Description | Target System | Target Table | Target Field | Target Description | Transformation Logic |
|---|---|---|---|---|---|---|---|---|---|
Transformation Mapping
| Mapping Table Name | Mapping Table Description |
|---|---|
Transformation Dependencies
List the steps that need to occur before transformation can commence| Item # | Step Description | Team Responsible |
|---|---|---|
Extract PF2 & WP2 source tables – MCHA & AUSP | ||
Ensure all vendor master data collection templates, deduplication and cleansing completeness and no errors | ||
Ensure that Business Partner – General is loaded | ||
Ensure that all required Configurations are in S/4HANA |
Pre-Load Validation
Project Team
Completeness
| Task | Action |
|---|---|
| Verify DCT & Load File Count | SCM Data Team to verify that the total number of relevant records from the DCT is equal to the total number of records in the Preload and Load Sheets. |
Verify Consent | Verify the appropriate consents for the records have been obtained by the business/Data Owners and properly recorded |
Accuracy
| Task | Action |
|---|---|
Conversion Accuracy | SCM Data team to verify that all the data in the load table/file is accurate as per signed-off DCT contents and transformation rules with below checks:
|
| Review Error Reports | Review and correct the errors. Achieve a zero-error record count as much as possible. Raise defects for data remediated and requiring a correction in the source data. |
Business
Completeness
| Task | Action |
|---|---|
| Verify Record Count | Business Data Owner/s to verify that the total number of relevant records from the the DCT is equal to the total number of records in the Preload and Load Sheets. |
Verify Consent | Verify that the appropriate consents for the records have been obtained by the business and properly recorded |
Accuracy
| Task | Action |
|---|---|
Conversion Accuracy | Business Data Owner/s to verify that all the data in the load table/file is accurate as per endorsed transformation/mapping rules (and signed-off DCT data). |
Load
The load process includes:
- Execute the automated data load into target system using load tool or product the load file if the load must be done manually
- Once the data is loaded to the target system, it will be extracted and prepared for Post Load Data Validation
- Load approach: Migration Cockpit using Staging Tables
Load Run Sheet
| Item # | Step Description | Team Responsible |
|---|---|---|
1 | Ensure Pre-load sign-offs are obtained. | SCM Data team |
2 | Go to the load tool and select the correct load Program. | SCM Data team |
3 | Proceed with Data load. | SCM Data team |
4 | Validate few records loaded by accessing standard transactions. | SCM Data team |
5 | Generate the post load reports in the tool. | SCM Data team |
6 | Log errors as defects, if any and address resolutions. Close defects. | SCM Data team |
7 | Resolve defects by re-upload and re-generate post load reports if necessary. | SCM Data team |
8 | Business to validate the post load files as part of post-load validation, raise data defects or provide the post-load sign-off. | Business |
9 | Repeat steps 5 to 7 if necessary. | SCM Data team |
Load Phase and Dependencies
Configuration
| Item # | Configuration Item |
|---|---|
Conversion Objects
| Object # | Preceding Object Conversion Approach |
|---|---|
| 1 | |
| 2 | CNV-1046 Classes Type: 023 ( Batch) |
Error Handling
| Error Type | Error Description | Action Taken |
|---|---|---|
Configuration | <configuration> is not valid/missing | If it is a missing configuration item then engage Functional team to expedite and fix the error in the system. |
Invalid Data | <parameter> is not valid. | The parameter entry needs to be reviewed (ex. invalid payment terms). If it is an invalid data, business needs to review and correct the source of the data either in Legacy Systems PF2 and WP2 or if it’s mapped in DCT. |
Technical Setup | Interface / Connection issue within target system’s landscape | N/A – the data will be loaded directly to S/4HANA environment |
Authorisation Error | <USER ID> is not authorised to access Business Partner create | Contact Basis to obtain Fire Fighter ID or fix the authorisation setup |
Post-Load Validation
Project Team
Completeness
| Task | Action |
|---|---|
| Verify the count | Verify that the record count in the post-load file is the same as the record count based on the relevancy (including any deduplication) results |
Accuracy
| Task | Action |
|---|---|
Data Accuracy | SCM Data team to verify that all the data in the post load table/file is accurate as per signed-off transformation rules and DCT contents |
Error Reports | Verify that all necessary error reports have been validated, and that errors have been addressed. |
Data Consistency | Verify that the data loaded is correctly reflected in T-Code: MSC03N or Table: MCHA & AUSP. |
Business
Completeness
| Task | Action |
|---|---|
Verify Count | Verify that the record count in the post load file is the same as the record count based on the relevancy (including deduplication) results |
Validate Loaded Data | Validate, as per the load files signed-off, that all records were created |
Accuracy
| Task | Action |
|---|---|
Verify Data Accuracy | Verify that all the data in the target tables is accurate as per signed-off transformation rules and DCT contents |
Review Post Load Error Reports | Verify that all necessary post load error reports have been validated, and that errors have been addressed. |
Validate Loaded Data | Validate, as per the loads files signed-off, that all records are in the target system |
Key Assumptions
- The Master Data Standards document is a evolving document where value mappings/validation checks are still being finalized as we are currently in the detailed phase as of September 2025.
- Batch Master and Classification data is in scope based on data design and any exception requested by business.