Italian chemicals producer Versalis’ butadiene (BD) unit at Brindisi, Italy, is expected to be up and running by the end of this week, a company source said on Wednesday.
“We are in the process of restarting, we expect to produce within the coming days,” the source said.
Maintenance at the 145,000 tonnes/year facility was originally slated to take place at the end of August but was taken offline a couple of weeks earlier because of poor market conditions. Last week, another source had said the restart process had begun.
Versalis owns and operates two BD extraction units in Italy - the other is a 140,000 tonne/year unit in Ravenna, according to ICIS data.
SOURCE Icis News
Italian chemicals producer Versalis’ butadiene (BD) unit at Brindisi, Italy, is expected to be up and running by the end of this week, a company source said on Wednesday.
“We are in the process of restarting, we expect to produce within the coming days,” the source said.
Maintenance at the 145,000 tonnes/year facility was originally slated to take place at the end of August but was taken offline a couple of weeks earlier because of poor market conditions. Last week, another source had said the restart process had begun.
Versalis owns and operates two BD extraction units in Italy - the other is a 140,000 tonne/year unit in Ravenna, according to ICIS data.
SOURCE Icis News