Purpose
The purpose of this document is to define the conversion approach to create Bill of Material in S/4 HANA.
In Syensqo’s SAP S/4HANA environment, the Bill of Materials (BOM) defines the structured list of components required to perform a specific maintenance task, build an assembly, or manufacture a product. Each BOM represents a hierarchical breakdown of items - materials, assemblies, or parts - along with their respective quantities and usage context.
In the maintenance and asset management domain, three types of BOMs are utilized:
- Functional Location BOM – Linked to a specific technical location, outlining the parts typically required for maintenance activities at that location.
- Equipment BOM – Associated with a particular equipment asset, detailing spare parts and components relevant to its structure or maintenance.
- Material BOM – Tied to a material number, commonly used in manufacturing or for assemblies that are consumed or produced.
For rotable materials—such as repairable or reusable components—always refer to the corresponding Equipment or Functional Location Bill of Materials (BOM). Only components that are specific to that individual Equipment or Functional Location and not commonly used across other similar assets, should be included. This ensures that the BOM accurately reflects asset-specific configurations and supports targeted maintenance planning.
Conversion Scope
The scope of this document covers the approach for converting active Bill of Material from Legacy Source Systems into S/4HANA following the Bill of Material Master Data Design Standard.
A Bill of Materials (BOM) is a structured list of components, spare parts, or assemblies required for maintenance activities on technical objects like equipment or functional locations. It helps streamline maintenance planning, spare parts procurement, and work order execution.
The data from legacy system includes:
- BOM Category (STKO-STLTY):
- E-Equipment BOM (EQST-EQUNR) for relevant Equipment
- M-Material BOM (MAST-MATNR) for relevant Assembly
- T-Functional Location BOM (TPST-TPLNR) for relevant Functional Location
- BOM Usage (EQST-STLAN/MAST-STLAN/TPST-STLAN) = Plant Maintenance
- BOM Item Category (STPO-POSTP) = I, L, N or T
- Material BOM with the latest Alternative BOM (MAST-STLAL), if applicable
The data from legacy system excludes:
- BOM where the BOM Header (MAST-MATNR) is Assembly and all the BOM items (STPO-IDNRK) are Assembly
- BOM Header with deletion indicator checked (STKO-LKENZ="X")
- BOM Header with delecton flag checked (STKO-LOEKZ="X")
- BOM Item with deletion indicator checked (STPO-LKENZ="X")
- Previous Alternative BOM (MAST-STLAL) for Material BOM with more than one Alternative BOM
For further explanation, a Material BOM for relevant Assembly excludes BOM Assembly Header (MAST-MATNR) that are not assigned to Functional Location (IFLOT-SUBMT), Equipment (EQUZ=SUBMT) or Task List (PLKO-ISTRU).
The following are not in scope for BOM Conversion:
- Document Info Record
- Long Text
List of Tables to extract for this object is maintained here: Extract Table Register.
| Source | Scope | Source Approx No. of Records | Target System | Target Approx No. of Records |
|---|---|---|---|---|
PF2, WP2 | Relevant BOM will be extracted from PF2 and WP2 | 10,000 | S/4 HANA | 10,000 |
| DCT | BOM for plants which do not have data existing from PF2 and PF2 Additional BOM originating from PF2 and WP2 (if required). | 10,000 | S/4HANA | 10,000 |
Additional Information
Multi-language Requirement
Direct update of short text , log text in desired language i.e User log on language.
Document Management
Not Applicable
Legal Requirement
Not Applicable
Special Requirements
Not Applicable
Target Design
The technical design of the target for this conversion approach.
| Table | Field | Data Element | Field Description | Data Type | Length | Requirement |
|---|---|---|---|---|---|---|
Data Cleansing
| ID | Criticality | Error Message/Report Description | Rule | Output | Source System |
|---|---|---|---|---|---|
| 1001-001 | C1 | Invalid, Inactive or no Component linked to Bill of Material | Bill of Material as per Relevancy Criteria within a plant assigned with a Component which does not belong below: 1. Material Master (S2P) as per Relevancy Criteria within the same plant as BOM | BOM Header, Plant, BOM Item Number, Material | PF2/WP2 |
| 1001-002 | C2 | BOM Component Quantity is Zero or Negative. | Bill lof Material Component as per Relevancy Criteria with Value <= 0. | BOM Header, Plant, BOM Item Number, Material, Component Quantity | PF2/WP2 |
| 1001-003 | C3 | Functional Location BOM assigned to non-relevant Functional Location | Bill of Material for relevant Plant with BOM Category (T-Functional Location) and with no Deletion Indicator but are assigned to non relevant Functional Location | Functional Location, Plant, BOM Category, Usage | PF2/WP2 |
| 1001-004 | C3 | Equipment BOM assigned to non-relevant Equipment | Bill of Material for relevant Plant with BOM Category (E-Equipment) and with no Deletion Indicator but are assigned to non relevant Equipment | Equipment, Plant, BOM Category, Usage | PF2/WP2 |
| 1001-005 | C1 | Functional Location BOM with blank Plant | Bill of Material with BOM Category (T-Functional Location) assigned to relevant Functional Location with blank Plant | Functional Location, Plant, BOM Category, Usage | PF2/WP2 |
| 1001-006 | C1 | Equipment BOM with blank Plant | Bill of Material with BOM Category (E-Equipment) assigned to relevant Equipment with blank Plant | Equipment, Plant, BOM Category, Usage | PF2/WP2 |
| 1001-007 | C3 | Material BOM with previous Alternative BOM not migrated | Bill of Material with BOM Category (M-Material) with more than 1 Alternative BOM, report all the previous Alternative BOM except for the latest | Material, Plant, BOM Category, Usage, Alternative BOM | PF2,WP2 |
Conversion Process
The high-level process is represented by the diagrams below.
The following represents the high-level process for Source System Extraction:
The following represents the high-level process for DCT:
Data Privacy and Sensitivity
Extraction
Extract data from a source into . There are 2 possibilities:
- The data exists. connects to the source and loads the data into . There are 3 methods:
- Perform full data extraction from relevant tables in the source system(s).
- Perform extraction through the application layer.
- Only if ; cannot connect to the source, data is loaded to the repository from the provided source system extract/report.
- The data does not exist (or cannot be converted from its current state). The data is manually collected by the business directly in . This is to be conducted using DCT (Data Collection Template) in
The agreed Relevancy criteria is applied to the extracted records to identify the records that are applicable for the Target loads
Extraction Run Sheet
| Req # | Requirement Description | Team Responsible |
|---|---|---|
| 1 | Extract data from source system based on relevancy rule | Data Team |
| 2 | Google Sheet report pre-populated with PF2 and WP2 information to be generated based on relevancy criteria. | Data Team |
Selection Screen
| Selection Ref Screen | Parameter Name | Selection Type | Requirement | Value to be entered/set |
|---|---|---|---|---|
| Not Applicable | ||||
Data Collection Template (DCT)
Target Ready Data Collection Template will be created for data with exception of some fields which require transformation as mentioned in the transformation rule.DCT Rules
| Field Name | Field Description | Rule |
|---|---|---|
Extraction Dependencies
| Item # | Step Description | Team Responsible |
|---|---|---|
| 1 | Only BOM linked to relevant Functional Location should be extracted. | Data Team |
| 2 | Only BOM linked to relevant Equipment should be extracted. | Data Team |
| 3 | Only BOM linked to relevant Assembly should be extracted. | Data Team |
Transformation
The Target fields are mapped to the applicable Legacy field that will be its source, this is a 3-way activity involving the Business, Functional team and Data team. This identifies the transformation activity required to allow to make the data Target ready:
- Perform value mapping and data transformation rules.
- Legacy values are mapped to the to-be values (this could include a default value)
- Values are transformed according to the rules defined in
- Prepare target-ready data in the structure and format that is required for loading via prescribed Load Tool. This step also produces the load data ready for business to perform Pre-load Data Validation
Transformation Run Sheet
| Item # | Step Description | Team Responsible |
|---|---|---|
1 | Ensure all mapping tables are up to date. | Syniti |
2 | In dspMigrate, select the wave –R3 S4/HANA – Plant Maintenance | Syniti |
3 | Go to Process Area Launch and Process the Object – BOM | Syniti |
4 | Review and Validate Error and Preload Reports | Syniti |
5 | Execute the transformation to prepare the target tables | Syniti |
6 | Validate data from pre-load and invalid reports by region | Business/Data owner |
7 | Generate export(load) file (If load tool is not dspIntergrate) | Data Team |
Transformation Rules
| Rule # | Source system | Source Table | Source Field | Source Description | Target System | Target Table | Target Field | Target Description | Transformation Logic |
|---|---|---|---|---|---|---|---|---|---|
Transformation Mapping
| Mapping Table Name | Mapping Table Description |
|---|---|
Transformation Dependencies
List the steps that need to occur before transformation can commence| Item # | Step Description | Team Responsible |
|---|---|---|
Pre-Load Validation
Project Team
Completeness
| Task | Action |
|---|---|
Verify Record Count | Data team to verify that the total number of relevant records from the source systems is equal to the total number of records in the Preload and Load Sheets. |
Accuracy
| Task | Action |
|---|---|
Conversion Accuracy | Data team to verify that all fields below meet pass the checks: 1. Mandatory Fields 2. Field and Value Mapping Correctness 3. Null Checks 4. Text Length Checks |
Review error reports | Review and correct the errors. Achieve a zero-error record count as much as possible. Raise defects for data remediated and requiring a correction in the source data. |
Business
Completeness
| Task | Action |
|---|---|
Verify Record Count | Business team to verify that the total number of relevant records from the source systems is equal to the total number of records in the Preload and Load Sheets. |
Accuracy
| Task | Action |
|---|---|
Conversion Accuracy | Business to verify that all the data in the load table/file is accurate as per endorsed transformation/mapping rules (and signed-off data) |
Load
The load process includes:
- Execute the automated data load into target system using load tool or product the load file if the load must be done manually
- Once the data is loaded to the target system, it will be extracted and prepared for Post Load Data Validation
Load Run Sheet
| Item # | Step Description | Team Responsible |
|---|---|---|
Load Phase and Dependencies
Pre-Cutover
Configuration
| Item # | Configuration Item |
|---|---|
| 1 | T001W-Plants/Branches |
| 2 | T006-Units of Measurement |
| 3 | T415S-Bill of Material Status |
Conversion Objects
| Object # | Preceding Object Conversion Approach |
|---|---|
| 1003 | Functional Location |
| 1002 | Equipment |
| 2010 | Material - General Plant Data / SLoc Data |
| 1010 | Construction Type |
Error Handling
| Error Type | Error Description | Action Taken |
|---|---|---|
Post-Load Validation
Project Team
Completeness
| Task | Action |
|---|---|
Verify Count | Data team to verify the record count created in target S/4 HANA by accessing post load reports in dspMigrate or standard reports from S/4 HANA. |
Verify Logs | Check if there is data that failed to load and perform the necessary actions (e.g. register as post load issue, or attempt to load the record again, etc.). |
Accuracy
| Task | Action |
|---|---|
Conversion Accuracy | Data team to verify that the Measuring Point data in target S/4 HANA were loaded correctly via dspMigrate post load reports or standard reports from S/4 HANA. |
Business
Completeness
| Task | Action |
|---|---|
Verify Count | Download Post Load Reports from dspMigrate and verify that the record count loaded in the target S/4 HANA is the same count as of the endorsed load file. |
Accuracy
| Task | Action |
|---|---|
Conversion Accuracy | Verify that the Measuring Point data in target S/4 HANA were loaded correctly via dspMigrate post load reports or standard reports from S/4 HANA. |
Key Assumptions
- Master Data Standard is up to date as on the date of documenting this conversion approach and data load.
- is in scope based on data design and any exception requested by business.
Data cleansing has met the required percentage threshold for the specified mock cycle and all preparation activities have been completed.