Quantity of production lost because of breakdowns or production stoppages caused by maintenance (OEE C2 and C4)
2/ Objective / Target
The set of strategic indicators has three main objectives: - Verification of the effectiveness of maintenance processes - Comparisons between plants independently from the business - Comparisons with external organizations
3/ Formula
Direct impact of maintenance on industrial performance (in TO) = OEE category 2 losses + OEE category 4 losses
4/ Frequency
Weekly
5/ SAP extraction and detailed calculation
Manual input of OEE losses from production report (Site template > Yearly tab)