1. INTRODUCTION
1.1. Objectives and scope of this procedure
This SOP explains how to add new items in an existing contracts for materials
Who uses this document? | What is the nature of the need | ||||
|---|---|---|---|---|---|
User / PREQ creator | Approver | PSR | PS | Goods | Services |
X | X | ||||
1.2. Material groups in scope
- The material groups in scope are all started with ZM.
1.3. Process step described in this procedure and expected end product
End Product
2. STANDARD OPERATING PROCEDURE DESCRIPTION
2.1. Creation of additional lines
# | Main activities | Tips / Best practices | Key points |
1 | Enter transaction ZZMCCONT. |
# | Main activities | Tips / Best practices | Key points |
2 | Enter the contract number that needs to be updated. | ||
3 | Enter the P.Org of the contract. | ||
4 | Enter the vendor number of the contract. | Code VN in partners. | |
5 | Flag 'Test mode' or 'Real Mode'. | First run must be always in test mode to check possible errors and avoid in real mode. | |
6 | Click . | Save the file before editing it. |
# | Main activities | Tips / Best practices | Key points |
7 | Add the material numbers necessary for this contract. | For each material, 1 Excel line will be added. So if 10 new materials need to be added, 10 new Excel lines must be in the finished Excel file before uploading it. | |
8 | Insert the unit price contracted for each material number. | ||
9 | After all the materials have been entered, select the first line.
| ||
10 | Save the file. |
# | Main activities | Tips / Best practices | Key points |
11 | Enter transaction ZZMCCONT again. |
# | Main activities | Tips / Best practices | Key points |
12 | Enter the contract number that needs to be updated. | ||
13 | Enter the P.Org of the contract. | ||
14 | Enter the vendor number of the contract. | Code VN in partners. | |
15 | Flag . | ||
16 | Select the file previously worked on and click upload. | ||
17 | Click . |
# | Main activities | Tips / Best practices | Key points |
18 | If no errors are shown, go back with and run the transaction in |
# | Main activities | Tips / Best practices | Key points |
19 | The number of lines created is shown. | ||
20 | Click on . |
# | Main activities | Tips / Best practices | Key points |
21 | Select the last line shown with your user. | ||
22 | Click |
# | Main activities | Tips / Best practices | Key points |
23 | Select "Display errors only" | If there are several lines to be created (over 100) it is preferable to run the session in background. | |
24 | Click . |
# | Main activities | Tips / Best practices | Key points |
25 | Enter transaction ME33K. |
# | Main activities | Tips / Best practices | Key points |
26 | Enter the contract number and hit Enter. |
# | Main activities | Tips / Best practices | Key points |
27 | In the contract display the number of lines can be confirmed and checked if are according to the request. |
2.2. Maintain Source list
We can link the sourcing of all items present in the Agreement and vendor for a specific plant(s). The system uses the sources of supply to determine to which vendor a purchase requisition created manually or by MRP should be assigned.
2.2.1. Update for only 1 plant
# | Main activities | Tips / Best practices | Key points |
28 | Enter transaction ZZMSOURC. |
# | Main activities | Tips / Best practices | Key points |
29 | Enter the contract number. | ||
30 | Enter the plant for which the source list must be assigned. | ||
31 | Flag "Fixed source" | ||
32 | MRP update must be "1" | ||
33 | Click |
2.2.2. Update for several plants
# | Main activities | Tips / Best practices | Key points |
34 | Enter transaction ZZMSOURA. |
# | Main activities | Tips / Best practices | Key points |
35 | Chose "Online create" in order to make the assignment in realtime | Available options are:
| |
36 | Insert the contract number. | Multiple contracts can be processed at the same time. | |
37 | Enter the P.Org | ||
38 | Enter the plants on which the source assignment must be done. | ||
39 | Flag the Fixed Source for MRP field | ||
40 | MRP update must be "1". | ||
41 | Click . |
# | Main activities | Tips / Best practices | Key points |
42 | The list of plants for which the source was assigned is shown. |
3. REFERENCES
This procedure refers to the documents listed in the table below:
File name | Document type | Document title |
List of SOPS related to PRO 20.1 | PRO | xxxx |