The purpose of this document is to define the conversion approach to create Bill of Material in S/4 HANA.
In Syensqo’s SAP S/4HANA environment, the Bill of Materials (BOM) defines the structured list of components required to perform a specific maintenance task, build an assembly, or manufacture a product. Each BOM represents a hierarchical breakdown of items - materials, assemblies, or parts - along with their respective quantities and usage context.
In the maintenance and asset management domain, three types of BOMs are utilized:
- Functional Location BOM – Linked to a specific technical location, outlining the parts typically required for maintenance activities at that location.
- Equipment BOM – Associated with a particular equipment asset, detailing spare parts and components relevant to its structure or maintenance.
- Material BOM – Tied to a material number, commonly used in manufacturing or for assemblies that are consumed or produced.
For rotable materials—such as repairable or reusable components—always refer to the corresponding Equipment or Functional Location Bill of Materials (BOM). Only components that are specific to that individual Equipment or Functional Location and not commonly used across other similar assets, should be included. This ensures that the BOM accurately reflects asset-specific configurations and supports targeted maintenance planning.
Conversion Scope
The scope of this document covers the approach for converting active Bill of Material from Legacy Source Systems into S/4HANA following the Bill of Material Master Data Design Standard.
A Bill of Materials (BOM) is a structured list of components, spare parts, or assemblies required for maintenance activities on technical objects like equipment or functional locations. It helps streamline maintenance planning, spare parts procurement, and work order execution.
The data from legacy system includes:
- BOM Category (STKO-STLTY):
- E-Equipment BOM (EQST-EQUNR) for relevant Equipment
- M-Material BOM (MAST-MATNR) for relevant Assembly
- T-Functional Location BOM (TPST-TPLNR) for relevant Functional Location
- BOM Usage (EQST-STLAN/MAST-STLAN/TPST-STLAN) = Plant Maintenance
- BOM Item Category (STPO-POSTP) = I, L, N or T
- Material BOM with the latest Alternative BOM (MAST-STLAL), if multiple alternative BOMs exist
- BOM Component (STPO-IDNRK) for relevant Material / Assembly
- BOM Component (STPO-IDNRK) for non-Assembly is extended to the relevant plant based on the BOM Header Plant (TPST-WERKS/EQST-WERKS/MAST-WERKS)
- BOM Component (STPO-IDNRK) for non-Assembly, only Material Type (MARA-MTART) with the following to-be values based on Material Type Mapping:
- ZIND
- NLAG
- UNBW
The data from legacy system excludes:
- BOM with BOM Item where there is no relevant Material / Assembly in the Component field (STPO-IDNRK)
- BOM where the BOM Header (MAST-MATNR) is Assembly and all the BOM items (STPO-IDNRK) are Assembly
- BOM Header with deletion indicator checked (STKO-LKENZ="X")
- BOM Header with deletion flag checked (STKO-LOEKZ="X")
- BOM Item with deletion indicator checked (STPO-LKENZ="X")
- Previous Alternative BOM (MAST-STLAL) for Material BOM with more than one Alternative BOM
For further explanation, a Material BOM for relevant Assembly excludes BOM Assembly Header (MAST-MATNR) that are not assigned to Functional Location (IFLOT-SUBMT), Equipment (EQUZ=SUBMT) or Task List (PLKO-ISTRU).
The following are not in scope for BOM Conversion:
- Document Info Record
- Long Text
List of Tables to extract for this object is maintained here: Extract Table Register.
Scenarios for Migration for Legacy (PF2,WP2)
| Scenario | Legacy | To-Be |
|---|---|---|
1 | Functional Location BOM or Equipment BOM with at least 1 BOM Component which has relevant Material (not Assembly). | Migrate BOM as-is, with the legacy values mapped to the to-be values. |
| 2 | Material BOM (where Header is Assembly) and the Assembly is assigned to the Functional Location / Equipment / Task List. There is at least 1 BOM Component which has relevant Material (not Assembly). |
|
| Source | Scope | Source Approx No. of Records | Target System | Target Approx No. of Records |
|---|---|---|---|---|
PF2, WP2 | Relevant BOM will be extracted from PF2 and WP2 | 10,000 | S/4 HANA | 10,000 |
| DCT | BOM for plants which do not have data existing from PF2 and PF2 Additional BOM originating from PF2 and WP2 (if required). | 10,000 | S/4HANA | 10,000 |
Additional Information
Multi-language Requirement
Direct update of short text , log text in desired language i.e User log on language.
Document Management
Not Applicable
Legal Requirement
Not Applicable
Special Requirements
Not Applicable
Target Design
The technical design of the target for this conversion approach.
1. BOM Header
| Table | Field | Data Element | Field Description | Data Type | Length | Requirement |
|---|---|---|---|---|---|---|
| Fields specific to Functional Location BOM | ||||||
| TPST | TPLNR | TPLNR | Functional Location | CHAR | 30 | Mandatory for Functional Location BOM |
| TPST | WERKS | WERKS_D | Plant | CHAR | 4 | Mandatory for Functional Location BOM |
| TPST | STLAN | STLAN | BOM Usage | CHAR | 1 | Mandatory for Functional Location BOM |
| Fields specific to Equipment BOM | ||||||
| EQST | EQUNR | EQUNR | Equipment | CHAR | 18 | Mandatory for Equipment BOM |
| EQST | WERKS | WERKS_D | Plant | CHAR | 4 | Mandatory for Equipment BOM |
| EQST | STLAN | STLAN | BOM Usage | CHAR | 1 | Mandatory for Equipment BOM |
| Fields specific to Material BOM | ||||||
| MAST | MATNR | MATNR | Material Number | CHAR | 40 | Mandatory for Material BOM |
| MAST | WERKS | WERKS_D | Plant | CHAR | 4 | Mandatory for Material BOM |
| MAST | STLAN | STLAN | BOM Usage | CHAR | 1 | Mandatory for Material BOM |
| Generic fields for BOM Header | ||||||
| STKO | DATUV | DATUV | Valid-From Date | DATS | 8 | Mandatory |
| STKO | BMENG | BASMN | Base quantity | QUAN | 13 | Mandatory |
| STKO | STLST | STLST | Bill of Material Status | CHAR | 2 | Mandatory |
2. BOM Item
| Table | Field | Data Element | Field Description | Data Type | Length | Requirement |
|---|---|---|---|---|---|---|
| STPO | POSNR | SPOSN | BOM Item Number | CHAR | 4 | Mandatory |
| STPO | POSTP | POSTP | Item category (bill of material) | CHAR | 1 | Mandatory |
| STPO | IDNRK | IDNRK | BOM component | CHAR | 40 | Mandatory |
| STPO | MENGE | KMPMG | Component Quantity | QUAN | 13 | Mandatory |
| STZU | ZTEXT | CSTEXT | BOM Description | CHAR | 40 | Mandatory |
| STPO | POTX1 | POTX1 | BOM Item Text (Line 1) | CHAR | 40 | Conditional |
| STPO | POTX2 | POTX2 | BOM Item Text (Line 2) | CHAR | 40 | Conditional |
| STPO | SANKA | CS_SANKA | Indicator for Relevancy to Costing | CHAR | 1 | Mandatory |
| STPO | STKKZ | STKKZ | PM assembly indicator | CHAR | 1 | Conditional |
Data Cleansing
| ID | Criticality | Error Message/Report Description | Rule | Output | Source System |
|---|---|---|---|---|---|
| 1001-001 | C1 | BOM Component Quantity is Zero or Negative. | Bill of Material as per Relevancy Criteria with BOM Item where the Material is not blank and Quantity <= 0. | BOM Header, Plant, BOM Item Number, Material, Component Quantity | PF2/WP2 |
| 1001-002 | C3 | No Component linked to Bill of Material. These BOMs are not relevant for migration. | Bill of Material whereby there is no BOM Item with relevant Material / Assembly as BOM Component. | Functional Location, Equipment, Material, BOM Category, Usage | PF2/WP2 |
| 1001-003 | C3 | BOM with BOM Component which is not relevant. These BOMs are migrated but the selected components are not relevant for migration. | Bill of Material whereby the BOM Component is a Material and not relevant to be migrated. | Functional Location, Equipment, Material, BOM Category, Usage,Item Number, Item Category, Material Number, Quantity | PF2/WP2 |
| 1001-004 | C3 | Functional Location BOM assigned to non-relevant Functional Location. These BOMs are not relevant for migration. | Bill of Material for relevant Plant with BOM Category (T-Functional Location) and with no Deletion Indicator but are assigned to non relevant Functional Location. | Functional Location, Plant, BOM Category, Usage | PF2/WP2 |
| 1001-005 | C3 | Equipment BOM assigned to non-relevant Equipment. These BOMs are not relevant for migration. | Bill of Material for relevant Plant with BOM Category (E-Equipment) and with no Deletion Indicator but are assigned to non relevant Equipment. | Equipment, Plant, BOM Category, Usage | PF2/WP2 |
| 1001-006 | C3 | Functional Location BOM with blank Plant. For these BOMs, the Plant will be defaulted from the Functional Location Plant. | Bill of Material with BOM Category (T-Functional Location) assigned to relevant Functional Location with blank Plant | Functional Location, Plant, BOM Category, Usage | PF2/WP2 |
| 1001-007 | C3 | Equipment BOM with blank Plant. For these BOMs, the Plant will be defaulted from the Equipment Plant. | Bill of Material with BOM Category (E-Equipment) assigned to relevant Equipment with blank Plant | Equipment, Plant, BOM Category, Usage | PF2/WP2 |
| 1001-008 | C3 | Material BOM with previous Alternative BOM are not relevant for migration. | Bill of Material with BOM Category (M-Material) for relevant plant with more than 1 Alternative BOM, report all the previous Alternative BOM except for the latest | Material, Plant, BOM Category, Usage, Alternative BOM | PF2,WP2 |
| 1001-009 | C3 | Material BOM with at least one BOM Item with Stocked / Non-Stocked Material whereby the Header Material is not a relevant Assembly. These BOMs are not relevant for migration. | Bill of Material with BOM Category (M-Material) for relevant plant with 1 or more Stocked / Non-Stocked Material whereby the Header Material is not a relevant Assembly | Material, Plant, BOM Category, Usage, Alternative BOM, Item Number, Item Category, Material Number, Quantity | PF2, WP2 |
Conversion Process
The high-level process is represented by the diagrams below.
The following represents the high-level process for Source System Extraction:
The following represents the high-level process for DCT:
Data Privacy and Sensitivity
Not Applicable.Extraction
Extract data from a source into Syniti Migrate. There are 2 possibilities:
- The data exists. Syniti Migrate connects to the source and loads the data into Syniti Migrate. There are 3 methods:
- Perform full data extraction from relevant tables in the source system(s).
- Perform extraction through the application layer.
- Only if Syniti Migrate cannot connect to the source, data is loaded to the repository from the provided source system extract/report.
- The data does not exist (or cannot be converted from its current state). The data is manually collected by the business directly in Syniti Migrate. This is to be conducted using DCT (Data Collection Template) in Syniti Migrate
The agreed Relevancy criteria is applied to the extracted records to identify the records that are applicable for the Target loads.
Extraction Run Sheet
| Req # | Requirement Description | Team Responsible |
|---|---|---|
| 1 | Extract data from source system based on relevancy rule. | SyWay Data Team |
Selection Screen
| Selection Ref Screen | Parameter Name | Selection Type | Requirement | Value to be entered/set |
|---|---|---|---|---|
| Not Applicable |
Data Collection Template (DCT)
Target Ready Data Collection Template will be created for data with exception of some fields which require transformation as mentioned in the transformation rule.
Delta Data Management: Initial collection will be done via the report and one-time load to the DCT will be performed. Any delta after the initial collection within the DCT will require business to take due diligence to ensure any subsequent delta cleansing is verified and aligned within the DCT.
Note: All rules specified below should be documented as a tooltip in the DC Page.
Format:
- Line 1: Mandatory / Conditional
- Line 2: Remaining text
1. BOM Header Data Construction Rules
| Field Name | Field Description | Rule |
|---|---|---|
2. BOM Item Data Construction Rules
| Field Name | Field Description | Rule |
|---|---|---|
Note: List of DCTs is maintained here: Conversion Specs Register (DCT & Cleansing Report)
Extraction Dependencies
| Item # | Step Description | Team Responsible |
|---|---|---|
| 1 | Relevancy Criteria for Functional Location | SyWay A2D Data Team |
| 2 | Relevancy Criteria for Equipment | SyWay A2D Data Team |
| 3 | Relevancy Criteria for PM Assembly / Construction Type | SyWay A2D Data Team |
Transformation
The Target fields are mapped to the applicable Legacy field that will be its source, this is a 3-way activity involving the Business, Functional team and Data team. This identifies the transformation activity required to allow Syniti Migrate to make the data Target ready:
- Perform value mapping and data transformation rules.
- Legacy values are mapped to the to-be values (this could include a default value)
- Values are transformed according to the rules defined in Syniti Migrate
- Prepare target-ready data in the structure and format that is required for loading via prescribed Load Tool. This step also produces the load data ready for business to perform Pre-load Data Validation
Transformation Run Sheet
| Item # | Step Description | Team Responsible |
|---|---|---|
1 | Obtain DCT Sign-off from Business. | SyWay Data Team |
2 | In dspMigrate, select the wave – S4/HANA – Plant Maintenance | Syniti |
3 | Go to Process Area Launch and Process the Object – BOM | Syniti |
4 | Review and Validate Error and Preload Reports | Syniti |
5 | Execute the transformation to prepare the target tables | Syniti |
6 | Validate data from pre-load and error reports | Business/Data owner |
7 | Generate load files | Syniti |
Transformation Rules
| Rule # | Source system | Source Table | Source Field | Source Description | Target System | Target Table | Target Field | Target Description | Transformation Logic |
|---|---|---|---|---|---|---|---|---|---|
** TAKE NOTE:
- UOM difference
- Component after dedupe
Transformation Mapping
| Mapping Table Name | Mapping Table Description |
|---|---|
Material Type | Mapping of legacy Material Types to target system value |
List of Transformation Mappings with additional details is maintained here: Transformation Mappings
Transformation Dependencies
List the steps that need to occur before transformation can commence| Item # | Step Description | Team Responsible |
|---|---|---|
1 | Ensure DCT tables completeness | SyWay Data Team |
2 | Ensure all Transformation mappings are up to date. | SyWay Data Team |
Pre-Load Validation
Project Team
Completeness
| Task | Action |
|---|---|
Verify Record Count | Data team to verify that the total number of relevant records from the source systems is equal to the total number of records in the Preload and Load Sheets. |
Accuracy
| Task | Action |
|---|---|
Conversion Accuracy | Data team to verify that all fields below meet pass the checks: 1. Mandatory Fields 2. Field and Value Mapping Correctness 3. Null Checks 4. Text Length Checks |
Review error reports | Review and correct the errors. Achieve a zero-error record count as much as possible. Raise defects for data remediated and requiring a correction in the source data. |
Business
Completeness
| Task | Action |
|---|---|
Verify Record Count | Business team to verify that the total number of relevant records from the source systems is equal to the total number of records in the Preload and Load Sheets. |
Accuracy
| Task | Action |
|---|---|
Conversion Accuracy | Business to verify that all the data in the load table/file is accurate as per endorsed transformation/mapping rules (and signed-off data) |
Load
The load process includes:
- Execute the automated data load into target system using load tool or product the load file if the load must be done manually
- Once the data is loaded to the target system, it will be extracted and prepared for Post Load Data Validation
Load Run Sheet
| Item # | Step Description | Team Responsible |
|---|---|---|
1 | Ensure Pre-load sign-offs are obtained. | SyWay Data team |
2 | Go to the load tool and select the correct load Program. | SyWay Data team |
3 | Proceed with Data load. | SyWay Data team |
4 | Validate few records loaded by accessing standard transactions | SyWay Data team |
5 | Generate the post load reports in the tool. | SyWay Data team |
6 | Log errors as defects, if any and address resolutions. Close defects. | SyWay Data team |
7 | Resolve defects by reupload and re-generate post load reports if necessary. | SyWay Data team |
8 | Business to validate the post load files as part of post-load validation, raise data defects or provide the post-load sign-off. | Business |
9 | Repeat steps 5 to 7 if necessary. | SyWay Data team |
Load Phase and Dependencies
Pre-Cutover
Configuration
| Item # | Configuration Item |
|---|---|
| 1 | T001W-Plants/Branches |
| 2 | T006-Units of Measurement |
| 3 | T415S-Bill of Material Status |
Conversion Objects
| Object # | Preceding Object Conversion Approach |
|---|---|
| 1003 | Functional Location |
| 1002 | Equipment |
| 2010 | Material - General Plant Data / SLoc Data |
| 1010 | Construction Type |
Error Handling
| Error Type | Error Description | Action Taken |
|---|---|---|
Post-Load Validation
Project Team
Completeness
| Task | Action |
|---|---|
Verify Count | Data team to verify the record count created in target S/4 HANA by accessing post load reports in dspMigrate or standard reports from S/4 HANA. |
Verify Logs | Check if there is data that failed to load and perform the necessary actions (e.g. register as post load issue, or attempt to load the record again, etc.). |
Accuracy
| Task | Action |
|---|---|
Conversion Accuracy | Data team to verify that the Bill of Material data in target S/4 HANA were loaded correctly via dspMigrate post load reports or standard reports from S/4 HANA. |
Business
Completeness
| Task | Action |
|---|---|
Verify Count | Download Post Load Reports from dspMigrate and verify that the record count loaded in the target S/4 HANA is the same count as of the endorsed load file. |
Accuracy
| Task | Action |
|---|---|
Conversion Accuracy | Verify that the Bill of Material data in target S/4 HANA were loaded correctly via dspMigrate post load reports or standard reports from S/4 HANA. |
Key Assumptions
- Master Data Standard is up to date as on the date of documenting this conversion approach and data load.
- is in scope based on data design and any exception requested by business.
Data cleansing has met the required percentage threshold for the specified mock cycle and all preparation activities have been completed.
- Data entries in DCT are target-ready data unless a specific transformation rule is stated for that field in the transformation rules.
See also