Table of contents
Create a fixed costs report
This workbook gives the detail of all cost centers CBS & GBU.
Access the workbook
The workbook to be used is BW_WBK_OSC_0001 - ONE SYENSQO - Cost center Analysis
=> Go to Analysis for Office in excel
=> Click "Open Data Source"
Go to the tab "Role" and open the folder FC - GBU Fixed Cost
Double-click on the workbook BW_WBK_OSC_0001 - ONE SYENSQO - Cost center Analysis to open it
Open the workbook
It is mandatory to enter
- the conso view (1): by default, it is recommended to enter 0
- the cost center perimeter (2): by default, it is recommended to enter 1
- Fiscal Year/Period (5): MMM.YYYY
To avoid authorization issues, enter:
- the authorization scope (3): ECO (PO2 - BW - Authorization scopes).
It is also recommended to enter at least a GBU, a company code or a plant code (4)
It is also possible to enter:
- a target currency (7) for conversion. By default the exchange rate type is C but you can change it and replace by CAR3. (P&L - Exchange rates)
Variable Cost (6): you can include or exclude variable costs in your report. The determination of variable costs is based on Mixed Cost Center. By default variable costs are excluded with != X
Click "OK"
Set-up a basic report
Production fixed costs
In this example, the aim is to build a fixed costs report for the production plant Collonges (7622) in January 2024.
Enter in the prompt
- Fiscal Year/Period (5): 001.2024
- Responsible Plant (4): 7622
When you start working with the workbook, you see by default
- All cost centers
- All type of postings: fixed costs, depreciation, COPA
In order to filter Production fixed costs of the site, we must
- Exclude depreciation & COPA cost elements
- Filter production cost centers
Click the button "display" to show the "Design Panel"
- Filter ZCBS group 2 Function = EPRD (=production cost centers)
- Exclude cost elements groups
- ZSO-29993
- ZSO-29993B
- ZSO-IND31
- ZSO-IND41
- ZSO-IND42
- ZSO-IND51
You can watch the video to see how to do it.
How to understand the report
Once you have filter the production cost centers and excluded non fixed costs cost elements, look at the total "Actual - Destination"
It should be exactly the same amount as what you see in the P&L (KE30 - Profitability report), value field E01 Period fixed costs for the same selection (Period & plant)
In case of discrepancies go to FC - What are the main sources of discrepancies?
If there is no discrepancy you can build a report using the field you want.
SG&A
In this example, the aim is to build a SG&A report for the GBU Silica in Rhodia Operation (ZFR3) in January 2024.
Enter in the prompt
- Fiscal Year/Period (5): 001.2024
- BFC - GBU (4): SI
- Company code: ZFR3
In order to filter SG&A costs, we must
- Exclude depreciation & COPA cost elements
- Filter SG&A cost centers (2 Function = EADM & EMSV)
How to understand the report
Once you have filter the SG&A cost centers, look at the total "Actual - Destination"
It should be exactly the same amount as what you see in the P&L ( KE30 - Profitability report ),
- 2 Function = EADM = value field I25 G&A Adm.Expenses for the same selection
- 2 Function = EMSV = value field I15 G&A Com.Expenses for the same selection
In case of discrepancies go to FC - What are the main sources of discrepancies?
If there is no discrepancy you can build a report using the field you want.
Set-up a detailed report
when you have a good understanding of the report, you can add additional information in the report. You can refer to the list FC - Characteristics to have a definition of each dimension available in the report.
What are the main sources of errors?
What are the main sources of discrepancies between the BW fixed cost request and the P&L?
How-to group members
How can you create your own groups of ZCBS (cost centers) or ZSOLV (cost elements)
How to create a group of cost elements in a workbook
Example: you want to create your own group of cost elements:
- Labor
- Maintenance
- Others
The ZSOLV cost elements group is too detailed for your need, to you need to group some of the ZSOLV groups
Going further with Fixed costs reports
- FC - Create a fixed costs report — This page explains how you can create step-by-step a fixed costs report.
- FC - ONE SYENSQO - Cost center Analysis — This workbook gives the detail of all cost centers CBS & GBU.
- FC - Characteristics — List of Characteristics & Measures available in the BW Fixed costs application with the link to more detailed documentation when it exists.
- FC - Methodology to create a fixed costs report
- FC - What are the main sources of discrepancies? — What are the main sources of discrepancies between the BW fixed cost request and the P&L?
- FC - Cost centers master data — This page explains how you can display cost centers master data. It is a useful tool for preparing and validating master data to ensure the accuracy of fixed costs reports.
- FC - Fixed costs report - P&L impact — The P&L impact fixed costs query is used when a cost center is shared with several GBUs
- FC2 - Fixed costs (obsolete) (WBP) — This page explains how the application FC2 - Fixed costs was replaced by the application FC - GBU Fixed costs.
- FC - How-to group members — How can you create your own groups of ZCBS (cost centers) or ZSOLV (cost elements)
- FC - Internal Orders master data — This page explains how you can display CO orders master data. It is a useful tool for preparing and validating master data to ensure the accuracy of fixed costs reports.






































9 Comments
Annelore PEROUZE
Hello,
Can we have ZCBS Hierarchy in a Google sheet ?
Thank you
Annelore
Jean-Pierre Godbillon
SARMENTO, Filipe, I think that question is for you
ROLLIER, Charlotte
Yes it is a good idea. SARMENTO, Filipe let me know if you need help. Then we can embed the page in the Rules - Cost Center ZCBS hierarchy
Davide Bernardo
Hello ROLLIER, Charlotte, can you please clarify me about the timetable of refreshes (during month and closure period) of this cube.
Thanks in advance
ROLLIER, Charlotte
Ludovic DEPOIX do you know how often the query is refreshed ? Thanks
Ludovic DEPOIX
Davide Bernardo Everyday and 3 times per day during closing. i talk about the query GBU Fixed Costs
Davide Bernardo
Hello Ludovic DEPOIX
Can you inform me about the hours of loading? We want to include this information in our teamsite.
Thanks in advance
Ludovic DEPOIX
Its difficult to give a an exact hour of availability . it depend on the volume,source (WP1, PF1 ), date..
If i check July/August data are available in cube around (Paris time)
i will ask for the extraction hours
Pedro Pinto
Aditional Information: the cost centers that has Fix and variable costs of Production and Utilities in node *-Y, BW Fixed Cost query will not show the amiunts in variable cots according to Cost element strucurre XCS-ALL, but will show only according to Cost element strucurre ZRCS-FC