The date of the first day of the cycle appears. To avoid any problems, calculation must remain until 31.12.9999.
The cycle starts with the selection of the materials that are costed. Click on in the column « Parameter » / line « Selection »
STEP 2
A new screen appears
Click on beside Material Type
Enter the Material type :
ZMAT : Finished product & RM & SF
ZVER : Packaging
and execute
STEP 3
In the same screen update the plants:
Click on beside Plant
In tab Exclude single values
Add the plants from SQ00 in tab excludes
STEP 4
To remove Trading Plants (Négoce/NDIR) from WP1 Costing Run the following selections must be performed:
Go to SQ00, user group "Costing", choose the Query "PLANTS" and execute
In case you get an error message saying that your User is not assigned to any User Group, go to Environment -> Work areas and choose Standard area. After go to Edit -> Other User Group -> Costing.
Select Layout /PLNT_CHECK and confirm for your scope if Plants listed are excluded from CK40N parameters.
Conclusion: The Plants should be included/added to the already existing exclude list in CK40N (do not delete the Plants already in the List).
1
2
3
STEP 5
Check Background Processing
and save
The message “Values of variant xxxx” appears
Go back by clicking
STEP 6
Click onin the column « Execute » / line « Selection »