BOMs
The BOM (Bill of Materials) is used to indicate the components of a manufactured product. Site planners are recommended to understand how it is created and modified. In some organizations, the creation of BOM is under responsibility of the production team.
This contains :
- A base quantity
- List of components
- Quantity of each component to produce the base quantity
Transaction layout:
Detailed learning session :
- BOMs creation - slide deck
- BOMs change and display - slide deck
Rate routings
In most PF1 plants, rate routings are used to manage capacity utilization and calculate production costs.
The rate routing allows for declaring production via a cost collector with repetitive manufacturing.
The rate routing contains the following minimum information:
- The resource where the product is produced. This represents the production line and should accurately reflect the reality.
- The production rate: This indicates how fast the production line is operating for that specific material
Transaction layout:
Detailed learning session :
- Rate routings create-change -slide deck
Production version
The production version is the information used by controlling to calculate production costs and also used by the site planner to manage the scheduling. It is a combination of the BOM and the rate routings.
There can be multiple production versions for a single mateiral:
- It could be more than one BOM for one material : if different ingredients can be used to produce the same material. In that case, 2 alternatives BOM’s are created and we need 2 production version
- It could be more than one rate routing for one material : if 2 different production line can produce the same material. In that case, 2 rate routings are created
You need then 4 production versions :
- Alt BOM1 with rate routing 1
- Alt BOM 2 with rate routing 1
- Alt BOM 1 with rate routing 2
- Alt BOM 2 with rate routing 2
Transaction layout :
Detailed training session:
- Plant master data introduction -video
- Production version create-change - slide deck
-> when using Master recipes, production version is create at the same time as the master recipe. This training is to create production version when using rate routings