Purpose
The purpose of this document is to define the conversion approach for Right of Use (ROU) assets Master and Transactional data in SyWay S/4 HANA. In ROU Fixed Assets migration both the master and transactional data will be migrated in one step. There will be only one SAP standard template which will be used for both the migration of the Master and Transactional data.
ROU Asset master consists of the following information:
- General information: Asset description, asset class, account determination, capitalization date etc.
- Time Dependent data: Cost Center, Plant, Location etc.,
- Depreciation terms data: Depreciation keys, Useful life and Depreciation areas
Conversion Scope
The scope of this document covers the approach for converting active ROU Assets from Legacy Source Systems into S/4HANA following the Master Data Design Standard DD-FUN-050 Master Data Standard_1070-Fixed Assets (incl. Sub Assets)
There are 2 group go-live as below:
- Group 1 go-live is planned for 1 July 2028
- Group 2 go-live is planned for 1 Jan 2029
RE-FX Contracts will be migrated to respective group go live as described in Enterprise Structure Catalog - Google Sheets (worksheet 10. Company code).
The data from legacy system includes:
The data from legacy system excludes:
| Source | Scope | Source Approx No. of Records | Target System | Target Approx No. of Records |
|---|---|---|---|---|
| PF2 | ROU Assets | 3,270 | S/4 HANA | Will be same as Source, unless any new Assets and/or deactivation of assets before Go-live |
| WP2 | ROU Assets | 1,044 | S/4 HANA | Will be same as Source, unless any new Assets and/or deactivation of assets before Go-live |
Additional Information
Multi-language Requirement
It was decided to apply approach below:
- Field “Description Line1” (ANLA-TXT50) = Migrate as it is from legacy system to S/4HANA. The description could be any languages (not only the 4 core languages but also any other non-core languages.
- Field “Description Line2” (ANLA-TXA50) = Migrate as it is from legacy system to S/4HANA. The description line 2 is used to add information on the description of the asset when the line 1 length is not enough.
- Field "Asset main no.text" (ANLH-ANLHTXT) must be in English
Document Management
N/A
Legal Requirement
There are no legal requirements relevant to data migration of ROU Assets
Special Requirements
N/A
Target Design
The technical design of the target for this conversion approach.
| Table | Field | Data Element | Field Description | Data Type | Length | Requirement |
|---|---|---|---|---|---|---|
ANLA | BUKRS | BUKRS | Company Code | CHAR | 4 | Mandatory |
ANLA | ANLN1 | ANLN1 | Main Asset number | CHAR | 12 | System generated number and mandatory |
ANLA | ANLN2 | ANLN2 | Asset sub-number | CHAR | 4 | System generated number and mandatory |
ANLA | ANLKL | ANLKL | Asset Class | CHAR | 8 | Mandatory |
ANLA | ZUJHR | DZUJAHR | Fiscal year in which first acquisition was posted | NUMC | 4 | Optional |
ANLA | ZUPER | DZUPER | Period in which first acquisition was posted | NUMC | 3 | Optional |
ANLA | ZUGDT | DZUGDAT | Asset value date of the first posting | DATS | 8 | Optional |
ANLA | AKTIV | AKTIVD | Asset capitalization date | DATS | 8 | Optional |
ANLA | DEAKT | DEAKT | Deactivation on | DATS | 8 | Optional |
ANLA | ORD41 | ORD41 | Evaluation group 1 | CHAR | 4 | Optional |
ANLA | ORD42 | ORD42 | Evaluation group 2 | CHAR | 4 | Optional |
ANLA | ORD43 | ORD43 | Evaluation group 3 | CHAR | 4 | Optional |
ANLA | ORD44 | ORD44 | Evaluation group 4 | CHAR | 4 | Optional |
ANLA | LIFNR | LIFNR | Account number of vendor (other key word) | CHAR | 10 | Optional |
ANLA | HERST | HERST | Manufacturer of asset | CHAR | 30 | Conditional |
ANLA | VMGLI | VMGLI | Property Classification Key | CHAR | 4 | Conditional |
ANLA | AIBN1 | AIBN1 | Original asset number or Original Group Asset number | CHAR | 12 | Mandatory |
ANLA | AIBN2 | AIBN2 | Original Sub-Asset | CHAR | 4 | Mandatory |
ANLA | AIBDT | AIBDT | Original Acquisition Date of AuC/ Transferred Asset | DATS | 8 | Optional |
ANLA | MENGE | AM_MENGE | Quantity | QUAN | 13 | Optional |
ANLA | MEINS | MEINS | Base unit of measure | UNIT | 3 | Conditional |
ANLA | INKEN | INKEN | Include asset in inventory list | CHAR | 1 | Mandatory |
ANLA | IVDAT | IVDAT_ANLA | Last Inventory on | DATS | 8 | Optional |
ANLA | INVZU | INVZU_ANLA | Inventory Note | CHAR | 15 | Optional |
ANLA | INVNR | INVNR_ANLA | Inventory Number | CHAR | 25 | Conditional |
ANLA | VBUND | RASSC | Company ID of Trading Partner | CHAR | 6 | Conditional |
ANLA | TXT50 | TXA50_ANLT | Asset description | CHAR | 50 | Mandatory |
ANLA | TXA50 | TXA50_MORE | Additional asset description | CHAR | 50 | Conditional |
ANLA | GDLGRP | GDLGRP | Evaluation group 5 | CHAR | 8 | Conditional |
ANLA | SERNR | AM_SERNR | Serial number | CHAR | 18 | Conditional |
ANLA | UMWKZ | AM_UMWKZ | Reason for Environmental Investment | CHAR | 5 | Conditional |
ANLB | AFABE | AFABE_D | Depreciation area | NUMC | 2 | Mandatory |
ANLB | AFABG | AFABG | Depreciation Start date | DATS | 8 | Optional |
ANLB | AFASL | AFASL | Depreciation Key | CHAR | 4 | Mandatory |
ANLB | NDJAR | NDJAR | Useful Life | NUMC | 3 | Optional |
ANLB | NDPER | NDPER | Useful Life (Period) | NUMC | 4 | Optional |
ANLB | SCHRW | SCHRW | Asset scrap value | CURR | 13 with 2 decimals | Conditional |
ANLB | SCHRW_PROZ | SCHRW_PROZ | Scrap value % | DEC | 14 | Conditional |
ANLB | ANLGR | ANLGR | Group asset | CHAR | 12 | Not used |
ANLZ | KOSTL | KOSTL | Cost Centre | CHAR | 10 | Mandatory |
ANLZ | PRCTR | PRCTR | Profit Centre | CHAR | 10 | System generated |
ANLZ | WERKS | WERKS_D | Plant | CHAR | 4 | Mandatory |
ANLZ | STORT | STORT | Location | CHAR | 10 | Optional |
ANLZ | RAUMN | RAUMNR | Room | CHAR | 8 | Optional |
ANLZ | KFZKZ | AM_KFZKZ | License Plate No. of Vehicle | CHAR | 15 | Optional |
ANLH | ANLHTXT | ANLHTXT | Asset main no. text | CHAR | 50 | Mandatory |
ANLZ | XSTIL | XSTIL | Asset shutdown indicator | CHAR | 1 | Optional |
Data Cleansing
| ID | Criticality | Error Message/Report Description | Rule | Output | Source System |
|---|---|---|---|---|---|
Conversion Process
The high-level process is represented by the diagram below:
Data Privacy and Sensitivity
Extraction
Extract data from a source into . There are 2 possibilities:
- The data exists. connects to the source and loads the data into . There are 3 methods:
- Perform full data extraction from relevant tables in the source system(s).
- Perform extraction through the application layer.
- Only if ; cannot connect to the source, data is loaded to the repository from the provided source system extract/report.
- The data does not exist (or cannot be converted from its current state). The data is manually collected by the business directly in . This is to be conducted using DCT (Data Collection Template) in
The agreed Relevancy criteria is applied to the extracted records to identify the records that are applicable for the Target loads
Extraction Run Sheet
| Req # | Requirement Description | Team Responsible |
|---|---|---|
Selection Screen
| Selection Ref Screen | Parameter Name | Selection Type | Requirement | Value to be entered/set |
|---|---|---|---|---|
Data Collection Template (DCT)
Target Ready Data Collection Template will be created for data with exception of some fields which require transformation as mentioned in the transformation rule.DCT Rules
| Field Name | Field Description | Rule |
|---|---|---|
Extraction Dependencies
| Item # | Step Description | Team Responsible |
|---|---|---|
Transformation
The Target fields are mapped to the applicable Legacy field that will be its source, this is a 3-way activity involving the Business, Functional team and Data team. This identifies the transformation activity required to allow to make the data Target ready:
- Perform value mapping and data transformation rules.
- Legacy values are mapped to the to-be values (this could include a default value)
- Values are transformed according to the rules defined in
- Prepare target-ready data in the structure and format that is required for loading via prescribed Load Tool. This step also produces the load data ready for business to perform Pre-load Data Validation
Transformation Run Sheet
| Item # | Step Description | Team Responsible |
|---|---|---|
Transformation Rules
| Rule # | Source system | Source Table | Source Field | Source Description | Target System | Target Table | Target Field | Target Description | Transformation Logic |
|---|---|---|---|---|---|---|---|---|---|
Transformation Mapping
| Mapping Table Name | Mapping Table Description |
|---|---|
Transformation Dependencies
List the steps that need to occur before transformation can commence| Item # | Step Description | Team Responsible |
|---|---|---|
Pre-Load Validation
Project Team
Completeness
| Task | Action |
|---|---|
Accuracy
| Task | Action |
|---|---|
Business
Completeness
| Task | Action |
|---|---|
Accuracy
| Task | Action |
|---|---|
Load
The load process includes:
- Execute the automated data load into target system using load tool or product the load file if the load must be done manually
- Once the data is loaded to the target system, it will be extracted and prepared for Post Load Data Validation
Load Run Sheet
| Item # | Step Description | Team Responsible |
|---|---|---|
Load Phase and Dependencies
The load phase for this object is Pre Cutover and this object will be loaded before RE-FX Contracts (object 9108) is loaded.
Configuration
The table below shows a key configuration elements
| Item # | Configuration Item |
|---|---|
1. | Company Code |
2 | Chart of Depreciation |
3 | Asset Class |
4 | Depreciation Areas |
5 | Depreciation Key |
6 | i) Soft Config - ROU Asset number ranges ii) Soft Config - Asset Data Transfer Configuration · Transfer date – Last day of the month prior to go-live · Legacy Data Transfer Status = In Preparation · Document type 9A |
Conversion Objects
| Object # | Preceding Object Conversion Approach |
|---|---|
| CNV-1073 | Profit Centre |
| CNV-1074 | Cost Centre |
Error Handling
The table below shows some possible system errors for this data object during data load. All data load error is to be logged as defect and managed within the Defect Management
| Error Type | Error Description | Action Taken |
|---|---|---|
Invalid Data | Relevant cost center is not valid in the validity of time dependent data in the ROU Asset master to be loaded. | Check whether the validity of time dependent data in cost center needs to be changed. |
Post-Load Validation
Project Team
The following post load validations will be performed by the project team.
Completeness
| Task | Action |
|---|---|
| Reconciliation of Total Record Count | Total number of records loaded for ROU Assets and Depreciation terms will be generated in the Post-load reports in ADMM. ROU Assets in the Post Load report is compared against total number of ROU assets in the pre-load reports by company code, Asset class, cost center, depreciation key etc., |
| Mandatory fields check | Review the post load file and note the records that failed the mandatory fields check and fix the errors |
| Post-load activity | Recalculate ROU Asset values using t.code AFAR |
Accuracy
| Task | Action |
|---|---|
| Check values in key fields for accuracy | Post-load reports will have the same structure as the load file and some additional columns as required to facilitate the post load validation. Leverage the Syniti ADMM tool to create a Post load report that reports S/4 HANA loaded records along with the legacy values side-by-side to allow for 100% check of all these fields in the shortest possible time. If any mismatch, they will report under 'Error' for corrective action. |
Business
The following post load validations will be performed by the business.
Completeness
| Task | Action |
|---|---|
| Record Count Check | Review the record count report from the Data Team and ensure it is correct by cross-checking with the record count confirmed during Pre-load Business Validations. |
Accuracy
| Task | Action |
|---|---|
| Spot checks | Business should choose some ROU Assets and perform comprehensive checks of the fields in S/4 HANA. Recommended to verify sample data per company code and Asset class combination. |
| Conversion Accuracy | Verify that the ROU Assets in target S/4 HANA are loaded correctly via load program and validate post load reports using standard t.code AR01 from S/4 HANA. |
Key Assumptions
- Master Data Standard is up to date as on the date of documenting this conversion approach and data load.
- is in scope based on data design and any exception requested by business.