Status

  Revision in progress

OwnerFRUTEAU-ext, Sabrina 
Stakeholders
Jira Request ID

ERP-131 Automated Close of Portfolio Item, Project & WBS

Jira Development IDERP-106 Automated Close of Portfolio Item, Project & WBS

High- Level Specification

ParameterValue
Application System

SAP S/4HANA - CUI instanceSAP S/4HANA - China instance

SAP S/4HANA - Rest of World instance
Business Process Reference10.02.04.01. Manage Project Settlement and Closure

Functional Overview

Over time, many PPM items and SAP Project System (PS) projects reach completion or become inactive but remain open in the system. This leads to administrative inefficiencies, a cluttered project portfolio, and potential compliance risks. To address these challenges, this enhancement proposes the automation of idle project closure. To address these issues, this enhancement introduces a program supporting 2 scheduled processes to manage idle projects and assets:

1. Projects Closure (Quarterly)

Run on a quarterly basis to identify inactive or idle projects, which have not been set to Closed status. The program will attempt to automatically close these projects if all closure criteria are met. If a project cannot be closed due to outstanding issues (such as open balances or commitments), the system will notify the responsible Financial Controller for further review and action. 

2. Pending Closure AuC (Monthly)

Run on a monthly basis to identify any idle Assets under Construction (AuC). The program will generate a consolidated notification listing all such AuCs that require attention and send it to the Asset Manager, enabling timely follow-up and resolution.


Scope and Objectives

This enhancement specifically targets SAP Project System (PS) projects that meet the following both criteria:

  • Project status is either "Technically Completed" (TECO)
  • No financial transactions have occurred for the past six months.

The scope includes:

  • Assessment of whether these projects can be fully closed in the system.
  • Notification to the responsible Financial Controller if closure is not possible due to outstanding issues (e.g., open balances or commitments).
  • Notification for regular review of idle Assets under Construction (AuC) to the Asset Manager.

The objectives are: 

  • Minimize erroneous postings by preventing transactions on inactive projects
  • Optimize reporting by ensuring only active and relevant projects appear as open
  • Maintain good data hygiene by keeping project data accurate, 
  • Highlighting non capitalized costs and POs or WOs left open.



Process Flow Diagram


  1. Inactive Project Closure Review
    (for SAP PS projects with no transactions for 6 months and status TECO)

Step

Description

Comment

1

3 possible scenarios:

  1. User/Person Responsible - Project: Completes all stage gates in the PPM item.
    • System: 
      • Sets PPM item status to TECO (Technically Completed).
      • Replicates PPM item status to the related SAP PS project.
    • SAP PS Project: Status is now TECO.

2. User/Responsible person - Project: Changes the PPM item status to TECO

    • System: 
      • Replicates PPM item status to the related SAP PS project.
    • SAP PS Project: Status is now TECO.

3. User/Responsible person - Project: No PPM item related to the SAP PS project. The User changes the SAP PS project status to TECO

The program only selects the SAP PS Projects with status = TECO
2

 Inactivity Period

  • No further transactions (financial or logistical) occur on the SAP PS project for X months.
X = Inactivity period defined as input parameter.
3

System (Scheduled Process): On a quarterly basis, scans for SAP PS projects with:

    • Status = TECO 
    • No transactions in the last 6 months
The program identifies the SAP PS projects in scope. 
4

Closure Attempt

The program checks if the eligible projects can be closed. 

  • If all closure criteria are passed:
    • System: Updates PS project status to CLSD (Closed).
    • PPM Item status to Closed or Cancelled/Closed
    • System: Notification to Financial Controller for successful project closure.
  • If closure criteria not fulfilled (e.g., open balances/commitments) and no Capitalization date maintained on the WBS element in the future:
    • System: Sends notification to the Financial Controller with project details and reason for failure.

 


2. Idle Asset Under Construction (AuC) Monitoring
(for periodic review and notification of AuCs with no recent activity)

Step

Description

Comment

1

AuC created and assigns it to a specific WBS element, linking it to a project.  Transactions are posted to the AuC as project activities occur.


2

 Inactivity Period: No further transactions (financial or logistical) occur on the AuC for X months.

X = Inactivity period defined as input parameter. 
3

The program compiles a consolidated list of all identified idle AuCs.

Sends a monthly consolidated notification to the Asset Manager with details of all idle AuCs requiring attention.

4

Asset Manager: Reviews the notification and takes appropriate follow-up actions (e.g., investigates, initiates settlement, etc...).

 



Assumptions

Dependencies

ERP-167 Sync Project Person Responsible & Applicant with HR Positions

ERP-174 Synch Status from PPM Item to PS Project/WBS

ERP-87 Automate Asset & Settlement Rule Creation - Workflow

Security, Integrity and Controls


Configuration Requirements

Language Requirements

Special Requirements


Design Rationale

Functional Requirements

This section describes the business process and decision logic for managing inactive SAP PS projects and idle Assets under Construction (AuCs). It outlines the key steps and criteria used to identify, review, and act on inactive projects and assets.
Please note that technical implementation details are provided separately in the Processing Logic section.

1. Scheduled Processing

  • The program runs in two modes:
    1. Inactive Project Closure Review: Conducted quarterly to identify and process inactive projects.
    2. Idle AuC Monitoring: Conducted monthly to identify and report on idle Assets under Construction.
  • The period of inactivity (default: six months) can be adjusted as needed (input parameter).
  • The program offers a test mode execution, which will issue a report with all the projects that can be closed and the ones that cannot. List the different reasons preventing the closure. See job log details in Handling Error section.

2. Inactive Project Closure Review

2.1. Identification of Inactive SAP PS Projects

    • The program identifies SAP PS projects that are no longer active, marked as “Technically Completed” TECO
    • Projects used solely for statistical or intercompany recharge purposes are excluded from this review.
    • Only projects and WBS elements with no recorded activity (actuals or commitments) in the past X months are considered inactive and subject to further review. X = Inactivity period. 

2.2 Closure Criteria Review:

    1. Attempt to close the WBS elements. Closure is only possible if all of the following conditions are met:

      • Outstanding Time Transfer Check: Confirm that all time bookings have been fully transferred to the relevant WBS elements
      • No open purchase orders or purchase requisitions
      • No open process or work orders
      • All linked assets under construction are fully capitalized or settled
      • The WBS element has a zero balance
      • No Capitalization date maintained on WBS element is the future
    2. Project Closure Action:

      • If all conditions are satisfied, the project status is set to closed. If the project is linked to a portfolio management item, its status is also updated to “Close.”
      • If any condition is not met, the project remains open and the reasons are documented in a notification to the Financial Controller (see section 4).

3. Idle AuC Monitoring

For each AuC assigned to a WBS element project:

  • Identify any AuCs that have not been fully capitalized or settled.
  • Identify last activity (posting) date.
  • If last activity date > Inactivity period and outstanding balance exist, send a consolidated notification to the Asset Manager (see section 4).

4. Notifications

  • Inactive Project Closure:
    Financial Controllers receive a consolidated notification listing:

    • Projects that were successfully closed
    • Projects that could not be closed, with reasons for each (e.g., open commitments, pending time transfers, unsettled assets)
    • Guidance on next steps and the date of the next scheduled review
  • Idle AuC Monitoring:
    Asset Managers receive a notification listing all identified idle AuCs, including relevant details and recommended actions.


  • If a responsible recipient cannot be identified, the issue is logged for further investigation.

  • See Processing logic for rules to derive email recipients. 

Proposed Technology to Use

Data Source Considerations

TableField NameComments/Calculation/Field Manipulation
PROJPSPNR, OBJNR, PROFLUsed to select the projects in scope
JESTOBJNR, STATSelect Projects which are set to status TECO
CATSCORPROJ, TRANSFERREDCheck if CATS time entries not transferred to WBS element
/RPM/ITEM_D ITEM_DIf SAP PS project id exists in this table, then there is a corresponding PPM item.
ACDOCAANLN1 Check if the AuC asset still has a balance
ANLAANLKLCheck the asset class = AuC.
COBRBOBJNR, COBRBIdentify assets linked to the related WBS element
PRPSUSR08, PSPHICapitalization date



Data Validation Considerations

TableField NameComments/Calculation/Field Manipulation













Custom Tables

Master Data

FieldDescriptionData Type/LengthValidation rule/ Value Help









Configuration Table

FieldDescriptionData Type/LengthValidation rule/ Value Help








Selection Screen Enhancement

Field NameDescription

Select:

Data Type/LengthDefault Value/ Validation rule/ Value HelpSelection Logic
Mode

2 options to select from: 

  1. Inactive project closure review
  2. Idle AuC Monitoring:
Options
None
Inactivity period (days)

Field used by the program to identify the projects to close or the idle AuC. 

The field can be a number of days.

Input fieldnumber 3 digits180 days (= 6 months)


Processing Logic

1. Scheduled Processing

The program can be executed in 2 modes: 

  1. Inactive project closure review: The identification and processing of inactive projects must occur quarterly.
  2. Idle AuC Monitoring: The identification and reporting of idle AuCs must occur monthly.

The Inactivity period (defined as 6 months in this FS) is set as an input parameter. 

2. Inactive project closure review

For each identified inactive project, the program:

2.1.Identification of Inactive SAP PS Projects

    • The program identify SAP PS projects with:
      • status TECO
        • JEST: Object Status (stores status information for objects like projects and WBS) STAT field = TECO
        • PROJ: Project Definition (main project header data)
        • Join the 2 tables to keep only project definitions.
        • Result: List of project definitions (IDs) that are TECO.
      • Exclude PS project with Project profile = PROJ-PROFL
ZPS0003Statistical Expense
ZPS0004Intercompany Recharges
ZPS0005Provisional Expense
    • Check that no transactions for the past 6 months: no Actuals nor Commitment posted on all of the related WBS elements. 

2.2 Checks if no outstanding time transfer 

All time booking is transferred to the WBS element (Time booked and time transfer completed).

Check table CATSCO

RPROJ = WBS element = Project id followed by * to obtain all WBS elements for a given project definition (Example, if the project id = A.000004, then search all RPROJ values starting with A.000004); 

TRANSFERRED = " "

If any records with Transferred = " ", then some records are still expected to be transferred. The project cannot be closed.

2.3 Attempt to set the project status to CLSD (Closed). Simulate a SAP PS Project status change to Closed. If not the below closure criteria are met, the system will prevent the closure and issue an error message.

No Open Commitments
 - Outstanding purchase orders
 - Outstanding purchase requisitions*
No Open R&I Process Orders
All process orders assigned to the WBS element are completed and closed in the system.
No Open Work Orders
All work orders (maintenance, production, or service) assigned to the WBS element are completed and closed in the system.

No Open AuC
Any assets under construction linked to the WBS element are fully capitalized or settled. 

Overall balance on WBS element = 0

Good receipt
Stock value fully settled and invoices processed.

*If Purchase requisitions are not replicated from Ariba to S4, no check at project closure is done. 

Use BAPIs below to simulate the project closure. Error messages will be provided if one of the above conditions are not fulfilled. 

BAPI_BUS2054_SET_STATUS 
BAPI_PS_PRECOMMIT

The BAPIs required to be initialized upfront with BAPI_PS_INITIALIZATION.  

No status change is saved at this point, this is only a simulation to identify the errors if any. 

2.4 If all the above criteria (2.and 2.2) are met, the project can be closed:

      • If the SAP PS project is related to a PPM id, the PPM item status be updated:
        • If PPM Item status = TECO/Cancelled => change PPM Item status to Closed/Cancelled.
        • If PPM Item status = TECO => change PPM item status to Closed. 

Check project id exist in /RPM/ITEM_D field ITEM_D

Function Module /RPM/ITEM_CHANGE - This function module allows to change attributes of a PPM item, including its status.

The status change to Close on the PPM item will be replicated to the SAP PS project. 

      • Else set the SAP PS project to status CLSD.
      • A consolidated notification is sent to the Financial Controller. See section 4.

2.4 If condition 2.1 and/or 2.2 are not fulfilled, the project will not be closed.

 Additionally if the Capitalization date (PRPS-USR08) is not maintained as a date in the future,  A notification is sent.

Notifications detailed in section 5 will be issued.

3. Idle AuC Monitoring

3.1. Identifying AuC Related to WBS
Use ANLA fields:
ANLN1 (Asset Number)
ANLN2 (Asset Subnumber)
POSNR (WBS Element)
ANLKL (Asset Class — to filter for AuC)
Filter where ANLKL corresponds to your AuC asset class and POSNR matches your WBS element.

3.2. Checking for the last Activity (identifying dormant AuC)
Use BUDAT (Posting Date) in ACDOCA.
If there are no entries for the asset in the last X months (X= Inactivity period), it meets inactivity criterion.

3.3. Checking Capitalization/Settlement
Analyze postings in ACDOCA for the asset to determine if it’s fully capitalized or settled.

Use FM FI_AA_VALUES_CALCULATE to determine if the calculated balance is zero, which indicates full settlement.

If there are still open balances or no settlement/capitalization postings, the asset is not fully settled.

3.4 If AuCs not fully capitalized/settled, send a notification to Asset Manager. Details in section 4. 

4. Notification

4.1. Inactive project closure review: 

A consolidated notification for each Financial Controllers highlighting: 

        • Projects that were closed by the program
        • Projects that could not be closed and the reasons.

Template email: 

Subject: Inactive Project Closure Review Results – [Processing Date]

Dear [Financial Controller, see section 4.3 for deriving Financial Controller],

As part of the regular review of inactive projects (PS status TECO and no activity in the past [Inactivity period] months), please find below the summary of closure attempts performed on [Processing Date].

1- Projects Successfully Closed

The following projects were successfully closed:

Project ID

Project Name/Description

...

...

2- Projects Not Closed

The following projects could not be closed. 

Project ID

Project Name/Description

Object (Order IDs, AuC, etc.)

Reason (SAP Error Message)

...

...

AuC: 1000000456

Error when processing asset under construction (AuC) for WBS element A
You cannot deactive asset 40000177 0.  (Please check.)    

...

...

WBS element id

Balance of WBS A.000046.01.02.02 is not zero

...

...

WBS element id

Pending CATS time entry records for transfer.*

*In this case the notification does not display the SAP error message, as no error is generated. Please use the mentioned reason. This occurs if condition 3.1 is valid.

Please review the reasons and take the necessary actions (e.g., settle balances, close orders, resolve AuC issues) to enable closure in the next review cycle.

Next scheduled review: [Next Review Date]


4.2 Idle AuC Monitoring:

A consolidated notification highlighting all the AuC which have not been 

Email template: 

Subject: Consolidated List of Idle Assets Under Construction (AuC) – [Processing Date]

Dear [Asset Manager, see section 4.3 for deriving Asset Manager],

As part of the periodic review of inactive AuC, the following Assets have been identified as inactive (no activity in the past [Inactivity period] months) and are not fully capitalized or settled.

Please review the list below and take appropriate action to settle or capitalize these assets as needed.

AuC NumberAuC DescriptionLinked WBS ElementProject IDOutstanding AmountCapitalization date
Identified AuC in section 4.Taken from table ANLA: input ANLN1 Asset number and retrieve  TXT50WBS element identified in section 4.Project ID identified in section 4.Section 4.3 - Use FM FI_AA_VALUES_CALCULATE to obtain the total outstanding amount.Maintained on the WBS element. Table PRPS field USR08.

4.3 Deriving email recipients

      • Financial controller: Financial controller position is stored in table PRPS, field ASTNR. From the position ID the SAP Personal ID can be derived through table HRP1001. Then obtain the email address through PA0105.
      • Asset Manager: Refer to FS ERP-87 Automate Asset & Settlement Rule Creation - Workflow.

4.4 Handling notification errors (No recipient derived)

If email recipients cannot be identified, no notification is sent, error is shown in the job error log report. 

Volumetrics

Unknown.


Performance Considerations



Error Handling

The job log report should:

  • Record the execution details of the program, including start and end times and selection criteria (Inactivity period).
  • Log the number of objects processed (e.g., number of projects with TECO status found).
  • List SAP PS projects successfully closed
  • List PPM items successfully closed
  • List SAP PS projects not closed and provide reason (error or pending timesheet transfer)
  • Capture any errors encountered during execution.
  • Provide an overview of the notifications sent (recipient, successful or failed)


Testing

How to Test


Test Conditions and Expected Results

IDConditionExpected Result
1

Prepare test data: 

  • Create some PPM items - complete first stage gate - create WBS element structure in SAP PS.
  • Create some SAP PS projects with WBS elements structure.
  • Assign to their WBS elements
    • WOs, some with settlement to WBS complete, some incomplete
    • Process Orders, some with settlement to WBS complete, some incomplete
    • AuCs, some fully capitalized, some not capitalized
    • AuCs not capitalized with capitalization date maintained on the WBS element in the future 
    • Indirect posting
    • CATS time entries some transferred, some not transferred.
  • Ensure that some committed cost is assigned to the some projects
  • Set your position id as Financial controller. 
Projects are created covering the various scenarios. 
2Execute the program in mode Inactive project closure review.

Expected projects are closed.

Expected PPM items are closed.

Notification is sent with the errors report for non closed projects and closed projects overview.

Records of all actions are included in the notification, including:

  • Projects processed
  • Closure attempts and results
  • Reasons for non-closure
  • Notification sent status

The job log should be reviewed for audit and troubleshooting.

3Execute the program in mode Idle AuC Monitoring

Notification is sent to the Asset Manager containing all inactive AuC.


Test Considerations/Dependencies


Other Information


Development Details

Package

Package NameParent Package




Enhancement Implementation

Enhancement TypeStandard Definition NameCustom Implementation NameDesign Rationale Reference









Other Development Objects

Object TypeObject NamePurpose/High Level LogicDesign Rationale Reference








Appendix

Custom Authorization Group Naming Convention

This table is based on the Syensqo development standards document. It provides the naming conventions for authorization groups to associated with custom reports and tables to comply with security requirements.

ABAP

ZFIZMMZPSZCOZSDZBCZFIZCA
TABLESZFITZMMTZPSTZCOTZSDTZBCTZFITZCAT

See also


No files shared here yet.

Change log

Version Published Changed By Comment
CURRENT (v. 49) Apr 23, 2026 13:32 FRUTEAU-ext, Sabrina
v. 123 Apr 14, 2026 05:44 FRUTEAU-ext, Sabrina
v. 122 Apr 13, 2026 08:29 FRUTEAU-ext, Sabrina
v. 121 Apr 13, 2026 07:31 FRUTEAU-ext, Sabrina
v. 120 Apr 10, 2026 07:22 FRUTEAU-ext, Sabrina
v. 119 Apr 10, 2026 07:17 FRUTEAU-ext, Sabrina
v. 118 Apr 10, 2026 06:58 FRUTEAU-ext, Sabrina
v. 117 Apr 10, 2026 06:54 FRUTEAU-ext, Sabrina
v. 116 Apr 09, 2026 07:54 FRUTEAU-ext, Sabrina
v. 115 Apr 09, 2026 07:52 FRUTEAU-ext, Sabrina

Go to Page History

  • No labels