3. Fill in all fields as described above4. Name the title of each section using OPD methodology naming convention - Infinitive verb without the “to”, mainly action verb...something) - " I do something..."5. Once the description of the operation is completed, ensure it is approved and published by launching the SBS-Finance approval workflow |
| Domain: Costing |
Responsibility area: Ensure Costing Allocations |
The objective of this operation is to guarantee that the delta FI-COPA inside COGS headings equals 0 at the end of the month during closure. It perform the necessary corrections based on defined and approved instructions and the necessary internal controls.
Definitions should be added in the Finance Glossary - Add definition and link it to respective Letter in Finance Glossary
See Finance Glossary:
In Z1K_Reconciliation we can enter directly inside of the documents by clicking in 1 of the documents below, depending on what we want to see:
|
In a general way, we might have several issues: FI posting without COPA posting
COPA posting without FI posting
Variance between the amount posted in FI and the amount posted in COPA for the same operation.
|
After performing the relevant checks and analyzing origins of differences, it is necessary to apply the appropriate corrections, according to this file. The corrections can be done via FI (this is the primary option that should be used almost everytime) or via COPA (in exceptional situations only), according to the type of difference. A check by plant/material can be done after corrections have been applied. At the end of the analysis and correction process, the gap should be equal or near 0. |
After performing the relevant checks and analyzing origins of differences, it is necessary to apply the appropriate corrections, according to this file. The corrections can be done via FI (this is the primary option that should be used almost everytime) or via COPA (in exceptional situations only), according to the type of difference. A check by plant/material can be done after corrections have been applied. At the end of the analysis and correction process, the gap should be equal or near 0. |