Quantity of production lost because of breakdowns or production stoppages caused by maintenance (OEE C2 and C4)
2/ Objective / Target
The set of strategic indicators has three main objectives: - Verification of the effectiveness of maintenance processes - Comparisons between plants independently from the business - Comparisons with external organizations
3/ Formula
Direct impact of maintenance on industrial performance = ( OEE category 2 losses + OEE category 4 losses ) x Economic contribution
Unit: local currency
Details of the formula: see "5/ SAP extraction and detailed calculation"
4/ Frequency
Depend of the plant
5/ SAP extraction and detailed calculation
Manual input of OEE losses from production report (Site template > Yearly tab)
- OEE category 2 losses : Amount of good product not delivered due to planned maintenance or planned capital installation
- OEE category 4 losses : Amount of good product not delivered due to breakdowns
- Economic contribution :
Contribution margin generated per produced unit (in local currency)