| Table of Contents |
|---|
General presentation
Objective of the application
CBS stands for 'Corporate Business Services'
CBS is a dedicated Reporting tool built on SAP BW module. It allow to analyse Functions fixed costs on cost centers and on project.
Usage information
Around 200 users have access to CBS applications. Those users are worldwide and most of them are function controllers.
History
Project done in 2012. It was the first project in BW mixing data from WP1 and PF1/PI1 systems.
Roles & Access
Roles and access
|
Access Management
| Panel | ||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| ||||||||||||
List of application role + menu role and explanation if we have several applications role with specials rules.
CBS is part of the Controlling application (Info Area AREA_F_CO in BW) |
...
| Role Code | Role Description | Explanation |
|---|---|---|
| ZR_RCS_CA_M23 | CBS - Functions costs | Role menu |
| ZBI_RCS_CO_A11 | CBS Function Costs Reporting Analysis - End User role | End user role for Function reporting |
| ZBI_RCS_CO_A21 | CBS Project costs Reporting Analysis - End User role | End user role for Project reporting |
Authorization objects
...
|
...
DataFlow
Overview
| Widget Connector | ||
|---|---|---|
|
| Widget Connector | |
|---|---|
|
|
Functional and Technical rules on Workbench + Reporting
Rules & Explanations
|
List of cubes MPR_FC001:
| Cube | Description | Last month where new data was loaded in cube (updated at 09.19.2023) |
|---|---|---|
| CUB_FC007 | Fixed costs Analysis (External data) | 06.2021 |
| CUB_FC002 | Fixed costs Analysis Acetow | 12.2017 |
| CUB_FC004 | Fixed costs Analysis CICC | 09.2023 |
| CUB_FC003 | Fixed costs Analysis PIM | - |
| CUB_FC006 | Fixed costs Analysis Rhodia | 09.2023 |
| CUB_FC005 | Fixed costs Analysis Solvay | 09.2023 |
List of provider MPR_FC002:
| Cube | Description | Last month where new data was loaded in cube (updated at 09.19.2023) |
|---|---|---|
| ODSACCA9 | Cost Center: Actual Costs through Delta Extraction Rhodia S | 01.2014 |
| ODS_CCA9 | Cost Centers: Actual Costs Through Delta Extraction | 09.2023 |
| ODS8CCA9 | Cost Centers: Actual Costs Through Delta Extraction - Acetow | 02.2019 |
| ODS7CCA9 | Cost Centers: Actual Costs Through Delta Extraction - CICC | 09.2019 |
| ODS6CCA9 | Cost Centers: Actual Costs Through Delta Extraction - Solvay | 09.2023 |
| ODS_OPA6 | ODS_OPA6Orders: Actual Costs Through Delta Extraction | 09.2023 |
| ODS8OPA6 | Orders: Actual Costs Through Delta Extraction - Acetow | 02.2019 |
| ODS7OPA6 | Orders: Actual Costs Through Delta Extraction - CICC | 01.2013 |
| ODS6OPA6 | Orders: Actual Costs Through Delta Extraction - Solvay | 09.2023 |
| ODS_WBS6 | WBS Element - Actual Costs trough Delta Extraction | 09.2023 |
| ODS6WBS6 | WBS Element - Actual Costs trough Delta Extraction - Solvay | 09.2023 |
Objective of the application
CBS stands for 'Corporate Business Services'
CBS is a dedicated Reporting tool built on SAP BW module. It allow to analyse Functions fixed costs on cost centers and on project.
History
Project done in 2012. It was the first project in BW mixing data from WP1 and PF1/PI1 systems.
Technical Rules on Workbench
Master data management
In the beginning of the project, we discovered that some objects may have same values but can be totally different in the ERP systems.
...
We have created a new catalog IOCC_MD_ID in the info objects where we will store the info objects with the System ID in key
Functional and Technical rules
Cost center hierarchies
Click on the Cost Center Hiearchies page.
Cost element hierarchies
Click on the Cost Element Hiearchies page.
Family of the WBS element
Click on the Family assignment page.
Usage of Responsible cost centers and Cost centers
During the month, costs of WBS elements and CO orders are managed at the WBS or Order level.
Example below (theorical) :
...
At 31.07.2016, query end of the month will display the 300€ costs on cost center STELLAR and query during the month will display it on resp cc IT-BW
Position of the person responsible and user responsible of the cost centers
The position of the person responsible (c_posit) corresponds to a position in the SRM7 organisational structure. It is coming from the person responsible field (verak) of the cost center MD in WP1/PF1 which not always contains a position (some companies doesn't use SRM7 for purchasing), so we check the existence of the position in c_posit MD before to update it in the BW cost center MD (C_COSTCTR).
...
The BIP login of the position in c_posit MD is updated from SRM7, using the Function Module ZWPU_GET_POSITIONS_CC in order to share the same rule with ECC reports (ZWFA119 for WP1 and ZZR_WPUR043 for PF1). FM ZWPU_GET_POSITIONS_CC checks the validity of the user in SRM7, in consequence, even when the organisational structure shows a user for a position, the user could be undetermined in the FM if not valid. If the FM finds multiple users for a position, which is not normal, the attribute BIP login of the position in BW is set to "ERROR_MULTI".
Technical
...
rules
...
PS PEC reporting referential.xlsx
Since the service pack update cause the H/S flag of data source 0CO_OM_CCA_9 change the concept of +/- sign (Note 65075), which cause the sign in WP1 was opposite. For PF1, we didn't apply the service pack yet (as of Nov 2021) because we afraid that it will impact to many program.
...
We can specific the company code by table TVARVC and maintain the list via tcode TVARVC in WP1. :
BW and ERP systems
- WBD (BW Development) is linked to WD1 (RCS development), DI1 (CICC development), DF1 (Solvay development), TS2 (Acetow Test)
- WBQ (BW Quality) is linked to WQ1 (RCS quality), QI1 (CICC quality), QF1 (Solvay quality) and TS2 (Acetow Test)
- WBP (BW Production) is linked to WP1 (RCS Production), PI1 (CICC Production), PF1 (Solvay Production), RHO (Acetow Production)
- PIM system is not used anymore
Reporting
Queries End User Documentation
Link to user guide
https://drive.google.com/file/d/1h4RMrmL5MR0plRCW0aqKelxvNKrVw-7J/view
Main queries
Dependencies with other applications
CBS applications is dependant with
- FC2 Fixed Costs (obsolete) now replaced by FC GBU Fixed costs
- PS / CAPEX Project costs (common DSO)
- CO Profitability (comme DSO ODS_OPA06)
Data
...
loading
Info providers and objects loaded
...
In the Excel files attached Function cost reporting referential.xls and PS PEC reporting referential.xls you will find a list of all objects included in:
- Data Sources used for master datas, texts, DSO
- DSO
- Cube
- Multi providers
Loading frequency
CBS is loaded every working day starting at 0:00 am (Paris time) and finishing around * :00 am (Paris time)*
Average performance
RSP_COOM CO_OM_OPA / WBS - delta extraction for RCS data: 2h
...
MPR_FC001
| Process chain | Provider loaded | Frequency | Time start | Duration |
|---|---|---|---|---|
| PC_FC_CYTEC_003 | CUB_FC007 | At demand (transaction) | ||
| RSP_COOM_OTHER | CUB_FC005 CUB_FC002 | Daily (not week-end) | 2:30 am | 15 min |
| RSV_COOM_CCA_ |
...
| OTHER | CUB_FC005 CUB_FC002 CUB_FC004 | Daily (not saturday) | 2:00 am | 15 min |
| PC_FC_D4 | CUB_FC006 | Working Day 2, 3 and 4 | 1 pm 8 pm | 5 min |
| RSP_COOM | CUB_FC006 | Daily (not saturday) | 1:15 am | 20 min |
| RPC_FC2_BUDGET_1 | CUB_FC006 | Wednesday | 7 am | 1h30 |
| PC_FIXED_COST_BUDGET | CUB_FC006 | Working Day 2, 3 and 4 | 1 pm 8 pm | 5 min |
MPR_FC002:
| Process chain | Provider loaded | Frequency | Time start | Duration |
|---|---|---|---|---|
| PC_FC_D4 | ODS_CCA9 ODS_OPA6 | Working Day 2, 3 and 4 | 1 pm 8 pm | 5 min |
| RSV_COOM_CCA | ODS_CCA9 | daily 1:30 am | 10min | |
| RSV_COOM_CCA_OTHER | ODS6CCA9 ODS6OPA6 | Daily (not saturday) | 2:00 am | 15 min |
| RSP_COOM | ODS_OPA6 ODS_WBS6 | Daily (not week-end) | 2:30 am | 15 min |
| RSP_COOM_OTHER | ODS6WBS6 | Daily (not week-end) | 2:30 am | 15 min |
Record Keeping
We have data since beginning of 2012 and we never made clean-up.
Main functionnalities
Jump query available
Data Quality Control
Data come from SAP system. To compare data between BW and sources systems, check propagation layers.
Operational Documentation
Procedures
<Describe the recurring procedures needed to operate the application (eg. start/pause/terminate/restart the app processes, data preparation, data ingestion, ETL, data visualization, data export, other manual activities)>
Scheduling
<Describe the scheduling in place for the application (eg. existing jobs, trigger time/event based, dependencies)>
Monitoring
<Describe the monitoring checks to confirm the application is performing well (eg. check the overall status, check performance metrics like runtime/data volume/memory/disk/CPU, maintain and react to alerts/notifications)>
Error Handling
<Describe how to handle errors (eg. error codes, description and respective resolution, alert users)>
Known Bugs
<List the existing bugs, its criticity, workarounds and resolution plan.>
Roadmap
<List past & future evolutions for the application (including links to MED/FSD/TSD)>
Record Keeping
We have data since beginning of 2012 and we never made clean-up.
Reporting
Queries End User Documentation
Link to user guide
https://drive.google.com/open?id=0B_p_Afe8sjVlZ0pxa1psVEFwNDQ
Main queries
BW_QRY_MPR_FC001_0001 CBS - Functions - end of month (Core query)
BW_QRY_MPR_FC001_0002 CBS - Functions by Companies - end of month (Core query)
BW_QRY_MPR_FC001_0003 CBS - Functions - during month (Core query)
BW_QRY_MPR_FC001_0004 CBS - Functionsby Companies - during month (Core query)
BW_QRY_MPR_FC001_0005 CBS - Synthesis of the Functions (Core query)
Main functionnalities
Jump query available
Broadcast
No broadcast
Maintenance
Known bugs
No known bug
Example of tickets
- 3729: 0PROFIT_CTR not updated
- 22045: Ask new report
Recurring procedure
No recurring procedure
Planned Evolution
- Remove old data: Only keep the 5 last years in the cubes in order to make the cube lighter and gain space in BWA.
- Fixed Cost project: A project is in progress to have fixed costs reporting by plant and GBU. This project will be finished end of july.
This project is a mix between CBS and COPA in order to provide fixed cost reporting by plant and GBU. The objective is also to replace actual fixed cost application for Rhodia legacy FC2.
For this project, we have created specific info areas
We have created MPR_FC003 for this purpose. This multi provider has same cubes as CBS application and one cube from COPA application.
For this multi provider we have 2 authorization object: C_RESP_CC__C_RPLANT Responsible Plant and C_RESP_CC__CPFCTR1_2.
We have also 3 new queries