It calculates the delay for the portfolio of work orders issued from a maintenance plan and display by duration of delay.
3/ Formula
Number of work orders issued from maintenance plan delayed : ∑ Due date on the notification, or planned date on the call if WO isn't linked to a notification < snapshot extraction date
rate of delay :
- on time: ∑ work orders on time/ ∑ total number of WO - delay<1 month: ∑ work orders delayed<1 month/ ∑ total number of WO - 1<delay<3 month: ∑ work orders 1<delayed<3 month/ ∑ total number of WO - delay>3 months: ∑ work orders delayed>3 months/ ∑ total number of WO
4/ Frequency
Weekly
5/ SAP extraction and detailed calculation
Extraction is based on the calls from the maintenance plans from SAP, the indicator takes the work orders which are not yet executed. Due date is defined as the required end date on the notification, or as the planned date on the call if the work order isn't linked to a notification
Field name
From
To
I/E
No date for order status (GS45, GS50, GS55, 6CMP, CNF) or no reference date on the WO